Question

In: Finance

Capital Budgeting Decision Rules: 1. Payback period approach in capital budgeting evaluation process fails to consider...

Capital Budgeting Decision Rules:
1. Payback period approach in capital budgeting evaluation process fails to consider all cash flows and the time value of money.
True False

2. If a project’s NPV is positive, then it is IRR is greater than its cost of capital.
True False
A project will cost $160,000. The after-tax future cash flows are expected to be $40,000 annually for 7 years. For #3-5.

3. What is the project’s payback period?
A. 1.5 yrs B. 2.0 yrs C. 3.3 yrs D. 4.0 years E. 4.3 years

4. Assume the required return is 10%. What is the project’s NPV?
A. $14,111 B. $27,322 C. $32,556 D. $34,737 E. $45,001

5. Assume the required return is 17%. What is the project’s IRR? Accept?
A. 12.2%; yes
B. 12.2%; no
C. 16.3%; yes
D. 16.3%; no
E. 17.0%; indifferent

6. XYZ company is planning to buy the ABC company. The acquisition would require an initial investment of $190,000, but in one year XYZ company's after-tax net cash flows would increase by $24,000 and remain at this new level annually forever. Assume a cost of capital of 10 percent. Should XYZ buy ABC?

Please provide all work for these problems not just final solutions so they can be modeled for other similar problems. Thank you :)

Solutions

Expert Solution

1. True. Payback period measures the time required to recover the initial outlay and it does not consider the cash flows after recovering of initial outlay. It is the drawback of payback period that it does not consider time value of money. Therefore the given statement is true that payback period approach in capital budgeting evaluation process fails to consider all cash flows and the time value of money.

2. True. If NPV is positive then its IRR is greater than cost of capital

Lets take an example, if projects cost is $2000, cash inflows for next three years will be $1000 a year. cost of capital is 10%

Its NPV will be 486.85 and its IRR will be 23%, which is more than cost of capital.

Hence the given statement is true.

3. Payback Period

Period Cash Flow Cumulative cash flow
0 -160000 -160000
1 40000 -120000
2 40000 -80000
3 40000 -40000
4 40000 0
5 40000 40000
6 40000 80000
7 40000 120000

Since at year 4 the cumilative cash flow is zero, it means it take 4 years to recover its initial outlay. Thus, Payback period is 4 years. Option D. 4 years is correct

4. NPV

Period Cash Flows PV factor @10% PV of cash flows
1 40000 0.909 36363.636
2 40000 0.826 33057.851
3 40000 0.751 30052.592
4 40000 0.683 27320.538
5 40000 0.621 24836.853
6 40000 0.564 22578.957
7 40000 0.513 20526.325
Total 194736.753

Present value of future cash inflows = 194736.753

Present value of cash outflow = 160000

NPV = Present value of future cash inflows - Present value of cash outflow

NPV = 194736.753 - 160000

= 34736.753

So NPV of the project is $34736.753 after rounding off it will be $34737. Correct answer is Option D. 34,737


Related Solutions

The Basics of Capital Budgeting: Payback Period Payback Period Payback period was the earliest ________ selection...
The Basics of Capital Budgeting: Payback Period Payback Period Payback period was the earliest ________ selection criterion. -Select- capital structure financial statement capital budgeting The _________ -Select- NPV MIRR IRR payback is a "break-even" calculation in the sense that if a project's cash flows come in at the expected rate, the project will break even. The equation is: The -Select- shorter longer a project's payback, the better the project is. However, payback has 3 main disadvantages: (1) All dollars received...
Are the capital budgeting rules discussed in Chapter 5 (namely NPV, IRR, Payback Period and Profitability...
Are the capital budgeting rules discussed in Chapter 5 (namely NPV, IRR, Payback Period and Profitability Index) applicable to not-for-profit corporations? How should such entities make capital budgeting decisions? Defend your recommendation.
A.    Capital Budgeting Evaluation Process 1.    2.    3.    4.    5.    B.    Cash Payback. 1.   Describe __________________
A.    Capital Budgeting Evaluation Process 1.    2.    3.    4.    5.    B.    Cash Payback. 1.   Describe __________________________________________________ ___________________________________________________________ 2.   Net annual cash flow is computed by ___________________________ ________________________________________________________. a.     Cash Payback Period = b.     The shorter the payback period, the more ___________the investment. c.     The cash payback technique recognizes that: (1) (2)    d.     In the case of uneven net annual cash flows, the company determines the cash payback period when _____________________________ _____________________________________________________ C.    Net Present Value Method. 1.    2.    3.    4.   The net present value method involves discounting net cash flows...
Which of the following decision measures should capital budgeting decision makers consider? a. discounted payback b....
Which of the following decision measures should capital budgeting decision makers consider? a. discounted payback b. NPV c. IRR d. MIRR e. Although NPV is considered the most important method in the decision process, the other measures can provide different relevant information that is useful to the process and thus should be used when appropriate
Capital Budgeting For the following two projects, determine the 1. Payback Period 2. Discounted Payback 3....
Capital Budgeting For the following two projects, determine the 1. Payback Period 2. Discounted Payback 3. Net Present Value 4. Profitability Index (Benefit-Cost Ratio) 5. Internal Rate of Return 6. Modified Internal Rate of Return Project A Project B Year Net Income Cash Flow Net Income Cash Flow 0 (15,000) (19,000) 1 5,000 6,000 3,000 4,000 2 5,000 6,000 5,000 6,000 3 5000 6,000 7,000 8,000 4 5,000 6,000 11,000 12,000 Risk Index 1.80 .60 The firm’s cost of capital...
1. What are disadvantages of Payback Period method used in capital budgeting. 2. A project has...
1. What are disadvantages of Payback Period method used in capital budgeting. 2. A project has an initial cost of $1000 and $450 cash inflow each year for 4 years with a discount rate of 10%. What is its payback period? What is its discounted payback period?
1. Capital Budgeting Decisions and Decision Rules You must evaluate a proposal to buy a new...
1. Capital Budgeting Decisions and Decision Rules You must evaluate a proposal to buy a new milling machine. The base price is Rs. 1,08,000, and shipping and installation cost would add another Rs. 12,500. The machine is depreciated under straight line basis. The life of the machine is 4 years. It will be sold after 4 years for Rs. 65,000. The machine would require a Rs. 55,000 increase in working capital. There would be net effect on pre-tax revenues and...
Capital Budgeting Assignment For the following two projects, determine the Payback Period Discounted Payback Net Present...
Capital Budgeting Assignment For the following two projects, determine the Payback Period Discounted Payback Net Present Value Profitability Index (Benefit-Cost Ratio) Internal Rate of Return Modified Internal Rate of Return             Project A Project B Year Net Income Cash Flow Net Income Cash Flow 0 (15,000) (19,000) 1 5,000 6,000 3,000 4,000 2 5,000 6,000 5,000 6,000 3 5000 6,000 7,000 8,000 4 5,000 6,000 11,000 12,000 Risk Index 1.80 .60 The firm’s cost of capital ko is 15% and...
Explain the concept of Payback Period (PP) in capital budgeting, and how it is computed. What...
Explain the concept of Payback Period (PP) in capital budgeting, and how it is computed. What is the payback period of a project with the following cashflows (at time periods 0, 1, 2 and 3): -$50,000, $30,000, $15,000, $15,000? Under what circumstances would PP be preferred to the Net Present Value (NPV) approach. (maximum length guide: about 150 words)
Explain the concept of Payback Period (PP) in capital budgeting, and how it is computed. What...
Explain the concept of Payback Period (PP) in capital budgeting, and how it is computed. What is the payback period of a project with the following cashflows (at time periods 0, 1, 2 and 3): -$50,000, $30,000, $15,000, $15,000? Under what circumstances would PP be preferred to the Net Present Value (NPV) approach. (maximum length guide: about 150 words)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT