Question

In: Finance

Murray’s Machine Shop is considering a five year project to improve its production efficiency. Buying a...

Murray’s Machine Shop is considering a five year project to improve its production efficiency. Buying a new machine press for $850,000 is expected to result in annual pre-tax cost saving of $310,000. No additional sales are expected from this project. The machine press will be depreciated straight-line to zero over its five year life. After that it is expected to be obsolete and therefore worthless. The company will be able to reduce net working capital (NWC) by $75,000 at the beginning of the project. NWC will revert back to its original level at the end of project. The company’s hurdle rate is 15%. The tax rate is 21%. a. List all the assumption of the project. b. Calculate each year’s depreciation and ending book values. c. Prepare pro forma income statements for the five years of the project’s life. d. Calculate the changes in net working capital. e.Calculate the project’s operating cash flows. f. Calculate the project’s net net cash flows. g. Calculate the project’s net present value (NPV) h. Calculate the project’s internal rate of return (IRR) i. Should the company purchase the new machine press? Why or why not? (Must be done on a spreadsheet using Excel formulas only)

Solutions

Expert Solution

Answer a
Assumptions of the project
- Zero salvage value of machine at the end of project.
- No additional sales
- tax rate and hurdle rate be 21% and 15% respectively for all years
Answer b
Calculation of depreciation and book values
Year Depreciation Book Values
0 0 850000
1 170000 680000
2 170000 510000
3 170000 340000
4 170000 170000
5 170000 0
Depreciation per year using straight line method = (Cost - salvage value)/Useful life
Depreciation per year using straight line method = ($850000-$0)/5 years = $1,70,000
Answer c
Proforma Income statement
Year 1 2 3 4 5
Cost savings 310000 310000 310000 310000 310000
Less : Depreciation 170000 170000 170000 170000 170000
Profit before tax 140000 140000 140000 140000 140000
Less : Tax @ 21% 29400 29400 29400 29400 29400
Increase in Net Income 110600 110600 110600 110600 110600
Answer d
Calculation of changes in working capital
Year 0 1 2 3 4 5
Changes in working capital 75000 -75000
Answer e
Calculation of project's operating cash flow
Year 1 2 3 4 5
Increase in net income 110600 110600 110600 110600 110600
Add : Depreciation 170000 170000 170000 170000 170000
Project's Operating cash flow 280600 280600 280600 280600 280600
Answer f
Calculation of project's net cash flow
Year 0 1 2 3 4 5
Initial Investment -850000
Changes in working capital 75000 -75000
Operating cash flow 280600 280600 280600 280600 280600
Net Cash flows -775000 280600 280600 280600 280600 205600
Answer g
Calculation of project’s net present value (NPV)
Year 0 1 2 3 4 5 NPV
Net Cash flows -775000 280600 280600 280600 280600 205600
x Discount factor @ 15% 1 0.869565 0.756144 0.657516 0.571753 0.497177
Present Values -775000 244000 212173.9 184499.1 160434 102219.5    128,326.47
NPV of the project =     128,326.47
Answer h
Calculation of IRR of the project
At IRR , the NPV of the project is equal to zero.
Year 0 1 2 3 4 5 IRR
Net Cash flows -775000 280600 280600 280600 280600 205600 22.05%
IRR of the project = 22.05%
Answer i
Company should purchase the new machine press as it has positive NPV and IRR is greater than hurdle rate.

Related Solutions

Massey Machine Shop is considering a four year project to improve its production efficiency. Buying a...
Massey Machine Shop is considering a four year project to improve its production efficiency. Buying a new machine press for $730,000 is estimated to result in $220,000 in annual pretax cost savings. The press falls in the MACRS five year class, and it will have a salvage value at the end of the project of $89,000. The press also requires an initial investment in spare parts inventory of $26,000, along with an additional $3,000 in inventory for each succeeding year...
Massey Machine Shop is considering a four year project to improve its production efficiency. Buying a...
Massey Machine Shop is considering a four year project to improve its production efficiency. Buying a new machine press for $730,000 is estimated to result in $220,000 in annual pretax cost savings. The press falls in the MACRS five year class, and it will have a salvage value at the end of the project of $89,000. The press also requires an initial investment in spare parts inventory of $26,000, along with an additional $3,000 in inventory for each succeeding year...
CMS Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
CMS Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $545,000 is estimated to result in $97,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value of $70,000. The press also requires an initial working capital of $21,000, along with an additional $3,000 in working capital for each succeeding years of project. The tax rate is 34%, and the company's...
Starset Machine Shop is considering a 4-year project to improve its production efficiency. Buying a new...
Starset Machine Shop is considering a 4-year project to improve its production efficiency. Buying a new machine press for $460,000 is estimated to result in $190,000 in annual pretax cost savings. The press falls in the 5-year MACRS class, and it will have a salvage value at the end of the project of $74,000. The press also requires an initial investment in spare parts inventory of $35,000, along with an additional $3,850 in inventory for each succeeding year of the...
Geller Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geller Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $390,000 is estimated to result in $150,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $66,000. The press also requires an initial investment in spare parts inventory of $12,000, along with an additional $1,700 in inventory for each succeeding year of the...
Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a...
Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $490,847 is estimated to result in some amount of annual pretax cost savings. The press will have an aftertax salvage value at the end of the project of $86,695. The OCFs of the project during the 4 years are $175,493, $191,453, $170,805 and $167,265, respectively. The press also requires an initial investment in spare parts inventory of $25,940, along with...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,132,800 is estimated to result in $377,600 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $165,200. The press also requires an initial investment in spare parts inventory of $47,200, along with an additional $7,080 in inventory for each succeeding year...
Geller Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geller Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $480,000 is estimated to result in $195,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $81,000. The press also requires an initial investment in spare parts inventory of $21,000, along with an additional $2,600 in inventory for each succeeding year of the...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $950,400 is estimated to result in $316,800 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $138,600. The press also requires an initial investment in spare parts inventory of $39,600, along with an additional $5,940 in inventory for each succeeding year...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $566,400 is estimated to result in $188,800 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $82,600. The press also requires an initial investment in spare parts inventory of $23,600, along with an additional $3,540 in inventory for each succeeding year...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT