In: Accounting
The following information concerns production in the Baking Department for March. All direct materials are placed in process at the beginning of production.
ACCOUNT Work in Process—Baking Department | ACCOUNT NO. | ||||||||
Date | Item | Debit | Credit | Balance | |||||
Debit | Credit | ||||||||
Mar. | 1 | Bal., 5,100 units, 3/5 completed | 11,985 | ||||||
31 | Direct materials, 91,800 units | 174,420 | 186,405 | ||||||
31 | Direct labor | 47,650 | 234,055 | ||||||
31 | Factory overhead | 26,798 | 260,853 | ||||||
31 | Goods finished, 93,000 units | 250,947 | 9,906 | ||||||
31 | Bal. ? units, 4/5 completed | 9,906 |
a. Based on the above data, determine each cost listed below. Round "cost per equivalent unit" answers to the nearest cent.
1. Direct materials cost per equivalent unit. | $ |
2. Conversion cost per equivalent unit. | $ |
3. Cost of the beginning work in process completed during March. | $ |
4. Cost of units started and completed during March. | $ |
5. Cost of the ending work in process. | $ |
b. Assuming that the direct materials cost is
the same for February and March, did the conversion cost per
equivalent unit increase, decrease, or remain the same in
March?
Increase
UNITS TO ACCOUNT FOR: | ||||||
Beginning Work in Process units | 5,100 | |||||
Add: Units Started in Process | 91,800 | |||||
Total Units to account for: | 96,900 | |||||
UNITS TO BE ACCOUNTED FOR: | ||||||
Units completed from Beginning WIP | 5100 | |||||
Units started and completed | 87,900 | |||||
Ending Work in Process | 3,900 | |||||
Total Units to be accounted for: | 96,900 | |||||
Equivalent Units: | ||||||
Material Cost | Conversion | |||||
% Completion | Units | % Completion | Units | |||
Units completed from Beg. WIP | 0% | 0 | 40% | 2,040 | ||
Units started and completed | 100% | 87,900 | 100% | 87,900 | ||
Ending Work in Process | 100% | 3,900 | 80% | 3,120 | ||
Total Equivalent units | 91,800 | 93,060 | ||||
COST PER EQUIVALENT UNIT: | ||||||
Material | Conversion | |||||
Total cost added during the year | 174,420 | 74,448 | ||||
Equivalent Units | 91,800 | 93,060 | ||||
Cost per Equivalent unit | 1.9 | 0.8 | ||||
TOTAL COST ACCOUNTED FOR: | ||||||
Units Completed from Beginning WIP (5100 units) | ||||||
Equivalent unit | Cost per EU | Total Cost | ||||
Beginning Cost | 11985 | |||||
Material | 0 | 1.9 | 0 | |||
Conversion Cost | 2,040 | 0.8 | 1632 | |||
Cost of units completed from Beg WIP | 13617 | |||||
Units started and Transferred out (87900 units) | ||||||
Equivalent unit | Cost per EU | Total Cost | ||||
Material | 87,900 | 1.9 | 167010 | |||
Conversion Cost | 87,900 | 0.8 | 70320 | |||
Total Cost of Units completed and transferred out: | 237330 | |||||
Ending Work in process (3,900 units) | ||||||
Equivalent unit | Cost per EU | Total Cost | ||||
Material | 3,900 | 1.9 | 7410 | |||
Conversison Cost | 3,120 | 0.8 | 2496 | |||
Total cost of Ending Work in process: | 9,906 | |||||
Total Cost of completed units | 250,947 | |||||
Req b: | ||||||
Total Beginning Cost | 11985 | |||||
Less: Material cost (5100*1.90) | 9690 | |||||
Conversion cost | 2295 | |||||
Divide: Equivalent units of conversion | 3060 | (5100*60%) | ||||
Conversion cost per unit | 0.75 | |||||
The converesion cost has been increased | ||||||