In: Finance
An capital investment project provides a company with expected cash flows of $10,000; $12,000; $14,000; $16,000, and $18,000 in years 1-5, respectively. The investment will require an initial expenditure of $45,000 and the company has a weighted average cost of capital of 8.0%. What is the net present value of the project?
What is the internal rate of return for the project given?
A stock earns a monthly return of 0.85%. What is the equivalent annualized rate of return?
The total return on an investment over a five year period is 85%. What is the equivalent annualized rate of return?
| Year | Cashflows | Discountinf Factor@ 8% | PV | 
| 0 | -45000 | 1 | - 45,000.00 | 
| 1 | 10000 | 0.93 | 9,259.26 | 
| 2 | 12000 | 0.86 | 10,288.07 | 
| 3 | 14000 | 0.79 | 11,113.65 | 
| 4 | 16000 | 0.74 | 11,760.48 | 
| 5 | 18000 | 0.68 | 12,250.50 | 
| NPV | 9,671.95 | 
| At IRR, NPV of cashflows =0 | 
Lets calculate PV of cashflows at 15%. Now we have two rates at which cashflows are calculated
| Year | Cashflows | Discountinf Factor@ 15% | PV | 
| 0 | -45000 | 1 | - 45,000.00 | 
| 1 | 10000 | 0.87 | 8,695.65 | 
| 2 | 12000 | 0.76 | 9,073.72 | 
| 3 | 14000 | 0.66 | 9,205.23 | 
| 4 | 16000 | 0.57 | 9,148.05 | 
| 5 | 18000 | 0.50 | 8,949.18 | 
| NPV | 71.84 | 
Let R1= 8%, R2= 15%
Formula for IRR = R1+NPV1*(R2-R1)/(NPV1-NPV2)
= 8% + 9671.95*(15-8)/(9671.95-71.84)
=15.06%
IRR = 15.06%
2nd Question
Annualised Rate of Return = 0.85%^12 = 10.69%
Total Return on investement = 85%
Annualised Return = (1.85^1/5) - 1 = (1.85^0.2) - 1= 1.1309 - 1 = 0.1309 or 13.09%