6. Solving for the WACC The WACC is used as the discount rate to evaluate various...

6. Solving for the WACC

The WACC is used as the discount rate to evaluate various capital budgeting projects. However, it is important to realize that the WACC is an appropriate discount rate only for a project of average risk.

Analyze the cost of capital situations of the following company cases, and answer the specific questions that finance professionals need to address.

Consider the case of Turnbull Co.

Turnbull Co. has a target capital structure of 45% debt, 4% preferred stock, and 51% common equity. It has a before-tax cost of debt of 8.2%, and its cost of preferred stock is 9.3%.

If Turnbull can raise all of its equity capital from retained earnings, its cost of common equity will be 12.4%. However, if it is necessary to raise new common equity, it will carry a cost of 14.2%.

If its current tax rate is 25%, how much higher will Turnbull’s weighted average cost of capital (WACC) be if it has to raise additional common equity capital by issuing new common stock instead of raising the funds through retained earnings? (Note: Round your intermediate calculations to two decimal places.)

1.06%

1.01%

0.92%

1.10%

Turnbull Co. is considering a project that requires an initial investment of $570,000. The firm will raise the $570,000 in capital by issuing $230,000 of debt at a before-tax cost of 11.1%, $20,000 of preferred stock at a cost of 12.2%, and $320,000 of equity at a cost of 14.7%. The firm faces a tax rate of 25%. What will be the WACC for this project?      (Note: Round your intermediate calculations to three decimal places.)

Consider the case of Kuhn Co.

Kuhn Co. is considering a new project that will require an initial investment of $45 million. It has a target capital structure of 45% debt, 4% preferred stock, and 51% common equity. Kuhn has noncallable bonds outstanding that mature in five years with a face value of $1,000, an annual coupon rate of 10%, and a market price of $1,050.76. The yield on the company’s current bonds is a good approximation of the yield on any new bonds that it issues. The company can sell shares of preferred stock that pay an annual dividend of $8 at a price of $92.25 per share.

Kuhn does not have any retained earnings available to finance this project, so the firm will have to issue new common stock to help fund it. Its common stock is currently selling for $33.35 per share, and it is expected to pay a dividend of $2.78 at the end of next year. Flotation costs will represent 8% of the funds raised by issuing new common stock. The company is projected to grow at a constant rate of 9.2%, and they face a tax rate of 25%. What will be the WACC for this project?      (Note: Round your intermediate calculations to two decimal places.)

Solutions

Expert Solution

1. How much higher will Turnbull’s weighted average cost of capital (WACC)

Capital structure:
Debt 45%
Preferred stock 4%
Common Equity 51%
Before tax cost of debt 8.20%
Cost of Preferred stock 9.30%
Cost of Common Equity (retained earnings) 12.40%
Cost of New Common Equity 14.20%
Tax rate 25%
After tax cost of debt (8.20 * (1-.25) 6.15%

Computation of WACC

WACC=(After tax cost of debt * Debt % of total capital)+(Cost of Preferred stock * Preferred stock % of total capital)+(Cost of Common Equity * Common Equity% of total capital)
If retained earnigs are used 9.46 (6.15*45%)+(9.30*4%)+(12.40*51%)
If new common equity is raised 10.38 (6.15*45%)+(9.30*4%)+(14.20*51%)
Higher WACC if new equity is raised 0.92 (10.38-9.46)

2. WACC for the project

Initial Investment 570,000
Debt value 230,000
Before tax cost of debt 11.10%
Tax rate 25%
After tax cost of debt (11.10 * (1-.25) 8.33%
Preferred stock value 20,000
Cost of Preferred stock 12.20%
Equity stock value 320,000
Cost of Equity stock 14.70%

Computation of WACC

WACC=(After tax cost of debt * Debt % of total capital)+(Cost of Preferred stock * Preferred stock % of total capital)+(Cost of Common Equity * Common Equity% of total capital)
Debt % of total capital 40.35% (230,000 / 570,000)
Preferred stock % of total capital 3.51% (20,000 / 570,000)
Common Equity % of total capital 56.14% (320,000 / 570,000)
WACC 12.04% (8.33*40.35%)+(12.20*3.51%)+(14.70*56.14%)

Related Solutions

6. Solving for the WACC The WACC is used as the discount rate to evaluate various...
6. Solving for the WACC The WACC is used as the discount rate to evaluate various capital budgeting projects. However, it is important to realize that the WACC is an appropriate discount rate only for a project of average risk. Analyze the cost of capital situations of the following company cases, and answer the specific questions that finance professionals need to address. Consider the case of Turnbull Co. 1. Turnbull Co. has a target capital structure of 45% debt, 4%...
7. Solving for the WACC The WACC is used as the discount rate to evaluate various...
7. Solving for the WACC The WACC is used as the discount rate to evaluate various capital budgeting projects. However, it is important to realize that the WACC is an appropriate discount rate only for a project of average risk. Analyze the cost of capital situations of the following company cases, and answer the specific questions that finance professionals need to address. Consider the case of Turnbull Co. Turnbull Co. has a target capital structure of 58% debt, 6% preferred...
2. Solving for the WACC 9.97 The WACC is used as the discount rate to evaluate...
2. Solving for the WACC 9.97 The WACC is used as the discount rate to evaluate various capital budgeting projects. However, it is important to realize that the WACC is only an appropriate discount rate for a project of average risk—in other words, a project that has the same beta as the company. If a project has less risk than the overall company risk, it should be evaluated with a lower discount rate; if a project is riskier than the...
The WACC is used as the discount rate to evaluate various capital budgeting projects. However, it...
The WACC is used as the discount rate to evaluate various capital budgeting projects. However, it is important to realize that the WACC is an appropriate discount rate only for a project of average risk. Analyze the cost of capital situations of the following company cases, and answer the specific questions that finance professionals need to address. Consider the case of Turnbull Co. Turnbull Co. has a target capital structure of 58% debt, 6% preferred stock, and 36% common equity....
The weighted average cost of capital (WACC) is used as the discount rate to evaluate various...
The weighted average cost of capital (WACC) is used as the discount rate to evaluate various capital budgeting projects. However, it is important to realize that the WACC is an appropriate discount rate only for a project of average risk. Consider the case of Turnbull Company. Turnbull Company has a target capital structure of 58% debt, 6% preferred stock, and 36% common equity. It has a before-tax cost of debt of 8.20%, and its cost of preferred stock is 9.30%....
A firm’s weighted average cost of capital (WACC) is used as the discount rate to evaluate...
A firm’s weighted average cost of capital (WACC) is used as the discount rate to evaluate various capital budgeting projects. However, remember the WACC is an appropriate discount rate only for a project of average risk. Analyze the cost of capital situations of the following company cases, and answer the specific questions that finance professionals need to address. Consider the case of Fuzzy Button Clothing Company Fuzzy Button Clothing Company has a target capital structure of 58% debt, 6% preferred...
discuss the advantages and limitations of using the WACC as a discount rate to evaluate capital...
discuss the advantages and limitations of using the WACC as a discount rate to evaluate capital budgeting products. How is the WACC method used for valuing business? explain
A company’s WACC can be used as the required rate of return to evaluate new projects...
A company’s WACC can be used as the required rate of return to evaluate new projects that have risk similar to that of the company’s existing operations. Suppose that Company A is currently considering a project that has operations that are substantially different to its existing operations – meaning that the risks involved will also be different. Discuss the approaches that company A may use to determine the required rate of return for assessing this project.
•What are two methods that can be used to compute the appropriate discount rate when WACC...
•What are two methods that can be used to compute the appropriate discount rate when WACC isn’t appropriate? •How should we factor flotation costs into our analysis?
is always correct to use WACC as the discount rate ? explain