In: Accounting
QUESTION 1 - Please show work for understanding of problem.
New Image Sports uses a WEIGHTED AVERAGE process-costing system.
For March, the company had the following activities:
Beginning work-in-process inventory 6,000 units
Units placed in production 24,000 units
Units completed and Transferred Out 25,000 units
Cost of beginning work in process -Materials $ 3,000
Cost of beginning work in process- Conversion Costs
$ 2,000
Direct material costs added in March $18,000
Conversion costs added in March $13,750
Direct materials are placed into production at the beginning of the process. Ending Work in Process is 60% completed as to conversion costs.
1. The Total Equivalent Units would be __________ for Direct
Materials and ________ for Conversion Costs.
2. The Cost per Equivalent Unit would be ________ for Direct Materials and _________ for Conversion Costs. Round Conversion Costs to 4 decimals.
3. The Total Cost of the 25,000 units completed and transferred out is ___________ .
4. The Total Cost of Ending Work In Process is _________ of which ________ is Direct Materials and ________ is Conversion Costs.
1) equivalent units
Particular | material | conversion |
Units completed and transferred out |
(25000×100%) 25000 |
(25000×100%) 25000 |
Ending inventory(note below) |
(5000×100%) 5000 |
(5000×60%) 3000 |
Equivalent units | 30000 | 280000 |
Note: ending inventory = beginning inventory+ units placed in production - units completed and transferred out
Ending inventory = 6000+24000 - 25000 = 5000 units
equivalent units of material = 30000 units
equivalent units of conversion = 28000 units
2) cost per Equivalent unit
Particular | material | conversion |
(a) cost of beginning inventory | $3000 | $2000 |
(b) cost added during the month | $18000 | $13750 |
(C) total cost (a+b) | $21000 | $15750 |
(d) equivalent units | 30000 | 28000 |
Cost per Equivalent unit (c/d) | $0.70 | $0.5625 |
Cost per Equivalent unit material = $0.70
Cost per Equivalent unit conversion = $0.5625
3) cost of units completed and transferred out
Material = 25000×$0.70 = $17500
Conversion = 25000×$0.5625 = $14062
total cost of units completed and transferred out = $17500+$14062= $31562
4) ending inventory cost
Material = 5000×$0.70 = $3500
conversion = 3000×$0.5625= $1688
total cost of ending inventory = $3500 +1688= 5188