Question

In: Accounting

The loan department of Your Local Bank uses standard costs to determine the overhead cost of...

The loan department of Your Local Bank uses standard costs to determine the overhead cost of processing loan applications. During the current month, a fire occurred, and the accounting records for the department were mostly destroyed. The following data were salvaged from the ashes:

Standard variable overhead rate per hour $9
Standard hours per application 3
Standard hours allowed 3,000
Standard fixed overhead rate per hour $6
Actual fixed overhead cost $19,800
Variable overhead budget based on standard hours allowed $27,000
Fixed overhead budget $19,800
Overhead budget variance $1,500 Unfavourable

1. Total actual overhead cost
2. Actual variable overhead cost

3. Variable overhead cost applied

4. Fixed overhead cost applied

5. Overhead volume variance

Determine how many loans were processed.

Solutions

Expert Solution

1.We Know that Total Actual Overhead Cost = Actual Fixed Overhead cost + Actual Variable Overhead cost.

Given

A. Fixed Overhead cost Budget = $19,800

B. Variable Overhead cost Budget=$27,000

So,Total Overhead Budget (A+B)=$46,800.

Also it is given that that there is an Unfavorable Overhead Budget Variance of 1,500$ it means Actual cost exceeded budget by 1,500$.

So,Total Actual Overhead cost =$46,800+$1,500=$48,300

2.It is given that Actual Fixed Overhead cost = $19,800

So,Actual Variable Overhead Cost=Total Actual Overhead cost-Actual Fixed Overhead cost=$48,300-$19,800=$28,500

3.As the Actual hours required per application or the actual hours incurred or actual rate incurred per hour is not given ,

Assuming the total variance ocurred is due to change in the volume,but not due to variance in rate,

Actual Variable Overhead cost applied per hour =$27000/3000=$9

4.Actual hours taken=Actual Variable Overhead Cost/Actual Variable Overhead cost applied per hour =$28,500/$9=3167 hours

So,Actual Fixed Overhead cost applied per hour=$19,800/3167=$6

5.Overhead Volume variance=Budgeted hours*Statndard rate-Actual hours*Standard rate

So,Overhead Volume variance=3000*$9-3167*$9=-1503$

Number of Loans processed=Standard hours allowed/Standard hours per application=3000/3=1000 applications


Related Solutions

Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 53,100 machine hours per year, which represents 26,550 units of output. Annual budgeted fixed factory overhead costs are $265,500 and the budgeted variable factory overhead cost rate is $3.00 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 50,000 machine hours per year, which represents 25,000 units of output. Annual budgeted fixed factory overhead costs are $250,000 and the budgeted variable factory overhead cost rate is $4 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 50,000 machine hours per year, which represents 25,000 units of output. Annual budgeted fixed overhead costs are $250,000 and the budgeted variable overhead cost rate is $4 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 20,000 units, which...
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced....
Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,500 machine hours per year, which represents 27,750 units of output. Annual budgeted fixed overhead costs are $277,500 and the budgeted variable overhead cost rate is $3.80 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 21,600 units, which...
Royale Mortgage Company uses a process cost system to accumulate costs in its loan application department....
Royale Mortgage Company uses a process cost system to accumulate costs in its loan application department. When an application is completed, it is forwarded to the loan department for final processing. The following processing and cost data pertain to September. Beginning WIP: Direct materials $1,130 Conversion costs 4,670 September costs: Direct materials $5,140 Direct labor 12,210 Overhead 8,688 1. Applications in process on September 1, 200 2. Applications started in September, 900 3. Completed applications during September, 700 Applications still...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced.
  Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 50,000 machine hours per year, which represents 25,000 units of output. Annual budgeted fixed factory overhead costs are $250,000 and the budgeted variable factory overhead cost rate is $4 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year...
The MoonStar Corporation uses a “predetermined overhead rate”to apply manufacturing overhead costs the each department....
The MoonStar Corporation uses a “predetermined overhead rate” to apply manufacturing overhead costs the each department. For the Department A, the company uses “labor cost” as allocation base and for the Department B, uses “machine-hours” as allocation base.             At the beginning of the year, the Corporation made the following estimates:Dept. ADept. BDirect labor cost$60,000$40,000Manufacturing overhead$90,000$45,000Direct labor-hours6,0009,000Machine-hours2,00015,000Question: Please compute the “predetermined overhead rates” for Dept. A and for Dept. B
Company uses activity-based costing to determine product cost. The accounting department identified the following overhead activities,...
Company uses activity-based costing to determine product cost. The accounting department identified the following overhead activities, costs, and activity drivers for the coming year. Activity Estimated cost Activity driver Activity capacity Setting up equipment $120,000 Number of setups 300 Ordering materials 90,000 Number of orders 9,000 Maintaining machines 210,000 Machine hours 21,000 Total overhead $420,000 The following actual results were collected for the production of Model X and Model Y during the year. Model X Model Y Units produced 8,000...
Your company is considering to take a loan from the local bank. Bank charges a 1.25%...
Your company is considering to take a loan from the local bank. Bank charges a 1.25% interest rate per quarter. Then the rate 1.25*4 =5% is called ____    annual percentage rate discount rate compound interest rate effective annual rate
Organizations determine standard costs for labor, materials, and overhead. Discuss variances for labor, materials, and overhead....
Organizations determine standard costs for labor, materials, and overhead. Discuss variances for labor, materials, and overhead. How do these variances differ from the standard costs? How is each computed? Why is calculating variances useful to an organization? Please help answer: How do these variances differ from the standard costs?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT