Question

In: Finance

Using Excel (if applicable), A company is considering a project that has the following cash flow...

Using Excel (if applicable),

A company is considering a project that has the following cash flow and WACC data. Note: CF0, CF2, and CF4 are negative Should the company take on this project if its WACC is 15? Justify your answer using NPV, IRR, and MIRR.

WACC:

15%

Year

0   

1

2

3

4

Cash flows

- $15,000

$25,000

- $2,000

$12,000

- $1,000

Solutions

Expert Solution

Using NPV rule, the project will be accepted as NPV >0.

As the cash flows are unconventional with three negative cash outflows, IRR rule will not be applicable here as IRR assumes the future cash flows reinvested as IRR and assumes conventional cash flows.

Using MIRR rule, as MIRR > Discount rate, the project will be accepted.

Formulae

Formulae as above


Related Solutions

A company is considering a project that has the following cash flow data. The firm’s WACC...
A company is considering a project that has the following cash flow data. The firm’s WACC is 11%. Year 0     1   2   3   Cash flows -$1,000 $300 $400 $600 a) What is the project’s payback period? b) What is the project’s discounted payback period? c) What is the project’s NPV? d) What is the project’s Profitability Index? e) Compute the Internal Rate of Return.
Warr Company is considering a project that has the following cash flow data. What is the...
Warr Company is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's projected IRR can be less than the WACC or negative, in both cases it will be rejected. Year 0 1 2 3 4 Cash flows -$1565 $400 $400 $400 $400 a. 0.85% b. 0.76% c. 0.89% d. 0.91% e. 0.78%
Warr Company is considering a project that has the following cash flow data. What is the...
Warr Company is considering a project that has the following cash flow data. What is the project's IRR? Year 0 1 2 3 4 Cash flows -$1,415 $400 $400 $400 $400
Using Excel (if applicable), . A company is considering a new product that would require an...
Using Excel (if applicable), . A company is considering a new product that would require an investment of $10 million now, at t = 0. If the new product is well received, then the project would produce after-tax cash flows of $6 million at the end of each of the next 3 years (t = 1, 2, 3), but if the market did not like the product, then the cash flows would be only $2 million per year. There is...
Cremona Company is considering a project that has the following cash flow and WACC data. What...
Cremona Company is considering a project that has the following cash flow and WACC data. What is the project’s Discounted payback, NPV, and MIRR? Weighted Average Cost of Capital (WACC) of Cremona Company is 12% Year CF 0 (1,000,000) 1 350,000 2 600,000 3 200,000 4 350,000 5 300,000 Please explain & show work/steps
Cremona Company is considering a project that has the following cash flow and WACC data. What...
Cremona Company is considering a project that has the following cash flow and WACC data. What is the project’s Discounted payback, NPV, and MIRR? Weighted Average Cost of Capital (WACC) of Cremona Company is 12% Year CF 0 (1,000,000) 1 350,000 2 600,000 3 200,000 4 350,000 5 300,000
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow...
Mega Dynamics is considering a project that has the following cash flows: Year Project Cash Flow 0 ? 1 $2,000 2 3,000 3 3,000 4 1,500 The project has an IRR of 17% . The firm's cost of capital is 11 percent. What is the project's net present value (NPV)?
Spence Company is considering a project that has the following cash flow data, Year 0: -$1000,...
Spence Company is considering a project that has the following cash flow data, Year 0: -$1000, Year 1-5: $350 each, Year 6: -$300. The company is using a WACC of 8%. What is the NPV of the project . What is the IRR of the project? What’s the discounted payback of the project
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW    ...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW     0                         -60,000     1                         25,000     2                         25,000     3                         25,000     4                         25,000 If the appropriate discount rate is 11 ​percent, what is the​ project's discounted payback​ period in years?
Forecasting Cash Flow and Burn Rate Create a Cash Flow Forecast on Excel using the following...
Forecasting Cash Flow and Burn Rate Create a Cash Flow Forecast on Excel using the following assumptions: Forecast duration: Years 0 through 5, then Exit Unit Sales: Sell 2000 units your first year and increase 30% per year Price: $100/unit first year and increase 5% per year COGS: Calculate based on a 75% Gross Profit Margin NOTE: to complete the Operating Expense section, break it into two lines: Payroll and Other Payroll: Start with 2 employees in year 0 paid...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT