In: Accounting
Do you feel that the price per unit is fair, or do you need to apply pressure for a substantially lower price? Why?
2. A labor intensive product takes 115 hours to assemble for the first unit. How long would it take to assemble the 25thunit assuming a 92% learning rate?
3. If the learning rate is assumed to be 88%, how long would it take to assemble the 50thunit?
1.
Direct Material = $6.50
Direct Labour = $1.50
Overheads = $1.50 x 200% = $3.00
Total cost = $11.00
Sales price after profit margin = $11.00 x 1.08 = $11.88
Since sales price is lower than what supplier charges, we need not pressurie.
2.
cumulative average time per unit = time taken to produce initial quantity x the cumulative units of production ^ the learning index
The learning index = Log 0.92 / Log 2 = -0.1203
cumulative average time per unit for 25 units = 115 hrs x 25 ^ -0.1203 = 78.08 hrs for 25 units
Total time for 25 units = 78.08 hrs x 25 = 1,952 hrs
cumulative average time per unit for 24 units = 115 hrs x 24 ^ -0.1203 = 78.46 hrs for 24 units
Total time for 24 units = 78.46 hrs x 24 = 1,883 hrs
Time taken for 25th unit = 1,952 hrs - 1,883 hrs = 68.85 hrs
3.
The learning index = Log 0.88 / Log 2 = -0.1844
cumulative average time per unit for 50 units = 115 hrs x 50 ^ -0.1844 = 55.89 hrs for 50 units
Total time for 25 units = 55.89 hrs x 50 = 2,795 hrs
cumulative average time per unit for 24 units = 115 hrs x 49 ^ -0.1844 = 56.10 hrs for 49 units
Total time for 24 units = 56.10 hrs x 49 = 2,749 hrs
Time taken for 25th unit = 2,795 hrs - 2,749 hrs = 45.67 hrs