Question

In: Finance

Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve...

Problem 9-21 Cost-Cutting Proposals [LO 2]

CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $491,000 is estimated to result in $190,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $58,000. The press also requires an initial investment in spare parts inventory of $21,600, along with an additional $3,600 in inventory for each succeeding year of the project. The shop’s tax rate is 40 percent and its discount rate is 10 percent.

  

Calculate the NPV. (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

  

Net present value              $

Solutions

Expert Solution

Time line 0 1 2 3 4
Cost of new machine -491000
Initial working capital -21600
=Initial Investment outlay -512600
5 years MACR rate 20.00% 32.00% 19.20% 11.52% 17.28%
Savings 190000 190000 190000 190000
-Depreciation =Cost of machine*MACR% -98200 -2E+05 -94272 -56563.2 84844.8 =Salvage Value
-working capital to be maintained -3600 -3600 -3600 -3600
=Pretax cash flows 88200 29280 92128 129836.8
-taxes =(Pretax cash flows)*(1-tax) 52920 17568 55276.8 77902.08
+Depreciation 98200 157120 94272 56563.2
=after tax operating cash flow 151120 174688 149548.8 134465.28
reversal of working capital 36000
+Proceeds from sale of equipment after tax =selling price* ( 1 -tax rate) 34800
+Tax shield on salvage book value =Salvage value * tax rate 33937.92
=Terminal year after tax cash flows 104737.92
Total Cash flow for the period -512600 151120 174688 149548.8 239203.2
Discount factor= (1+discount rate)^corresponding period 1 1.1 1.21 1.331 1.4641
Discounted CF= Cashflow/discount factor -512600 137381.8 144370 112358.23 163379
NPV= Sum of discounted CF= 44889.30

Related Solutions

Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve...
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $491,000 is estimated to result in $190,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $58,000. The press also requires an initial investment in spare parts inventory of $21,600, along with an additional $3,600...
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve...
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $491,000 is estimated to result in $190,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $58,000. The press also requires an initial investment in spare parts inventory of $21,600, along with an additional $3,600...
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve...
Problem 9-21 Cost-Cutting Proposals [LO 2] CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $491,000 is estimated to result in $190,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $58,000. The press also requires an initial investment in spare parts inventory of $21,600, along with an additional $3,600...
Problem 10-21 Cost-Cutting Proposals [LO2] Masters Machine Shop is considering a four-year project to improve its...
Problem 10-21 Cost-Cutting Proposals [LO2] Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $420,000 is estimated to result in $166,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $66,000. The press also requires an initial investment in spare parts inventory of $27,000, along with an additional $3,450 in inventory for...
Problem 10-21 Cost-Cutting Proposals [LO2] Masters Machine Shop is considering a four-year project to improve its...
Problem 10-21 Cost-Cutting Proposals [LO2] Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $450,000 is estimated to result in $184,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $74,000. The press also requires an initial investment in spare parts inventory of $33,000, along with an additional $3,750 in inventory for...
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $423,000 is estimated to result in $158,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table) and it will have a salvage value at the end of the project of $59,000. The press also requires an initial investment in spare parts inventory of $16,400, along with an additional $3,400 in inventory for each succeeding year...
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $415,000 is estimated to result in $154,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table) and it will have a salvage value at the end of the project of $55,000. The press also requires an initial investment in spare parts inventory of $16,000, along with an additional $3,000 in inventory for each succeeding year...
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $497,000 is estimated to result in $196,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $61,000. The press also requires an initial investment in spare parts inventory of $22,200, along with an additional $4,200 in inventory for each succeeding year...
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $485,000 is estimated to result in $184,000 in Sales minus Costs. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $55,000. The press also requires an initial investment in spare parts inventory of $21,000, along with an additional $3,000 in inventory for each succeeding year of the project....
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $425,000 is estimated to result in $159,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table) and it will have a salvage value at the end of the project of $60,000. The press also requires an initial investment in spare parts inventory of $16,500, along with an additional $3,500 in inventory for each succeeding year...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT