In: Finance
Question 3
Consider the following two mutually exclusive projects. The required rate of return is 10%.
Part A: Calculate the NPV for each project.
Year | Project A | Project B |
0 |
-$100,000 |
-$100,000 |
1 |
30,000 |
80,000 |
2 | 40,000 | 20,000 |
3 | 60,000 | 20,000 |
Part B: Calculate the IRR for each project.
Part C: Calculate the payback period for each project.
Part D: Suppose you were the manager deciding between these two projects. Would you prefer to use the payback period decision rule or the NPV decision rule? Why – use your solutions to parts A and C to support your answer?
PART A | NPV: | |||||
PROJECT A: | ||||||
Year | Cash flow | PVIFA at 10% | PV at 10% | |||
0 | -100000 | 1.00000 | -100000 | |||
1 | 30000 | 0.90909 | 27273 | |||
2 | 40000 | 0.82645 | 33058 | |||
3 | 60000 | 0.75131 | 45079 | |||
NPV OF PROJECT A = | 5409 | |||||
PROJECT B: | ||||||
Year | Cash flow | PVIFA at 10% | PV at 10% | |||
0 | -100000 | 1.00000 | -100000 | |||
1 | 80000 | 0.90909 | 72727 | |||
2 | 20000 | 0.82645 | 16529 | |||
3 | 20000 | 0.75131 | 15026 | |||
NPV OF PROJECT B = | 4282 | |||||
PART B | IRR: | |||||
IRR is that discount rate which gives 0 NPV. I has to be found out by | ||||||
trial and error using different discount rates. The workings are given below: | ||||||
PROJECT A: | ||||||
Year | Cash flow | PVIFA at 13% | PV at 13% | PVIFA AT 12% | PV AT 12% | |
0 | -100000 | 1.00000 | -100000 | 1.00000 | -100000 | |
1 | 30000 | 0.88496 | 26549 | 0.89286 | 26786 | |
2 | 40000 | 0.78315 | 31326 | 0.79719 | 31888 | |
3 | 60000 | 0.69305 | 41583 | 0.71178 | 42707 | |
-542 | 1380 | |||||
IRR lies between 13% and 12%. The exact value can be found out by | ||||||
simple interporation as below: | ||||||
IRR = 12+1380/(1380+542) = | 12.72% | |||||
PROJECT B: | ||||||
Year | Cash flow | PVIFA at 13% | PV at 13% | PVIFA AT 14% | PV AT 14% | |
0 | -100000 | 1.00000 | -100000 | 1.00000 | -100000 | |
1 | 80000 | 0.88496 | 70796 | 0.87719 | 70175 | |
2 | 20000 | 0.78315 | 15663 | 0.76947 | 15389 | |
3 | 20000 | 0.69305 | 13861 | 0.67497 | 13499 | |
320 | -936 | |||||
IRR lies between 13% and 14%. The exact value can be found out by | ||||||
simple interporation as below: | ||||||
IRR = 13+320/(320+936) = | 13.25% | |||||
PART C: | PAYBACK PERIOD: | |||||
PROJECT A: | ||||||
Year | Cash flow | Cumulative cash flow | ||||
0 | -100000 | -100000 | ||||
1 | 30000 | -70000 | ||||
2 | 40000 | -30000 | ||||
3 | 60000 | 30000 | ||||
Payback period = 2+30000/60000 = | 2.5 years | |||||
PROJECT B: | ||||||
Year | Cash flow | Cumulative cash flow | ||||
0 | -100000 | -100000 | ||||
1 | 80000 | -20000 | ||||
2 | 20000 | 0 | ||||
3 | 20000 | 20000 | ||||
Payback period = 2.0 years | ||||||
PART D: | DECISION: | |||||
The results obtained above are tabulated below: | ||||||
Project A | Project B | |||||
NPV | $ 5,409 | $ 4,282 | ||||
IRR | 12.72% | 13.25% | ||||
Paback period | 2.5 years | 2.0 years | ||||
Payback favors Project B as it has lower payback. | ||||||
IRR also favors Project B as it has higher IRR. | ||||||
But NPV favors Project A which has higher NPV. | ||||||
For making a decision, I would prefer the NPV rule. | ||||||
The reason is that payback period has the following drawbacks: | ||||||
*It does not take into account the time value of money. | ||||||
*It does not consider the cash flows for the entire life of the | ||||||
project. | ||||||
As against this, the NPV has the following merits: | ||||||
*It considers the time value of money. | ||||||
*It considers all the cash flows during the life of the | ||||||
projects. | ||||||
*It gives directly the dollar addition to the present worth of | ||||||
the shareholders, which is the goal financial decision making. |