The Gorman Manufacturing Company must decide whether to manufacture a component part at its Milan, Michigan,...


The Gorman Manufacturing Company must decide whether to manufacture a component part at its Milan, Michigan, plant or purchase the component part from a supplier. The resulting profit is dependent on the demand for the product. The following payoff table shows the projected profit (in thousands of dollars):

State of Nature
Low Demand Medium Demand High Demand
Decision Alternative s 1 s 2 s 3
Manufacture, d 1 -20 40 100
Purchase, d 2 10 45 70

The state-of-nature probabilities are P(s1) = 0.50, P(s2) = 0.40, and P(s3) = 0.10

(a) Use a decision tree to recommend a decision.
- Select your answer -Manufacture component partPurchase component partItem 1
(b) Use EVPI to determine whether Gorman should attempt to obtain a better estimate of demand. Enter your answer in thousands dollars. For example, an answer of $200 thousands should be entered as 200,000.
Gorman - Select your answer -shouldshould notItem 2 attempt to obtain a better estimate of demand, as the additional information could be worth up to $ for Gorman.
(c)

A test market study of the potential demand for the product is expected to report either a favorable (F) or unfavorable (U) condition. The relevant conditional probabilities are as follows:

P(F|s1) = 0.10 P(U|s1) = 0.90
P(F|s2) = 0.40 P(U|s2) = 0.60
P(F|s3) = 0.60 P(U|s3) = 0.40

What is the probability that the market research report will be favorable? [Hint: We can find this value by summing the joint probability values as follows: P(F) = P(F∩s1) + P(F∩s2) + P(F∩s3) = P(s1)P(F|s1) + P(s2)P(F|s2) + P(s3)P(F|s3) .] If required, round your answer to three decimal places.

(d) What is Gorman’s optimal decision strategy? Choose the correct option.
A. Conduct test market, and manufacture component part, regardless of the market research report
B. Conduct test market, and purchase component part, regardless of the market research report
C. Conduct test market, and manufacture component part if market is favorable, or purchase component part if market is unfavorable
D. Do not conduct test market, and purchase component part
E. Do not conduct test market, and manufacture component part

- Select your answer -ABCDEItem 5

(e) What is the expected value of the market research information? Enter your answer in thousands dollars. For example, an answer of $200 thousands should be entered as 200,000. If your answer is zero, enter “0”.
$

Solutions

Expert Solution


Related Solutions

A firm must decide whether to make a component part in-house or to contract it out...
A firm must decide whether to make a component part in-house or to contract it out to an independent supplier. Manufacturing the part requires a nonrecoverable investment in specialized assets. The most efficient suppliers are located in countries with currencies that many foreign exchange analysts expect to appreciate substantially over the next decade. What are the pros and cons of (a) manufacturing the component in-house and (b) outsourcing manufacturing to an independent supplier? Which option would you recommend and why?...
Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it...
Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CIO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2018. 1. 8,100 units of CIO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CIO unit were: direct materials $4.58, direct labor...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 8,100 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...
The management of Pina Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Pina Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 7,900 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...
The management of Swifty Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Swifty Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 7,900 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...
The management of Borealis Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Borealis Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called WISCO, is a component of the company's finished product. The following information was collected from the records and production data for the year ending December 31, 2016. 8,000 units of WISCO were produced in the Machining Department. Variable manufacturing costs applicable to the production of each WISCO unit were: direct materials $4.80, direct...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT