Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work such as removal of asbestos insulation around heating pipes in older homes and nonroutine work such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work and should bear higher customer charges. The estimator sums up his position in this way: “My job is to measure the area to be cleared of asbestos. As directed by top management, I simply multiply the square footage by $3.60 to determine the bid price. Since our average cost is only $2.85 per square foot, that leaves enough cushion to take care of the additional costs of nonroutine work that shows up. Besides, it is difficult to know what is routine or not routine until you actually start tearing things apart.”

     To shed light on this controversy, the company initiated an activity-based costing study of all of its costs. Data from the activity-based costing system follow:

  Activity Cost Pool                Activity Measure Total Activity           
  Removing asbestos Thousands of square feet 750 thousand square  feet
  Estimating and job setup Number of jobs 400 jobs
  Working on nonroutine jobs Number of nonroutine jobs 100 nonroutine jobs
  Other (costs of idle capacity and
     organization-sustaining costs)
None    

Note: The 100 nonroutine jobs are included in the total of 400 jobs. Both nonroutine jobs and routine jobs require estimating and setup.

  Costs for the Year
  Wages and salaries $ 460,000
  Disposal fees 862,000
  Equipment depreciation 104,000
  On-site supplies 66,000
  Office expenses 360,000
  Licensing and insurance 560,000
  Total cost $ 2,412,000
  Distribution of Resource Consumption Across Activities
Removing Asbestos Estimating and Job Setup Working on Nonroutine Jobs Other Total
  Wages and salaries 50 % 15 % 20 % 15 % 100 %
  Disposal fees 70 % 0 % 30 % 0 % 100 %
  Equipment depreciation 50 % 10 % 15 % 25 % 100 %
  On-site supplies 60 % 30 % 10 % 0 % 100 %
  Office expenses 15 % 35 % 20 % 30 % 100 %
  Licensing and insurance 25 % 0 % 60 % 15 % 100 %
Required:

   

1.

Perform the first-stage allocation of costs to the activity cost pools.

     


2. Compute the activity rates for the activity cost pools.

      


3.

Using the activity rates you have computed, determine the total cost and the average cost per thousand square feet of each of the following jobs according to the activity-based costing system. (Round the "Average cost" to 2 decimal places.)

   

a. A routine 1,000-square-foot asbestos removal job.

         


b. A routine 2,000-square-foot asbestos removal job.

        


c. A nonroutine 2,000-square-foot asbestos removal job.

         

Solutions

Expert Solution

1Perform the first-stage allocation of costs to the activity cost pools.

Removing Asbestos Estimating and Job Setup Working on Nonroutine Jobs Other Total
Wages and salaries 230000 69000 92000 69000 460000
Disposal fees 603400 0 258600 0 862000
Equipment depreciation 52000 10400 15600 26000 104000
On-site supplies 39600 19800 6600 0 66000
Office expenses 54000 126000 72000 108000 360000
Licensing and insurance 140000 0 336000 84000 560000
Total 1119000 225200 780800 287000 2412000

2

Compute the activity rates for the activity cost pools.

Total Cost Total Activity Activity Rate
Removing Asbestos 1119000 750 1492 Per thousand square feet
Estimating and Job Setup 225200 400 563 Per jobs
Working on Nonroutine Jobs 780800 100 7808 Per nonroutine jobs

3. Using the activity rates you have computed, determine the total cost and the average cost per thousand square feet of each of the following jobs according to the activity-based costing system

a

Activity Rate QTY Per 1000
Removing Asbestos 1492 1 1492
Estimating and Job Setup 563 1 563
Total 2055

b

Activity Rate QTY Per 1000
Removing Asbestos 1492 2 2984
Estimating and Job Setup 563 1 563
Total 3547

c

A routine 1,000-square-foot asbestos removal job.
Activity Rate QTY Per 1000
Removing Asbestos 1492 1 1492
Estimating and Job Setup 563 1 563
Working on Nonroutine Jobs 7808 1 7808
Total 9863

Related Solutions

Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has...
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the company’s estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work such as removal of asbestos insulation around heating pipes in older homes and nonroutine work such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT