Consider palletizer at a bottling plant that has a first cost of $141,424, has operating and maintenance costs of $14,037 per year, and an estimated net salvage value of $44,603 at the end of 30 years. Assume an interest rate of 8%. What is the future worth of this project?
Enter your answer as follow: 123456.78
The given data are executed in excel.
Therefore Future worth of the project is= $-2968756
The excel calculation are given below:
F/P factor has been taken from the table.