In: Finance
Vanderheiden Inc. is considering two average-risk alternative ways of producing its patented polo shirts. Process S has a cost of $8,000 and will produce net cash flows of $5,000 per year for 2 years. Process L will cost $11,500 and will produce cash flows of $4,000 per year for 4 years. The company has a contract that requires it to produce the shirts for 4 years, but the patent will expire after 4 years, so the shirts will not be produced after 4 years. Inflation is expected to be zero during the next 4 years. If cash inflows occur at the end of each year, and if Vanderheiden's cost of capital is 10 percent, by what amount will the better project increase Vanderheiden's value? a. $ 677.69 b. $1,098.89 c. $1,179.46 d. $1,237.76 e. $1,312.31
Formula sheet
A | B | C | D | E | F | G | H | I | J | K | L |
2 | |||||||||||
3 | The value increased by the project will be the NPV of the project. | ||||||||||
4 | Since patent will expire in four years, therefore project life is 4 Year. | ||||||||||
5 | Process S has life of 2 Years and will be replaced after 2 Years. | ||||||||||
6 | |||||||||||
7 | Cash Flow of process S will be as follows: | ||||||||||
8 | Year | 0 | 1 | 2 | 3 | 4 | |||||
9 | Cash Flow | -8000 | 5000 | =5000-8000 | 5000 | 5000 | |||||
10 | |||||||||||
11 | Cash Flow of process L will be as follows: | ||||||||||
12 | Year | 0 | 1 | 2 | 3 | 4 | |||||
13 | Cash Flow | -11500 | 4000 | 4000 | 4000 | 4000 | |||||
14 | |||||||||||
15 | Calculation of NPV of process S: | ||||||||||
16 | |||||||||||
17 | NPV of the project is present value of future cash flows discounted at required rate of return less the initial investment. | ||||||||||
18 | Given the following cash flow and WACC, NPV for the project can be calculated as follows: | ||||||||||
19 | Year | 0 | 1 | 2 | 3 | 4 | |||||
20 | Cash Flow (FCF) | =D9 | =E9 | =F9 | =G9 | =H9 | |||||
21 | Cost of capital (i) | 0.1 | |||||||||
22 | (P/F,i,n) for each year | =1/((1+$D21)^E19) | =1/((1+$D21)^F19) | =1/((1+$D21)^G19) | =1/((1+$D21)^H19) | ||||||
23 | Present Value of cash flows = FCF*(P/F,i,n) | =E20*E22 | =F20*F22 | =G20*G22 | =H20*H22 | ||||||
24 | Present value if future cash flows | =SUM(E23:H23) | =SUM(E23:H23) | ||||||||
25 | |||||||||||
26 | NPV for Project | =Present value fo future cash flows - Initial investment | |||||||||
27 | =D24+D20 | =D24+D20 | |||||||||
28 | |||||||||||
29 | Hence NPV for Project S | =D27 | |||||||||
30 | |||||||||||
31 | Calculation of NPV of process L: | ||||||||||
32 | |||||||||||
33 | NPV of the project is present value of future cash flows discounted at required rate of return less the initial investment. | ||||||||||
34 | Given the following cash flow and WACC, NPV for the project can be calculated as follows: | ||||||||||
35 | Year | 0 | 1 | 2 | 3 | 4 | |||||
36 | Cash Flow (FCF) | =D13 | =E13 | =F13 | =G13 | =H13 | |||||
37 | Cost of capital (i) | 0.1 | |||||||||
38 | (P/F,i,n) for each year | =1/((1+$D37)^E35) | =1/((1+$D37)^F35) | =1/((1+$D37)^G35) | =1/((1+$D37)^H35) | ||||||
39 | Present Value of cash flows = FCF*(P/F,i,n) | =E36*E38 | =F36*F38 | =G36*G38 | =H36*H38 | ||||||
40 | Present value if future cash flows | =SUM(E39:H39) | =SUM(E23:H23) | ||||||||
41 | |||||||||||
42 | NPV for Project | =Present value fo future cash flows - Initial investment | |||||||||
43 | =D40+D36 | =D24+D20 | |||||||||
44 | |||||||||||
45 | Hence NPV for Project L | =D43 | |||||||||
46 | |||||||||||
47 | Since NPV of the project S is higher therefore project S is better project. | ||||||||||
48 | Hence value added by better project is | =D29 | |||||||||
49 | Thus option (d) is correct. | ||||||||||
50 | |||||||||||
51 |