Question

In: Accounting

Exercise 17-15 Activity-based costing rates and allocations LO P3 A company has two products: standard and...

Exercise 17-15 Activity-based costing rates and allocations LO P3

A company has two products: standard and deluxe. The company expects to produce 38,375 standard units and 64,240 deluxe units. It uses activity-based costing and has prepared the following analysis showing budgeted cost and cost driver activity for each of its three activity cost pools.

Budgeted Activity of
Cost Driver
Activity Cost Pool Budgeted Cost Standard Deluxe
Activity 1 $ 108,500 2,500 5,250
Activity 2 $ 112,000 4,500 5,500
Activity 3 $ 98,600 3,000 2,800

   
Required:
1. Compute overhead rates for each of the three activities.
2. What is the expected overhead cost per unit for the standard units?
3. What is the expected overhead cost per unit for the deluxe units?
(Round activity rate and cost per unit answers to 2 decimal places.)

Solutions

Expert Solution


Related Solutions

Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following information applies to...
Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials Other Overhead Grinding $ 380,000 Polishing $ 145,000 Product modification 450,000 Providing power $ 205,000 System calibration 470,000 Additional information on the drivers for its production activities follows. Grinding 19,000 machine hours...
Jennifer Company has two products: A and B. The company uses activity-based costing
Jennifer Company has two products: A and B. The company uses activity-based costing. The estimated total cost and expected activity for each of the company's three activity cost pools are as follows: The activity rate under the activity based costing system for Supporting customers is closest to:
A company has two products: A and B. It uses activity-based costing and has prepared the...
A company has two products: A and B. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three acivity cot pools. Cost Pool Budgeted Cost Product A Product B Activity 1 $87,000 3,000 2,800 Activity 2 $62,000 4,500 5,500 Activity 3 $93,000 2,500 5,250 Annual Production and sales level of Product A is, 34,300 units, and the annual production and sales level of Product B is 69,550 Units. What is...
A company has two products: A1 and B2. It uses activity-based costing and has prepared the...
A company has two products: A1 and B2. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools: Budgeted Activity Activity Cost Pool Budgeted Cost Product A1 Product B2 Activity 1 $ 49,000 1,300 4,900 Activity 2 $ 64,000 2,340 4,860 Activity 3 $ 82,000 7,300 900 Annual production and sales level of Product A1 is 8,580 units, and the annual production and sales level of Product...
(LO 3) A company uses activity-based costing to determine the costs of its three products: A,...
(LO 3) A company uses activity-based costing to determine the costs of its three products: A, B, and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table: Budgeted Activity Activity Cost Pool Budgeted Cost Product A Product B Product C Activity 1 $ 89,000 7,900 10,900 21,900 Activity 2 $ 64,000 8,900 16,900 9,900 Activity 3 $ 120,000 4,400 2,900 3,525 How much overhead will be assigned to...
Abel Company uses activity-based costing. The company has two products: A and B. The annual production...
Abel Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 200 units and of Product B is 400 units. There are three activity cost pools, with estimated costs and expected activity as follows: Expected ActivityActivity Cost PoolEstimated CostProduct AProduct BTotalActivity 1$16,660600100700Activity 218,4501,1007001,800Activity 39,7316016022022. The cost per unit of Product A is closest to which of the following? A. $27.91. B. $56.38. C. $141.04. D. $70.52.
Lindsey Company uses activity-based costing. The company has two products: A and B. The annual production...
Lindsey Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 9,000 units and of Product B is 8,000 units. There are three activity cost pools, with total cost and total activity as follows: Total Activity Activity Cost Pool Total Cost Product A Product B Total Activity 1 $31,000 100 520 620 Activity 2 $46,287 860 250 1,110 Activity 3 $156,750 840 3,910 4,750 The activity-based costing cost per...
1. A company has two products: A1 and B2. It uses activity-based costing and has prepared...
1. A company has two products: A1 and B2. It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools: Budgeted Activity Activity Cost Pool Budgeted Cost Product A1 Product B2 Activity 1 $ 63,000 2,700 6,300 Activity 2 $ 78,000 3,740 6,260 Activity 3 $ 110,000 8,700 2,300 Annual production and sales level of Product A1 is 9,980 units, and the annual production and sales level of...
Macpherson Limited produces two products: Standard and Deluxe. The company uses an activity-based costing system. Macpherson...
Macpherson Limited produces two products: Standard and Deluxe. The company uses an activity-based costing system. Macpherson produces 8,000 units of Standard and 2,000 units of Deluxe. The company uses two activity cost pools, with estimated total cost and activity as follows: Expected Activity Activity Cost Pool Estimated Cost Standard Deluxe #1 $12,000 500 250 #2 $24,000 400 1,200         What is the cost per unit of Macpherson under activity-based costing? a. $15.00 b. $11.00 c. $16.00 d. $1.75 What is the...
Assume a company that uses activity-based costing (ABC) has only two products – A and B....
Assume a company that uses activity-based costing (ABC) has only two products – A and B. The company does not have any organization-sustaining activities or unused capacity costs. The company’s total manufacturing overhead cost of $56,000 has been allocated to the three activities shown below: Setups Machining Packing Orders Activity measure quantity: Product A 20 1,000 150 Activity measure quantity: Product B 20 ? 350 Overhead cost per activity cost pool ? ? $ 10,000 Activity rate    $ 150 per...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT