Question

In: Accounting

Mosaic Company applies overhead using machine hours and reports the following information. Actual machine hours used...

Mosaic Company applies overhead using machine hours and reports the following information.

Actual machine hours used (AH) 4,900 hours
Standard machine hours (for actual production) (SH) 5,400 hours
Actual variable overhead rate per hour (AVR) $ 4.55
Standard variable overhead rate per hour (SVR) $ 4.40

QS 23-18A Total variable overhead cost variance LO P5

Compute the total variable overhead cost variance and classify it as favorable, unfavorable or no variance.

Compute the variable overhead spending variance and the variable overhead efficiency variance and classify each as favorable, unfavorable or no variance.

Solutions

Expert Solution

Working Notes:
Standard Overhead Cost
Standard Time Standard Rate Standard Cost per unit
5400 $                       4.40 $                   23,760
ACTUAL OVERHEAD EXPENSES
Actual Time Actual Rate Actual Cost
4900 $                       4.55 $                   22,295
Hrs Per Hours
Solution:
Variable OVH Cost variance =     V-OVH std. Cost - V-OVH Actual Cost
Variable OVH Cost variance =     $                   23,760 - $                22,295
Variable OVH Cost variance =     $                     1,465 Favorable
Variable OVH Spending variance =     Act. Hrs Worked   X   ( Act Ovh. Rate   - Std. Overhead rate   )
Variable OVH Spending variance =                             4,900 X   ( $                     4.55 - $                              4.40 )
Variable OVH Spending variance =                             4,900 X    $                     0.15
Variable OVH Spending variance =     $                   735.00 Unfavorable
Variable OVH Efficiency variance =     Std. Oveh Rate X   ( Actual Hrs - Standard Hours )
Variable OVH Efficiency variance =     $                       4.40 X   ( 4900 - 5400 )
Variable OVH Efficiency variance =     $                       4.40 X    500
Variable OVH Efficiency variance =     $                     2,200 Favorable

Related Solutions

Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs...
Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $300,000 for the year, and machine usage is estimated at 125,000 hours. For the year, $322,000 of overhead costs are incurred and 130,000 hours are used. Collapse question part (a) Compute the manufacturing overhead rate for the year. (Round answer to 2 decimal places, e.g. 1.25.) Manufacturing overhead rate $ per machine hour
Ikea Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs...
Ikea Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $456,789 4 for the year, and machine usage is estimated at 126,000 hours For the year, $432450 of overhead costs are incurred and 125,500 hours are used. What is the predetermined overhead rate What is the amount of overhead applied Has it been over or underapplied? Prepare the adjusting entry to adjust the cost of goods sold
Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs...
Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are estimated to total $283,725 for the year, and machine usage is estimated at 126,100 hours. For the year, $303,850 of overhead costs are incurred and 130,200 hours are used. Compute the manufacturing overhead rate for the year. (Round answer to 2 decimal places, e.g. 1.25.) Manufacturing overhead rate $ per machine hour What is the amount of under- or overapplied overhead at December...
Barnes Company applies overhead on the basis of machine hours. Given the...
Question 14 Barnes Company applies overhead on the basis of machine hours. Given the following data, compute overhead applied and the under- or overapplication of overhead for the period: Estimated annual overhead cost  $3,000,000 Actual annual overhead cost       $2,970,000 Estimated machine hours           300,000Actual machine hours  295,000 1) $2,950,000 applied and $20,000 overapplied 2) $3,000,000 applied and $20,000 overapplied 3) $2,950,000 applied and $20,000 underapplied 4) $2.970,000 applied and neither under- nor overappliedQuestion 21 Activity-based costing uses 1) one plantwide pool and a single cost driver. 2)...
Robert Company, which applies overhead to production on the basis of machine hours, reported the following...
Robert Company, which applies overhead to production on the basis of machine hours, reported the following data for the period just ended: Actual units produced: 12,000 Actual variable overhead incurred: $77,700 Actual machine hours worked: 18,800 Standard variable overhead cost per machine hour: $4.50 Robert estimates that it takes  1.5 hours manufacture a completed unit. Compute all standards and variances
The company applies overhead cost to jobs on the basis of machine-hours worked. For the current...
The company applies overhead cost to jobs on the basis of machine-hours worked. For the current year, the company estimated that it would work 75,000 machine-hours and incur $450,000 in manufacturing overhead cost. The following transactions were recorded for the year: a. Raw materials were purchased on account, $ 410,000 b. Raw materials were requisitioned for use in production, $ 380,000 ($360,000 direct materials and $20,000 indirect materials). c. The following costs were incurred for employees services: direct labor, $...
Martinez Corporation applies overhead based upon machine-hours. Budgeted factory overhead was $362,000 and budgeted machine-hours were...
Martinez Corporation applies overhead based upon machine-hours. Budgeted factory overhead was $362,000 and budgeted machine-hours were 24,000. Actual factory overhead was $393,000 and actual machine-hours were 27,000. Before disposition of under/overapplied overhead, the cost of goods sold was $610,000 and ending inventories were as follows:             Direct materials                    $ 80,000             WIP                                        200,000             Finished goods                       270,000                   Total                               $550,000 Required: a.   Determine the budgeted factory overhead rate per machine-hour. b.   Compute the over/underapplied overhead. c.   Prepare the journal entry to dispose of the variance using the write-off to cost of...
Schulz Corporation applies overhead based upon machine-hours. Budgeted factory overhead was $266,400 and budgeted machine-hours were...
Schulz Corporation applies overhead based upon machine-hours. Budgeted factory overhead was $266,400 and budgeted machine-hours were 18,500. Actual factory overhead was $287,920 and actual machine-hours were 19,050. Before disposition of under/overapplied overhead, the cost of goods sold was $560,000 and ending inventories were as follows: Direct Materials: $60,000 WIP: 190,000 Finished Goods: 250,000 Total: $500,000 1) Determine the budgeted factor overhead rate per machine-hour. 2) Compute the over/underapplied overhead. 3) Select the journal entry to dispose of the variance using...
Martin Corp. applies overhead based on machine hours. Budgeted factory overhead is $275,000 and budgeted machine...
Martin Corp. applies overhead based on machine hours. Budgeted factory overhead is $275,000 and budgeted machine hours were 19,000. Actual factory overhead was $270,000 and actual machine hours were 19,100. Before disposition of under/overapplied overhead, cost of goods sold was $500,000 and ending inventories were as follows: Direct materials50,000 WIP200,000 Finished Goods300,000 Total550,000 Determine the budgeted factory overhead rate per machine hour Compute the over/underapplied overhead Prepare the journal entry to dispose of the variance using the write-off to cost...
Western Company allocates $10 overhead to products based on the number of machine hours used. The...
Western Company allocates $10 overhead to products based on the number of machine hours used. The company uses a plantwide overhead rate with machine hours as the allocation base. Given the amounts below, how many machine hours does the company expect in department 2? Estimated: Department 1 Department 2 Manufacturing overhead costs $ 263,000 $ 163,000 Direct labor hours 9,300 DLH 25,000 DLH Machine hours 16,300 MH ? MH Multiple Choice 35,600 MH 146,730 MH 87,830 MH 94,500 MH 26,300...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT