In: Finance
Big Steve's, makers of swizzle sticks, is considering the purchase of a new plastic stamping machine. This investment requires an initial outlay of $90,000 and will generate net cash inflows of $17,000 per year for 11 years.
a. If the discount rate is 8%, then the project's NPV is $________ (Round to the nearest dollar.)
The project (should not be/ Should be) accepted because the NPV is (negative/positive) and therefore (does not add/ adds) value to the firm. (Select the correct answer)
b. If the discount rate is 13% , then the project's NPV is $_________ (Round to the nearest dollar.)
The project (should not be/ Should be) accepted because the NPV is (negative/positive) and therefore (does not add/ adds) value to the firm. (Select the correct answer)
c. This project's internal rate of return is _______% (Round to two decimal places.)
If the project's required discount rate is 8%, then the project (should not be/ should be) accepted, because the IRR is (lower than/ higher than) the required discount rate (Select the correct answer)
If the project's required discount rate is 13%, then the project (should not be/ should be) accepted, because the IRR is (lower than/ higher than) the required discount rate (Select the correct answer)
a.Net present value can be solved using a financial calculator. The steps to solve on the financial calculator:
Net present value at 8% discount rate is $31,362.39.
The project should be accepted because the NPV is positive and therefore adds value to the firm.
b.Net present value can be solved using a financial calculator. The steps to solve on the financial calculator:
Net present value at 13% discount rate is $6,677.9992 $6,678.
The project should be accepted because the project is positive and therefore adds value to the firm.
c.Internal rate of return can be calculated using a financial calculator by inputting the below:
The IRR of the project is 14.72%.
If the project's discount rate is 8%, then the project should be accepted, because the IRR is higher than the required discount rate.
If the project's discount rate is 13%, then the project should be accepted, because the IRR is higher than the required discount rate.