Resource optimization techniques involve the scheduling of activities and the resources required by those activities while taking into consideration both the resource availability and:
a. Project Time
b. Trend Analysis
c. Expert Judgement
d. Data Analysis
Resource optimization techniques involve the scheduling of activities and the resources required by those activities while taking into consideration both the resource availability and:
Answer: Project Time. While using resource optimization techniques like resource loading, schedule of individual activities is considered, schedule and loading / availability of resources is considered considering project schedule i.e. given resource optimized schedule should not result in exceeding project overall duration and project getting delayed.