Marvel Parts, Inc., manufactures auto accessories. One of the company’s products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,035 hours each month to produce 2,070 sets of covers. The standard costs associated with this level of production are:
Total | Per Set of Covers |
||||
Direct materials | $ | 31,878 | $ | 15.40 | |
Direct labor | $ | 6,210 | 3.00 | ||
Variable manufacturing overhead (based on direct labor-hours) | $ | 4,347 | 2.10 | ||
$ | 20.50 | ||||
During August, the factory worked only 500 direct labor-hours and produced 1,700 sets of covers. The following actual costs were recorded during the month:
Total | Per Set of Covers |
||||
Direct materials (5,000 yards) | $ | 25,500 | $ | 15.00 | |
Direct labor | $ | 5,440 | 3.20 | ||
Variable manufacturing overhead | $ | 4,080 | 2.40 | ||
$ | 20.60 | ||||
At standard, each set of covers should require 2.0 yards of material. All of the materials purchased during the month were used in production.
Required:
1. Compute the materials price and quantity variances for August.
2. Compute the labor rate and efficiency variances for August.
3. Compute the variable overhead rate and efficiency variances for August.
(Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
Solution :
1. | Material Price Variance | $ 13,000 | F |
Material Quantity Variance | $ 12,320 | U | |
2. | Labor Rate Variance | $ 2,440 | U |
Labor Efficiency Variance | $ 2,100 | F | |
3. | Variable OH Rate Variance | $ 1,980 | U |
Variable OH Efficiency Variance | $ 1,470 | F |
Working :
1. Material Variances
Direct Material Price Variance = (SR - AR) * AQ
= [($ 15.4 / 2) - ($ 25,500 / 5,000)] * 5,000
= [$ 7.70 - 5.10] * 5,000
= $ 13,000 Favorable
Direct Material Quantity Variance = (SQ - AQ) * SR
= [(1700 * 2) - 5,000] * $ 7.70
= [3,400 - 5,000] * $ 7.70
= $ 12,320 Unfavorable
2. Direct Labor Variances
Direct Labor Rate Variance = (SR - AR) * AH
= [($ 6,210 / 1,035) - ($ 5,440 / 500)] * 500
= [($ 6.00 - $ 10.88] * 500
= $ 2,440 Unfavorable
Direct Labor Efficiency Variance = (SH - AH) * SR
= [(1,700 * 0.50*) - 500] * $ 6.00
= [850 - 500] * $ 6.00
= $ 2,100 Favorable
* Standard Hour per Cover = 1,035 / 2,070 = 0.50 per Hour
3. Variable OH Variances
Variable OH Rate Variance = (SR - AR) * AH
= [($ 4,347 / 1,035) - ($ 4,080 / 500)] * 500
= [($ 4.20 - $ 8.16] * 500
= $ 1,980 Unfavorable
Variable OH Efficiency Variance = (SH - AH) * SR
= [(1,700 * 0.50) - 500] * $ 4.20
= [850 - 500] * $ 4.20
= $ 1,470 Favorable
Please vote up and write your doubts in comment section. Would be glad to help you further.