Question

In: Accounting

True Colour Inc. manufactures waterproof laptop backpacks. The standard cost card of a single backpack is...

True Colour Inc. manufactures waterproof laptop backpacks. The standard cost card of a single backpack is given below:

  

Standard Quantity
or Hours

Standard Price
or Rate

Standard
Cost

Direct materials

?

$

4.00

per yard

$

?

Direct labor

?

?

?

Variable manufacturing overhead

?

$

2

per direct labor-hour

?

Total standard cost per unit

$

?

Overhead is applied to production on the basis of direct labor-hours. During March, 700 backpacks were manufactured and sold. Selected information relating to the month’s production is given below:

  

Materials
Used

Direct Labor

Variable
Manufacturing
Overhead

Total standard cost allowed*

$

11,200

$

10,500

$

2,100

Actual costs incurred

$

8,925

?

$

4,032

Materials price variance

?

Materials quantity variance

$

700

U

Labor rate variance

?

Labor efficiency variance

?

Variable overhead rate variance

?

Variable overhead efficiency variance

?

*For the month's production.

The following additional information is available for March’s production:

Actual direct labor-hours

1,050

Difference between standard and actual cost per backpack produced during March

$

0.34

F

Required:

Hint: It may be helpful to complete a general model diagram for direct materials, direct labor, and variable manufacturing overhead before attempting to answer any of the requirements.

1. What is the standard cost of a single backpack?

2. What was the actual cost per backpack produced during March?

3. How many yards of material are required at standard per backpack?

4. What was the materials price variance for March if there were no beginning or ending inventories of materials?

Solutions

Expert Solution

Ans 1. cost of materials = $11,200

cost of Direct labour= $10,500

Variable manufacturing overhead= $ 2,100

Total standard cost = $11,200 + $10,500 $ 2,100 = $23, 800

Number of backpacks produced= 700

Standard cost of a single backpack= total standard cost / number of backpacks

= $23,800 / 700

= $34

Ans 2. Standard cost of a single backpack = $ 34 (as calculated in ans 1)

variance between standard and actual cost per backpack = $ 0.34 (F)

Actual cost per backpack produced during March = Standard cost - variance between standard and actual cost

= $34 - $0.34

= $33.66

Ans 3. Total standard cost of materials during March = $ 11,200

Number of backpacks produced during March = 700

Standard material cost (SMC) per backpack = total standard material cost / number of backpacks

= $11,200 / 700

= $16

Standard material cost (SMC) per yard = $4 (given in Ques)

Yards of material required at standard per backpack = SMC per backpack / SMC per yard

= $16 / $4

= 4 yards per backpack

Ans 4. Standard cost of materials used = $11,200

Actual cost of materials used = $ 8,925

Total material Variance = Standard cost of Material - Actual cost of material used

= $ 11, 200 - $ 8,925

= $2,275 (Favourable)

As there is no beginning or ending inventories of materials, the total material purchased was used during the month.

The price and quantity variance together therefore equal the total material variance. The material quantity variance is given as $700 (U). So, the price variance must be calculated as follows:

Total material variance = $2,275 (F) = + $2,275 (F stands for Favourable)

material quantity variance = $ 700 (U) = - $700   (U stands for unfavourable)

The price variance per march = Total material variance - material quantity variance

= (+2,275) - (-700)

=2,275 + 700

= $2,975 (F)


Related Solutions

True Colour Inc. manufactures waterproof laptop backpacks. The standard cost card of a single backpack is...
True Colour Inc. manufactures waterproof laptop backpacks. The standard cost card of a single backpack is given below:    Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials ? $ 4.00 per yard $ ? Direct labor ? ? ? Variable manufacturing overhead ? $ 2 per direct labor-hour ? Total standard cost per unit $ ? Overhead is applied to production on the basis of direct labor-hours. During March, 700 backpacks were manufactured and sold. Selected...
) A partial standard cost card for the single product produced by Macentoch Company is given...
) A partial standard cost card for the single product produced by Macentoch Company is given below: Direct materials: 3 pounds @ $8 per pound Direct labor: ? hours @ ? Per hour Last period the company produced 4,000 units of product. Cost and other data associated with this production are given below: Direct materials purchased and used, at cost $103,320 Direct labor cost incurred (10,400 hours) $120,640 Materials price variance $2,520 Unfavorable Labor efficiency variance $4,800 Unfavorable Total labor...
Jordan Corporation Inc. manufactures a single product and uses a standard cost system for control purposes....
Jordan Corporation Inc. manufactures a single product and uses a standard cost system for control purposes. The standard cost card for the product is as follows: Standard Cost Standard Cost Per Unit ($) Direct materials 2 metres @ $8.45 per metre $16.90 Direct labour 1.4 hours @ $16 per DLH 22.40 Variable overhead 1.4 hours @ $2.50 per DLH 3.50 Fixed overhead 1.4 hours @ $6 per DLH 8.40 Total cost $51.20 * DLH - Direct labour hours Some additional...
Pardoe, Inc., manufactures a single product. The company uses a standard cost system and has established...
Pardoe, Inc., manufactures a single product. The company uses a standard cost system and has established the following standards for one unit of product: Standard Quantity of inputs Standard Price or Rate per input Standard Cost per unit Direct materials 1.5 pounds $3.20 per pound $4.80 Direct labor 0.7 hours $5.00 per hour $3.50 Pardoe's budget for March used estimated production and sales of 2,900 units. During March, the following activity was recorded by the company: The company produced 3,000...
XYZ Company manufactures tables. A standard cost card for the manufacture of one table shows the...
XYZ Company manufactures tables. A standard cost card for the manufacture of one table shows the following: Standard Cost per Table: Direct material: 4 sq. ft. @ $3/sq. ft. $12 Direct labor: 2 hours @ $8/hr 16 Total prime costs $28 In November, the company produced 1,000 tables. Actual production costs and quantities were: Direct material: 3,900 sq. ft. @ $3.10/sq. ft. $12 Direct labor: 2,300 hours @ $7.80/hr 16 Required: Calculate the price and quantity variances for direct material...
A single card is drawb from a standard 52-card deck. What is the probability that the...
A single card is drawb from a standard 52-card deck. What is the probability that the card is either a) a seven, or an eight, or a ten? b) a heart, or a club, or a spade? c) a five, or an ace, or a heart? d) a queen, or an eight, or a club, or a spade?
1) A single card is drawn from a standard 52 card deck. Calculate the probability that...
1) A single card is drawn from a standard 52 card deck. Calculate the probability that a black card or an ace is drawn. (show answer as a reduced fraction #/#) 2)A professor knows from past experience that in a class of 36 students the time for students to complete an exam has an N(50,10) distribution. Suppose that he wants to allow sufficient time so that 98% of the students will complete the exam in the allotted time. How much...
Company X manufactures a single product for which the standard cost of one unit is as...
Company X manufactures a single product for which the standard cost of one unit is as follows: € Direct material (3.0 kg at €2 per kg)   6.00 Direct labour (1.2 hours at €10 per hour)   12.00 Manufacturing overheads 7.00 25.00 During January, the company produced 9,000 units and the actual costs were as follows: Costs:          € 24,000 kg of material    56,500 10,950 hours of labour        110,700 Overheads 61,700 228,900 Material price variance is                        ...
Buil Corporation manufactures a single product. The standard cost per unit of the product is as...
Buil Corporation manufactures a single product. The standard cost per unit of the product is as follows. Direct materials—2 pounds of plastic at $6 per pound $12 Direct labour—2 hours at $13 per hour 26 Variable manufacturing overhead 7 Fixed manufacturing overhead 5 ______ Total standard cost per unit $50 The master manufacturing overhead budget for the month based on the normal productive capacity of 20,000 direct labour hours (10,000 units) shows total variable costs of $70,000 ($3.50 per labour...
Belfast Industries manufactures a single product, the standard cost of which is: Direct materials – 6...
Belfast Industries manufactures a single product, the standard cost of which is: Direct materials – 6 kgs @ £4 kg £24.00 Direct labour – 2 hour @ £8 hour £16.00 Variable overhead – 2 hour @ £6 hr £12.00 Fixed overhead – 2 hour @ £10 hr £20.00 Total per unit £72.00 Other data relating to the standard cost: * The fixed overhead rate is based on a budgeted output of 4,000 units per month. * The standard selling price...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT