In: Finance
Your division is considering two projects with the following cash flows (in millions):
0 1 2 3
Project A - $25 $5 $10 $17
Project B -$20 $10 $9 $6
ANSWER THIS. What are the projects’ NPVs assuming the discount interest rate is 12%?
Please explain and show work
ANSWER THIS What are the projects’ IRRs?
Please explain and show work.
Net present value :
Project A :
NPV = Cash flow / ( 1 + r )1 + Cash flow / ( 1 + r )2 + Cash flow / ( 1 + r )n - initial investment
NPV = 5 / ( 1 + 0.12) + 10 / (1+0.12)2 + 17 / (1+0.12)3 - 25
= (5 / 1.12) + (10 / 1.2544) + ( 17 / 1.404928) - 25
= 4.464 + 7.971 + 12.100 - 25
= 24.535 - 25
= $-0.465
Project B :
NPV = 10 / ( 1 + 0.12) + 9 / (1+0.12)2 + 6 / (1+0.12)3 - 20
= ( 10 /1.12) + (9 / 1.2544) + (6 / 1.404928) - 20
= 8.928 + 7.174 + 4.2706 - 20
= 20.372 - 20
= $ 0.372
Internal rate of return ;
Project A :
Trial and error method , discount rate 11 %
NPV = 5 / ( 1 + 0.11) + 10 / (1+0.11)2 + 17 / (1+0.11)3 - 25
= 4.504 + 8.116 + 12.430 - 25
= 25.05 - 25
= 0.05
IRR = A + [( C-O) / (C -D ) ] * [B - A]
A = lower discount rate
C-O = lowest discount rate NPV
C = lowest discount rate total of cash flows
D =Higher discount rate cash flow total
B = Higher discount rate
IRR = 11 % + [( 0.05) / ( 25.05 - 20.37)] * [ 12 - 11]
= 11% + [ 0.05 / 4.678] * 1
= 11 % + (0.010 * 1)
= 11 % + 0.01
=11.01 %
Project B :
Discount rate @14%
NPV = 10 / ( 1 + 0.14) + 9 / (1+0.14)2 + 6 / (1+0.14)3 - 20
= 8.771+ 6.925+ 4.049 - 20
= 19.745 - 20
= -0.255
IRR = A + [( C-O) / (C -D ) ] * [B - A]
= 12 % + [ ( 0.37) / ( 20.37 - 19.74 )] * [ 14-12]
= 12% + [0.37 / 0.63] * 2
= 12% + (0.5873 *2 )
= 12% + 1.174
= 13.17 %
Project B have higher NPV than project A. it is accepted. project A should be rejected
Project B have higher IRRand project A have lower IRR