Question

In: Civil Engineering

Critically evaluate the engineering, procurement and construction (EPC) contract and the engineering, procurement and construction management...

Critically evaluate the engineering, procurement and construction (EPC) contract and the engineering, procurement and construction management (EPCM) contract as used in the civil engineering industry. Critically evaluate how each contracting strategy is used in the real world

Solutions

Expert Solution

While an EPC contract takes the form of a design and construction contract, the EPCM model can be regarded as a professional services contract. The EPCM contractor has a duty to ensure that the engineering and design of the project is in compliance with the projects technical and functional specifications

The fundamental difference is the role of the EPC or EPCM contractor. In an EPC contract, the EPC contractor develops the project from commencement to final completion. The owner or principal of the EPC project provides the EPC contractor with a detailed design including technical and functional specifications, in order for the EPC contractor to build and deliver the project to the "turn of the key", within a specified time period. This is why EPC contracts are often referred to as "turnkey" projects. The scope of work should be clearly defined in the contract documents; therefore, amendments to the scope of work should not be a common feature in EPC contracts. For this reason an EPC contract is often a fixed price contract or an all-encompassing lump sum contract. Any shortfall of costs is a risk that rests with the EPC contractor, making cost control their number one priority.

A further identifying feature of the EPC contract is that the EPC contractor enters into separate agreements with the contractors, vendors, sub-contractors, sub-vendors and so on. This is advantageous to the owner or principal of the project, as they will look to the EPC contractor to take full responsibility for the project and, in the event of a dispute between the EPC contractor and any party to the sub-agreements, to resolve the dispute without the owner or principal being required to be a party to the dispute. The EPC contractor will, in most cases, have a right of recourse against a party to a sub-agreement who was responsible for causing the loss or damage. The EPC contractor must ensure that its contracts mirror those that it has with the owner of principal.

In contrast to the EPC model, the EPCM contractor is not directly involved in the building and construction of the project, but is rather responsible for the detailed design and overall management of the project, on behalf of the owner or principal. While an EPC contract takes the form of a design and construction contract, the EPCM model can be regarded as a professional services contract.

The EPCM contractor has a duty to ensure that the engineering and design of the project is in compliance with the projects technical and functional specifications. Supervising, management and co-ordinating construction interface in accordance with a detailed schedule is the key responsibility of the EPCM contractor.

The EPCM contractor is responsible for establishing contractual arrangements on behalf of the owner or principal with other contractors, vendors, sub-contractors and sub-vendors, through a tender process. The EPCM contractor is contracted by the owner or principal for the construction management role, while the owner or principal is bound to various contractual relationships for construction related works. From an owner or principal's perspective, there lies a disadvantage in being bound to various contractual relationships in the event of a dispute. Unlike the EPC model, the owner or principal will more often than not find itself involved in a dispute with one or more of the other parties relating to the construction of the project, to whom the EPCM contractor must offer assistance.

In most instances, the EPCM model is structured on the basis of a cost-reimbursable fee structure or a unit rate fee structure. The former allows the EPCM contractor to be paid an upfront sum of money with additional fixed monthly payments, while the latter allows for an upfront sum of money with further payments to be made on completion of specified phases within the construction process.

Both the EPC and EPCM contracts can be highly beneficial to a project. Choosing the incorrect form of contract can have a major effect on the cost and risk associated with the project. The contract you choose to utilise requires a clear understanding of the objectives, scope of work, the role of each party and the contract structure as a whole.


Related Solutions

Critically evaluate the engineering, procurement and construction (EPC) contract and the engineering, procurement and construction management...
Critically evaluate the engineering, procurement and construction (EPC) contract and the engineering, procurement and construction management (EPCM) contract as used in the civil engineering industry. Critically evaluate how each contracting strategy is used in the real world
Determine when to use either the engineering, procurement and construction (EPC) contract model or the engineering,...
Determine when to use either the engineering, procurement and construction (EPC) contract model or the engineering, procurement and construction management (EPCM) contract model. When is it appropriate to use EPC and when is it appropriate to use EPCM. Provide recommendations on how to decide for civil engineering projects.
Given specific contract procurement conditions for a project, evaluate the factors that influence a contract pricing...
Given specific contract procurement conditions for a project, evaluate the factors that influence a contract pricing strategy and recommend the strategy that is best suited for the given conditions.
Construction Engineering question: Produce a environmental management plan Company has been awarded the contract for a...
Construction Engineering question: Produce a environmental management plan Company has been awarded the contract for a bridge replacement, including 2km approach resurfacing on each side and has placed you and your team in charge. Produce a environmental management plan. Thanks!!
critically analyse how IT and e-procurement are changing the role of procurement
critically analyse how IT and e-procurement are changing the role of procurement
1,Evaluate the accuracy and reliability of different research methods applied. 2. Critically evaluate the project management...
1,Evaluate the accuracy and reliability of different research methods applied. 2. Critically evaluate the project management process and appropriate research methodologies applied.
QUESTION 2: a) Critically examine the following terms in the context of contract management i. implied...
QUESTION 2: a) Critically examine the following terms in the context of contract management i. implied and express terms in contract ii. An article of Agreement in contract and why do we need them in contract? iii. An appendix (contract particulars) and addendum iv. Insolvency and termination of contract under JCT b. Compare and contrast the followings: practical completion and Sectional Completion and their impact under the JCT 2011 SBC/Q.
Essay question: "Discuss how the deposit contract makes banks susceptible to runs, and critically evaluate potential...
Essay question: "Discuss how the deposit contract makes banks susceptible to runs, and critically evaluate potential solutions to the problematic features of deposit contracts."
critically evaluate the impact of the recent financial crisis on modern risk management practices and comprehensively...
critically evaluate the impact of the recent financial crisis on modern risk management practices and comprehensively understand the changes which are currently being introduced into financial markets to comply with the new, post-crisis regulatory financial reform
Critically discuss the importance and techniques of foreign exchange risk management and evaluate the basic hedging...
Critically discuss the importance and techniques of foreign exchange risk management and evaluate the basic hedging strategies involved. Use examples with calculations to demonstrate your knowledge. (500 words)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT