For problem 1:
We have given the data for defective bicycle frame for 14 days like 3,2,1,3,2,2,8,2,0,3,5,2,0,4
Now take the mean of above given data
Mean=total sum/number of sum
Now derive the standard deviation for given data
Now mean of data is the control line value
Now find out the up control line and lower control line
Up control line=mean+(3*std deviation)
Lower control line=mean-(3* std deviation
For the bicycle frame problem no any consecutive point exception 5 and 6 on the same side of the control line so we can say that process is under control
For Scott paper test problem point 7,8 and 9 are on the same side of control line farther than (1*std deviation) from control line so the processes is not in control