In: Finance
Cantelevellers plc’s primary financial objective is to maximize the wealth of its shareholders. The business specializes in the development and assembly of high quality television sets. It normally subcontracts manufacture of the components of each set, carrying out the final assembly itself.
Recently the business has developed a new TV set that has been named Flatview and a decision now needs to be taken as to whether to take it into production. The following data are available:
Each Flatview set requires the use of
one component F451.
Prepare a schedule that derives the annual net relevant cash flows arising from the Flatview project, and use this to assess the project on the basis of its net present value as at 31 December 20X3.
Ignore any factors (such as taxation) that are not referred to in the question.
1) What i the Net Relevant Cash flow arising from Flatview Project.
The following table shows the calculation for Flatview project.
Particulars | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 |
Sales in Units - A | £ - | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 |
Selling price per unit - B | £ - | £ 2,000 | £ 2,000 | £ 2,000 | £ 2,000 | £ 2,000 |
Sales in value C = AxB | £ - | £ 3,000,000 | £ 3,000,000 | £ 3,000,000 | £ 3,000,000 | £ 3,000,000 |
F451 Material cost per Unit - D | £ - | £ 120 | £ 120 | £ 120 | £ 120 | £ 120 |
Other Mateial cost per Unit - E | £ - | £ 260 | £ 260 | £ 260 | £ 260 | £ 260 |
F451 Material quantity required - F | £ - | 1,000 | 1,500 | 1,500 | 1,500 | 1,500 |
F451 Material cost G = D x F | £ - | £ 120,000 | £ 180,000 | £ 180,000 | £ 180,000 | £ 180,000 |
Other Material cost H = Ax E | £ - | £ 390,000 | £ 390,000 | £ 390,000 | £ 390,000 | £ 390,000 |
Opportunity cost on F451* - 500 Units @ 100/Unit - I | £ - | £ - | £ 50,000 | £ - | £ - | £ - |
Total Material cost J = G+H+I | £ - | £ 510,000 | £ 620,000 | £ 570,000 | £ 570,000 | £ 570,000 |
Labour cost - K | £ - | £ 200,000 | £ 200,000 | £ 200,000 | £ 200,000 | £ 200,000 |
Overhead - L | £ - | £ 200,000 | £ 200,000 | £ 200,000 | £ 200,000 | £ 200,000 |
Lease rent -M | £ - | £ 450,000 | £ 450,000 | £ 450,000 | £ 450,000 | £ 450,000 |
Cash from Operation N = C-J-K-L-M | £ - | £ 1,640,000 | £ 1,530,000 | £ 1,580,000 | £ 1,580,000 | £ 1,580,000 |
Initial Outflow - O | -£ 4,750,000 | £ - | £ - | £ - | £ - | £ - |
Salvage Value - P | £ - | £ - | £ - | £ - | £ - | £ 700,000 |
Net Relevant Cash flow N+O+P | -£ 4,750,000 | £ 1,640,000 | £ 1,530,000 | £ 1,580,000 | £ 1,580,000 | £ 2,280,000 |
Note:
i) The following costs are not considered as these are not relevant.
Type of cost | Amount in £ | Reason for not considering |
Development and market research | 3,000,000 | It is a sunk cost as it is already incurred. Hence it is not considered. |
ii) Initial outflow
Initial Outflow | 2013 |
Purchase of Machine | -£ 5,000,000 |
Savings on Labour compensation | £ 250,000 |
Total Initial Outflow | -£ 4,750,000 |
iii) Terminal Flow | |
Terminal Flow | 2018 |
Sale of Machine | £ 1,000,000 |
Compensation to Labourers | -£ 300,000 |
Total Terminal flow | £ 700,000 |
* iv) Opportunity cost on Material F451 - If the project doesnot go ahead, the stock of 500 units of F451 could have been retrurned to the supplier at £100 per unit. This is an opportunity cost and hence relevant for this project. It has been considered as outflow in 2015.
2) What is the Net Present Value (NPV) of the Project.
NPV of the project is derived at by discounting the relevant cash flows with the discounting factor (in this case, it will be 15%). The following table shows the NPV for the project.
Year | Cash flow - A | Discounting factor @ 15% - B | PV - AxB |
2013 | -£ 4,750,000 | 1 | -£ 4,750,000 |
2014 | £ 1,640,000 | 0.870 | £ 1,426,087 |
2015 | £ 1,530,000 | 0.756 | £ 1,156,900 |
2016 | £ 1,580,000 | 0.658 | £ 1,038,876 |
2017 | £ 1,580,000 | 0.572 | £ 903,370 |
2018 | £ 2,280,000 | 0.497 | £ 1,133,563 |
NPV (Sum) | £ 908,795 |
Discounting factor = 1/(1+i)^n | ||
i = Discounting rate (in this case 15%) | ||
n = Period (in this case 1 to 5). |
Conclusion - Since the NPV is positive, Cantelevellers plc can proceed with the Flatview project.