In: Accounting
v
The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows:
Code |
Description |
Time (hrs) |
Immediate Predecessor(s) |
A |
Find location; determine resource requirements |
20 |
None |
B |
Requisition of lumber and sand |
60 |
A |
C |
Dig and grade |
100 |
A |
D |
Saw lumber into appropriate sizes |
30 |
B |
E |
Position lumber in correct locations |
20 |
D, C |
F |
Nail lumber together |
10 |
E |
G |
Put sand in and under the equipment |
20 |
F |
H |
Put dirt around the equipment |
10 |
F |
I |
Put grass all over the garden, landscape, paint |
30 |
G, H |
Refer to the legend
LOADING...
for the activity that corresponds to each code.
Using the line drawing tool, draw a Gantt chart for activites E through I of the project.
020406080100120140160180200IHGFEDCBA
Answer:
Critical path: A,C,E,F,G,I
Duration: 185 hours
Explanation;
Network Activity on Nodo (AON)
Steps
Forward calculations
Start Node: ES=EF=0
Initial node. ES = 0; EF=ES+t
In the other nodes:
1) Earliest start time (ES) = max (EF of predecessors)
2) EF=ES+t
Backward calculations
End node: LF=EF; LS=LF- t
In the other nodes:
1) Last completion time (LF) = min (LS of successors)
2)LS=LF- t
Slack = LS - ES or LF - EF
Critical path: activities without slack
A,C,E,F,G,I
Duration: 185 hours