Question

In: Finance

Problem 12-21 WACC and NPV [LO 4] Hankins, Inc., is considering a project that will result...

Problem 12-21 WACC and NPV [LO 4]

Hankins, Inc., is considering a project that will result in initial aftertax cash savings of $6.5 million at the end of the first year, and these savings will grow at a rate of 3 percent per year indefinitely. The firm has a target debt–equity ratio of .64, a cost of equity of 13.4 percent, and an aftertax cost of debt of 5.9 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective approach and applies an adjustment factor of +1 percent to the cost of capital for such risky projects.

Calculate the WACC. (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
  
WACC             %

What is the maximum cost the company would be willing to pay for this project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
  
Present value            $

Solutions

Expert Solution

Solution:-

a) Calculation of WACC

WACC = Kd*(1-tax)* Wd+Ke*We

Where,

Kd*(1-tax) = After tax cost of debt = 5.9%

Ke= Cost of equity = 13.4%

Since the debt equity ratio =0.64

i.e Debt/Equity=0.64/1

Hence

Wd= Weight of debt = 0.64/1.64

We =Weight of equity= 1/1.64

Substituting the values we get

WACC= 5.9*0.64/1.64+13.4*1/1.64

WACC = 10.4731707%

Hence the WACC= 10.47%

The project discount rate= WACC + Adjustment

                                                               =10.4731707%+1%= 11.4731707%

Hence the project discount rate = 11.4731707%

b) calculation of maximum cost the company would be willing to pay for this project

In order to calculate PV of cash flow we can use formula for growing perpetuity

       PV of cash inflow = Cash flow/(RR-g)

Where Cash flow= $6.5 million

RR= Project discount rate = 11.4731707%

g= growth rate = 3%

Substituting the values we get,

Present value of cash inflow= $6,500,000 /(0.114731707-0.03)

                                  =$6,500,000 /0.0847317

                                  =$76,712,723.09

Hence the maximum cost the company will be willing to pay for this project =$76,712,723.09

Please feel free to ask if you have any query in the comment section.


Related Solutions

Problem 9-12 NPV and MACRS [LO 2] H. Cochran Enterprises is considering a new three-year expansion...
Problem 9-12 NPV and MACRS [LO 2] H. Cochran Enterprises is considering a new three-year expansion project that requires an initial fixed asset investment of $2,410,000. The fixed asset falls into the three-year MACRS class (MACRS schedule). The project is estimated to generate $1,775,000 in annual sales, with costs of $672,000. The project requires an initial investment in net working capital of $380,000, and the fixed asset will have a market value of $375,000 at the end of the project....
XYZ, Inc. is considering a 5 year, 12% WACC capital budgeting project under three scenarios. If...
XYZ, Inc. is considering a 5 year, 12% WACC capital budgeting project under three scenarios. If conditions are excellent, the cash flows from this project are expected to be $4,000 per year; under fair conditions, cash flows are projected at $2,500 per year; and under unfavorable conditions, cash flows are projected at ($600) per year. The initial investment outlay is $3,000 and the probabilities of these three conditions are 30%, 50% and 20%, respectively. Assume that XYZ has the option...
If you earn the WACC on a project, (IRR = WACC) or NPV = 0, what...
If you earn the WACC on a project, (IRR = WACC) or NPV = 0, what have you accomplished for your shareholders? 1A. A semiannual bond pays a 4.5 % coupon for the next 27 years. If investors want a 7.3% return, what are they willing to pay for the bond?
Rocket Inc. is considering a project that has the following cash flow and WACC data. WACC:...
Rocket Inc. is considering a project that has the following cash flow and WACC data. WACC: 10.00% Year 0    1 2 3 4 Cash flows -$1,000 $510 $440 $425 $405 What is the project's payback?    What is the project's discounted payback?    Is the project worthwhile to undertake? (Would you undertake the project?) Why?
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve...
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $491,000 is estimated to result in $190,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $58,000. The press also requires an initial investment in spare parts inventory of $21,600, along with an additional $3,600...
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve...
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $491,000 is estimated to result in $190,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $58,000. The press also requires an initial investment in spare parts inventory of $21,600, along with an additional $3,600...
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve...
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $491,000 is estimated to result in $190,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $58,000. The press also requires an initial investment in spare parts inventory of $21,600, along with an additional $3,600...
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve...
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $491,000 is estimated to result in $190,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $58,000. The press also requires an initial investment in spare parts inventory of $21,600, along with an additional $3,600...
Problem 10-12 NPV and Modified ACRS [LO1] Quad Enterprises is considering a new three-year expansion project...
Problem 10-12 NPV and Modified ACRS [LO1] Quad Enterprises is considering a new three-year expansion project that requires an initial fixed asset investment of $2.79 million. The fixed asset falls into the three-year MACRS class. The project is estimated to generate $2,110,000 in annual sales, with costs of $799,000. The project requires an initial investment in net working capital of $330,000, and the fixed asset will have a market value of $225,000 at the end of the project.    If...
1) Garrett Inc WACC is 10% Garrett inc is considering a project that will cost the...
1) Garrett Inc WACC is 10% Garrett inc is considering a project that will cost the company $1M. the project will provide after tax cash flows for the next 5 years : Y1: $0 Y2: $400,000 Y3: $500,000 Y4: $300,000 Y5: $200,000 A) what is the IRR for Garrett’s project? B) what is the payback for the Garrett project? 2) what is the terminal value of the following asset: cost: $1,000,000 accumulated depreciation: $750,000 projected scrap value: $300,000 company tax...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT