In: Economics
3. Restricted maximization of three activities Bma = Bmb = Bmc
Pa Pb Pc
Conditions: that the marginal profit per dollar is the same for the three activities and that the assigned budget is not exceeded.
. A firm wants to maximize its benefits with three activities, whose costs are x = 2, y = 4, z = 6. The budget allocated is $ 46.00 Determine the optimal levels of x, y,z
Act. |
Bmx |
BMx/px |
Costo x |
Bmy |
Bmy/py |
Costo y |
Bmz |
Bmz/pz |
costoz |
1 |
16 |
40 |
54 |
||||||
2 |
14 |
36 |
48 |
||||||
3 |
12 |
32 |
42 |
||||||
4 |
10 |
24 |
36 |
||||||
5 |
8 |
20 |
24 |
||||||
6 |
6 |
16 |
18 |
||||||
7 |
4 |
12 |
12 |
||||||
8 |
2 |
8 |
6 |
Determine the optimal levels for the three activities
Activities |
of x |
Cost of x |
|
Activities of y
|
Cost of y |
||
Activities of z
|
Costo of Z |
||
Total |
The equi marginal principle (production version) states that at the producers will maximize their output by allocating their cost such a way that the marginal product per dollar for the last unit of each input employed will be same for both the inputs. In production the minimization of cost requires:
The table is completed as below
ACT | BMx | BMx/Px | Costto x | Bmy | Bmy/Py | Costto y | BMz | BMz/Pz | Costto z |
1 | 16 | 8 | 2 | 40 | 10 | 4 | 54 | 9 | 6 |
2 | 14 | 7 | 4 | 36 | 9 | 8 | 48 | 8 | 12 |
3 | 12 | 6 | 6 | 32 | 8 | 12 | 42 | 7 | 18 |
4 | 10 | 5 | 8 | 24 | 6 | 16 | 36 | 6 | 24 |
5 | 8 | 4 | 10 | 20 | 5 | 20 | 24 | 4 | 30 |
6 | 6 | 3 | 12 | 16 | 4 | 24 | 18 | 3 | 36 |
7 | 4 | 2 | 14 | 12 | 3 | 28 | 12 | 2 | 42 |
8 | 2 | 1 | 16 | 8 | 2 | 32 | 6 | 1 | 48 |
From the figure above, it can be seen that the marginal profit is same at 4 levels. For marginal profit level 8,6,4, and 2. The corresponding level of act is summarize in the table below
Bmi/Pi | x | y | z | Cost |
8 | 1 | 3 | 2 | 26 |
6 | 3 | 4 | 4 | 46 |
4 | 7 | 6 | 5 | 68 |
2 | 8 | 8 | 7 | 90 |
From the table above, the cost constraint is satisfied for marginal profit level 6. Then the activity level and the cost is given as
Activities |
of x 3 |
Cost of x |
6 |
Activities of y 4
|
Cost of y |
16 | |
Activities of z 4
|
Costo of Z |
24 | |
Total |
46 |