In: Accounting
29) The Tulip Company makes mugs for which the following standards have been developed:
Standard Inputs Expected Standard Price Expected
For Each Unit of Output Per Unit of Input
Direct Materials 5 ounces $2 per ounce
Direct Labor 2.5 hours $8 per hour
Production of 400 mugs was expected in August, but 440 mugs were actually completed. Direct materials purchased and used were 2,100 ounces at an actual price of $2.20 per ounce. Direct labor cost for the month was $5,310, and the actual pay per hour was $9.00. What is the direct labor price variance for August?
A) $420 Favorable
B) $420 Unfavorable
C) $590 Favorable
D) $590 Unfavorable this is correct. please explain why
Direct labour price variance
Direct labour price variance is the difference between standard rate per hour and actual rate paid per labour hour for actual labour hours worked.
The formula being used to calculate labor rate variance is:
(Standard rate - Actual rate) * Actual hours worked
Thus, we need to first calculate actual hours worked from the given information.
Actual pay per hour - $9.00 per hour
Actual labour cost - $5310
Therefore, actual labour hours will be -
= Actual labour cost / actual pay per hour
= $5310 / $9.00
= 590 hours
Now, we can compute labor price/rate variance by using the above mentioned formula,
Standard price - $8.00 per hour
Actual price -$9.00 per hour
Actual labor hours - 590
= (8.00 - 9.00) * 590
= $ 590 unfavorable
Note: As the actual price paid per labour hour is more than standard price per labour hour, the variance is unfavorable. It is because, the price paid actually is more than the standard set.
Thank you!