Question

In: Accounting

Googlish Imports needs to determine the variable utilities rate per machine hour in order to estimate...

Googlish Imports needs to determine the variable utilities rate per machine hour in order to estimate cost for August. Relevant information is as follows.

Month

Machine Hours Worked

Utilities Cost

April

4,750

9,810

May

4,700

9,690

June

7,000

11,225

July

8,000

12,400

Googlish anticipates producing 5,500 units in August, each unit requiring 3.0 hours of machine time. The company uses the high-low method to analyze costs.

Required:
A. Calculate the variable and fixed components of the utilities cost.
B. Using the data calculated above, estimate the utilities cost for August.
C. Compare the high-low method versus the visual-fit method with respect to (1) number of data observations used in the analysis and (2) objectivity of the results

Solutions

Expert Solution

A) Calculate the variable and fixed components of the utilities cost.
Month Machine hous Worked Utilities Cost
April 4,750 9810
May 4,700 9690
June 7,000 11225
July 8,000 12400
Variable Cost per Mhr (Highest Activity Cost - Lowset Activity Cost)
(Highest Activity Units - Lowset Activity Units)
(12,400 - 9,690)
(8,000 - 4,700)
2,710
3,300
Variable Cost per Mhr 0.8212
Fixed Cost (High Cost - (Variable Cost per unit x High Activity Unit)
OR
(High Cost - (Variable Cost per unit x High Activity Unit)
= (12,400 - (0.8212 x 8,000)
= 5,830
OR
= (9,690 - (0.8212 x 4,700)
= 5,830
B)             calculated the, estimate the utilities cost for August.
         Machine Hours           = 16,500 [5,500 Units x 3 Mhr p.u.]
Variable Cost per Mhr 0.8212
Total Variable Costs 13,550 [16,500 Mhrs x 0.8212]
Total Fixed Costs 5,830
Total Utilities Costs 19,380
C) Compare the high-low method versus the visual-fit method
Month Machine hous Worked Utilities Cost
April 4,750 9810
May 4,700 9690
June 7,000 11225
July 8,000 12400
Variable Cost per Mhr (Change in Cost)
(Change Units)
(12,400 - 11,225)
(8,000 - 7,000)
1,175
1,000
Variable Cost per Mhr 1.175
Fixed Cost (Total Cost - Total Variable Cost )
= (12,400 - (1.175 x 8,000)
= 3,000
OR
= (11,225 - (1.175 x 7,000)
= 3,000
            calculated the, estimate the utilities cost for August.
         Machine Hours           = 16,500 [5,500 Units x 3 Mhr p.u.]
Variable Cost per Mhr 1.175
Total Variable Costs 19,388 [16,500 Mhrs x 1.175]
Total Fixed Costs 3,000
Total Utilities Costs 22,388
High Low Cost Method Visual Fit Method
Variable Cost per Mhr 0.8212 1.175
Total Variable Costs 13,550 19,388
Total Fixed Costs 5,830 3,000
Total Utilities Costs 19,380 22,388

Related Solutions

27) Lichtenstein Imports needs to determine the variable utilities rate per machine hour in order to...
27) Lichtenstein Imports needs to determine the variable utilities rate per machine hour in order to estimate cost for August. Relevant information is as follows. Month Machine Hours Worked Utilities Cost April 4,500 $9,560 May 4,200 $9,440 June 6,500 $10,725 July 7,000 $11,400 Lichtenstein anticipates producing 5,000 units in August, each unit requiring 1.5 hours of machine time. The company uses the high-low method to analyze costs. Required: A. Calculate the variable and fixed components of the utilities cost. B....
If overhead is applied on the basis of machine hours, what will be the overhead rate per hour?
Simplex Company has the following estimated costs for next year: Simplex estimates that 10,000 direct labour and 16,000 machine hours will be worked during the year. If overhead is applied on the basis of machine hours, what will be the overhead rate per hour?
Edison Corporation's variable manufacturing overhead rate is $5.00 per direct labor-hour.
Edison Corporation's variable manufacturing overhead rate is $5.00 per direct labor-hour. Total budgeted fixed overhead is $25,000 per month. The $25,000 per month includes $7,000 in depreciation expense. Total budgeted direct labor-hours for the month of July is 20,000. Based on the month of July only, the predetermined overhead rate is $ (Enter your answer as a number rounded to 2 decimal places.)
Gallop, Inc. budgeted its variable overhead application rate as $0.25 per direct labor hour. Actual variable...
Gallop, Inc. budgeted its variable overhead application rate as $0.25 per direct labor hour. Actual variable overhead cost for the period is $9,700. If the actual number of labor hours worked during the period are 38,500 and if there is a total unfavorable flexible variable overhead variance of $230, calculate the standard number of direct labor hours allowed for the output achieved by Gallop within this period. a. 38,500 b. 37,880 c. 37,920 d. 39,720 Can you please indicate the...
1. The predetermined manufacturing overhead rate is $18 per machine hour based on an estimated manufacturing...
1. The predetermined manufacturing overhead rate is $18 per machine hour based on an estimated manufacturing overhead of 180,000 and 10,000 machine hours. For the year the actual overhead was 200,000 and machine hours were 11,000. How much manufacturing overhead was applied during the year? a. 198,000 b. 200,000 c. none of the above 2. Overapplied manufacturing overhead that is not material is adjusted by which entry? a. debit manufacturing overhead and credit misc exp b. debit cash and credit...
Estimated variable manufacturing overhead $25 per machine hour Estimated fixed manufacturing overhead $67,100 Estimated machine-hours 6,100...
Estimated variable manufacturing overhead $25 per machine hour Estimated fixed manufacturing overhead $67,100 Estimated machine-hours 6,100 Actual manufacturing overhead $231,500 Actual machine-hours 6,250 The estimates of the manufacturing overhead and of machine-hours were made at the beginning of the year for the purpose of computing the company's predetermined overhead rate for the year. The applied manufacturing overhead for the year is:
72) Keeran Corporation estimates that its variable manufacturing overhead is $5.20 per machine-hour and its fixed...
72) Keeran Corporation estimates that its variable manufacturing overhead is $5.20 per machine-hour and its fixed manufacturing overhead is $242,048 per period. If the denominator level of activity is 6,200 machine-hours, the predetermined overhead rate would be: A) $520.00 per machine-hour B) $5.20 per machine-hour C) $44.24 per machine-hour D) $39.04 per machine-hour 73) Fleming Incorporated makes a single product—a critical part used in commercial airline seats. The company has a standard cost system in which it applies overhead to...
Keeran Corporation estimates that its variable manufacturing overhead is $6.50 per machine-hour and its fixed manufacturing...
Keeran Corporation estimates that its variable manufacturing overhead is $6.50 per machine-hour and its fixed manufacturing overhead is $280,080 per period. If the denominator level of activity is 7,200 machine-hours, the predetermined overhead rate would be: Multiple Choice $650.00 per machine-hour $38.90 per machine-hour $6.50 per machine-hour $45.40 per machine-hour
Amethyst has a standard variable overhead rate of $5 per direct labour hour. The standard quantity...
Amethyst has a standard variable overhead rate of $5 per direct labour hour. The standard quantity of direct labour per unit of production is 2 hours. The company's static budget was based on 50,000 units. Actual results for the year are as follows. Actual units produced 45,000 Actual direct labour hours 100,000 Actual variable overhead $495,000 The time has come for the company to compare of actual results with planned results. Required a) What is the company’s (i) static budget...
Amethyst has a standard variable overhead rate of $5 per direct labour hour. The standard quantity...
Amethyst has a standard variable overhead rate of $5 per direct labour hour. The standard quantity of direct labour per unit of production is 2 hours. The company's static budget was based on 50,000 units. Actual results for the year are as follows. Actual units produced               45,000 Actual direct labour hours         100,000 Actual variable overhead           $495,000 The time has come for the company to compare of actual results with planned results. Required What is the company’s (i) static budget and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT