In: Accounting
Primare Corporation has provided the following data concerning last month’s manufacturing operations.
Purchases of raw materials | $ | 31,000 |
Indirect materials used in production | $ | 4,510 |
Direct labor | $ | 58,100 |
Manufacturing overhead applied to work in process | $ | 88,600 |
Underapplied overhead | $ | 4,170 |
Inventories | Beginning | Ending | ||
Raw materials | $ | 10,800 | $ | 19,700 |
Work in process | $ | 54,700 | $ | 65,000 |
Finished goods | $ | 34,700 | $ | 43,500 |
Required:
1. Prepare a schedule of cost of goods manufactured for the month.
2. Prepare a schedule of cost of goods sold for the month. Assume the underapplied or overapplied overhead is closed to Cost of Goods Sold.