In: Finance
You are a manager at Percolated Fiber, which is considering expanding its operations in synthetic fiber manufacturing. Your boss comes into your office, drops a consultant's report on your desk, and complains, "We owe these consultants $ 1.1 million for this report, and I am not sure their analysis makes sense. Before we spend the $ 21.7 million on new equipment needed for this project, look it over and give me your opinion." You open the report and find the following estimates (in millions of dollars):
Earnings Forecast | 1 | 2 | . . . | 9 | 10 |
Sales Revenue | 26 | 26 | 26 | 26 | |
- Cost of Goods Sold | 15.6 | 15.6 | 15.6 | 15.6 | |
Gross Profit | 10.4 | 10.4 | 10.4 | 10.4 | |
- General, Sales and Administrative expenses | 1.736 | 1.736 | 1.736 | 1.736 | |
- Depreciation | 2.17 | 2.17 | 2.17 | 2.17 | |
Net Operating Income | 6.494 | 6.494 | 6.494 | 6.494 | |
- Income Tax | 2.273 | 2.273 | 2.273 | 2.273 | |
Net Income | 4.221 | 4.221 | 4.221 | 4.221 |
All of the estimates in the report seem correct. You note that the consultants used straight-line depreciation for the new equipment that will be purchased today (year 0), which is what the accounting department recommended. They also calculated the depreciation assuming no salvage value for the equipment. The report concludes that because the project will increase earnings by $ 4.221 million per year for 10 years, the project is worth $ 42.1 million. You think back to your glory days in finance class and realize there is more work to be done!
First, you note that the consultants have not included the fact that the project will require $ 14.3 million in working capital up front (year 0), which will be fully recovered in year 10. Next, you see they have attributed $ 1.736 million of selling, general, and administrative expenses to the project, but you know that $ 0.868 million of this amount is overhead that will be incurred even if the project is not accepted. Finally, you know that accounting earnings are not the right thing to focus on!
a. Given the available information, what are the free cash flows in years 0 through 10 that should be used to evaluate the proposed project?
b. If the cost of capital for this project is 10 %, what is your estimate of the value of the new project?
a) The free cash from 0 to 10 years are calculated are as follows-
(in million of dollars)
Earning Forecast | 0 | 1 | 2 | ,,, | 9 | 10 | |
Cost of new equipment | (21.7) | ||||||
Change in Working Capital | (14.3) | 14.3 | |||||
|
26 | 26 | 26 | 26 | |||
- Cost of Goods Sold | 15.6 | 15.6 | 15.6 | 15.6 | |||
Gross Profit | 10.4 | 10.4 | 10.4 | 10.4 | |||
-General Sales & Adm. Expenses | 0.868 | 0.868 | 0.868 | 0.868 | |||
- Depreciation | 2.17 | 2.17 | 2.17 | 2.17 | |||
Net operating Income | 7.362 | 7.362 | 7.362 | 7.362 | |||
- Income Tax | 2.5767 | 2.5767 | 2.5767 | 2.5767 | |||
Net Income (A) | 4.7853 | 4.7853 | 4.7853 | 4.7853 | |||
Depreciation (B) | 2.17 | 2.17 | 2.17 | 2.17 | |||
Cash flows (A+B) | 6.9553 | 6.9553 | 6.9553 | 6.9553 | |||
Cost of Machine plus change in Net Working Capital (C) | (36) | 14.3 | |||||
Total Cash Flows (A+B+C) | (36) | 6.9553 | 6.9553 | 6.9553 | 21.2553 |
b) If the cost of Capital is 10%, the estimated value of project is calculated as follows -
= -36+6.9553*5.757+21.2553*0.385
= -36+40.01+8.18
= $12.19 million
The NPV of the project is $12.19million