Question

In: Accounting

4. Suppose that, over a period, the average raw material unit cost was $ 4.85 and...

4. Suppose that, over a period, the average raw material unit cost was $ 4.85 and the average conversion cost was $ 9.15. At the end of the period, there were 600 units in process, with 100% of the raw material and 65% of the conversion costs. How much is the balance of the inventory of goods in process at the end of the period?
to. $ 6,479 b. $ 8,400 c. $ 5,460 d. $ 5,850
5. A company considers it normal for 5% of the units that are completed to be spoilage and transferred to finished goods inventory. In the most recent period, 5,000 units were completed and transferred and 350 units were damaged. How is the cost of damaged units accounted for?
to. The cost of the 350 units is added to the cost of the 5,000 units transferred.
b. The cost of the 350 units is charged to expense for the period.
c. The cost of 250 units is added to the cost of the 5,000 units transferred and the cost of 100 units is charged to expense for the period.
d. The cost of the 350 units is recognized in a separate damaged goods inventory account.
8. A production system that combines “Job costing” and “Process costing” features is known as:
to. Operations costing c. Job-process costing
b. Backflush costing d. There is no such system

Solutions

Expert Solution

4. Given information

Average raw material unit cost 4.85

Average conversation cost 9.15

At end of period 600 units are in process

How much is the balance of inventory of goods in process at the end of the period?

Balance of inventory of goods in process at the end of the period =average raw material cost ×units in process×percantage of completion +average conversation cost×units in process×percentage of completion

= 4.85 × 600 × 100%

= $ 6479

5.In question mentioned normally 5% of units that are completed to be spoilage and transferred to finished good inventory.

Therefore it can be treated as normal loss,

Normal loss means that loss which is inherent in the processing operations. It can be expected or anticipated in advance i.e. at the time of estimation.The cost of normal loss is considered as part of the cost of production in which it occurs.

Therefore cost of the 350 units to be added to the cost of 5000 units transferred


Related Solutions

Rustica Ltd. uses one raw material for one of their products. The standard cost per unit...
Rustica Ltd. uses one raw material for one of their products. The standard cost per unit at the beginning of the year was £28, made up as follows: Standard material cost per unit = 7 kg per unit @ £4 per kg = £28 In the middle of the year, the supplier had changed the specification of the material slightly due to problems experienced in the country of origin, so that the standard had to be revised as follows: Standard...
Prepare a raw material inventory card for Material A using FIFO and Weighted Average methods of...
Prepare a raw material inventory card for Material A using FIFO and Weighted Average methods of inventory costing for the following transactions: June 1 Opening Balance                    50 units @ $5.00 June 2 Purchases                              40 units @ $4.50 June 3 Issues                         70 units June 4 Purchases                              35 units @ $4.00 June 5 Issues                         45 units Prepare the journal entry necessary to charge the raw material issued to the production process.
Suppose that chemical X is manufactured using a raw material B that is available from a...
Suppose that chemical X is manufactured using a raw material B that is available from a location ... Suppose that chemical X is manufactured using a raw material B that is available from a location called the "mine." Production of one ton of X requires 1/3 of a ton of B. A firm called X ENTERPRISES, which has a contract to deliver 30 tons of X to a location called the "market," is trying to decide where to locate its...
A company produces six products in the following manner. Each unit of raw material purchased yields...
A company produces six products in the following manner. Each unit of raw material purchased yields 4 units of product 1, 2 units of product 2, and 1 unit of product 3. Up to 1200 units of product 1 can be sold and up to 300 units of product 2 can be sold. Demand for products 3 and 4 is unlimited. Each unit of product 1 produced from raw material can be sold or processed further. Each unit of product...
During the month December the company procured raw material worth OMR 150,000.During this period the company...
During the month December the company procured raw material worth OMR 150,000.During this period the company has undertaken different jobs. The factory overhead rate is estimated at 130% of direct labour cost but actual factory overhead incurred is OMR 68,000. The company purchased a machinery on 01.01.2019 at OMR 500,000 to be depreciated at 10% p.a. Other important information is given below: Jobs completed No:301,303,304,305 and 306 Job no. 301,303,304 and 305were shipped and customers were billed for OMR 60,000,...
Calculate the cost per equivalent unit of material and conversion cost for January - using the...
Calculate the cost per equivalent unit of material and conversion cost for January - using the Weighted Average Approach Units Materials Conversion Work in process January 1 2,500 50% 35% Work in process January 31 45% 25% Materials cost in work in process January 1 $25,000 Conversion costs in work in process January 1 $10,000 Units started in production 12,000 Units transferred to the next department 8,000 Materials cost added during January $20,000 Conversion costs added during January $7,500 Complete...
Q3) Level of Activity = 1,040,000 units Selling Price = PKR 20 per unit Raw Material...
Q3) Level of Activity = 1,040,000 units Selling Price = PKR 20 per unit Raw Material Cost = PKR 8 per unit Labor Cost = PKR 3 per unit Overhead Cost = PKR 6 per unit Raw Material in Stock = 4 weeks Processing Time = 2 weeks Finished Goods in stock = 3 weeks Credit received from customer is 8 weeks Credit received from supplier is 6 weeks Delay in payment of wages is 4 weeks Delay in payment...
Standard cost information: Standard Quantity / Unit Standard Price Standard Cost / Unit Direct Material 2...
Standard cost information: Standard Quantity / Unit Standard Price Standard Cost / Unit Direct Material 2 $0.75 $1.50 Direct Labor 5 $0.35 $1.75 Variable Overhead 3 $1.20 $3.60 Actual cost information: Total Actual Used Total Actual Cost Direct Material 19,500 $19,500 Direct Labor 34,500 $15,750 Variable Overhead 18,000 $22,000 Do not enter dollar signs or commas in the input boxes. Round all Unit values to 2 decimal places. Round all other answers to the nearest whole number. Enter all variances...
A company located on the sea has the following cost sheet: Cost per unit GH₵ Raw...
A company located on the sea has the following cost sheet: Cost per unit GH₵ Raw Materials 60 Direct Labour 20 Overheads       40 Total Cost      120 Profit             20 Selling Price 140 The following is also made available • Average raw material in stock is equivalent to 30days • Average material in process is 15 days • Credit all owned by suppliers is 30days • Time lag in payment of wages is 10 days • Time lag in...
Illustrate the per unit cost graph. You must include average total cost, average fixed cost, average...
Illustrate the per unit cost graph. You must include average total cost, average fixed cost, average variable cost and marginal cost.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT