Question

In: Accounting

Pillar Pillar Manufacturing Inc. ("the company") makes pillars, and is considering bidding on a job In...

Pillar Pillar Manufacturing Inc. ("the company") makes pillars, and is considering bidding on a job In order to submit this bid, the company needs to calculate the total cost of performing this job. Financial details for the proposed job are as follows:
Number of inspections
160
Number of machine hours
1,200
Number of direct labour hours
4,000
Direct materials
$42,000
Direct labour
$32,000
Number of material moves
50
The company has three different categories of overhead. The overhead costs for each of the categories for the next year are as follows:
Costs
Cost Driver
Expected Activity
Materials handling
$120,000
Material moves
8,000
Maintenance
$360,000
Machine hours
24,000
Inspection
$14,000
Inspections
4,000
The company applies overhead using a predetermined overhead rate based upon a budgeted direct labour hours of 100,000.
Using the above information answer all of the following questions.
Question 20 (1 point)
Question 20 options:
If the company used activity-based costing, calculate the total overhead cost that would be assigned for material handling to the job
Question 21 (1 point)
Question 21 options:
If the company used activity-based costing, calculate the total overhead cost that would be assigned for maintenance to the job
Question 22 (1 point)
Question 22 options:
If the company used activity-based costing, calculate the total overhead cost that would be assigned for inspections to the job
Question 23 (1 point)
Question 23 options:
If the company used activity-based costing, calculate the total of material cost + direct labour cost that would be assigned to the job
Question 24 (1 point)
Question 24 options:
If the company used activity-based costing, calculate the total cost that would be assigned to the job
Question 25 (2 points)
Question 25 options:
If the company allocated overhead to the job using a plantwide overhead rate, calculate the total overhead cost assigned to the job
Question 26 (1 point)
Question 26 options:
If the company allocated overhead to the job using a plantwide overhead rate, calculate the total cost assigned to the job
Question 27 (1 point)
It would not be appropriate to adopt an ABC policy if which of the following were true:
Question 27 options:

a)

All products consumed resources in a similar manner.




b)

The cost of developing individual cost pools was too great.




c)

All of the other answers are correct.




d)

The products being produced were quite similar.



Bottom of Form

Solutions

Expert Solution

Solution

Pillar Pillar Manufacturing Inc

Q20.

Calculation of overhead cost that would be assigned for material handling to the job using the Activity Based Costing:

Material handling cost = $120,000

Material moves = 8,000

Material handling activity rate = 120,000/8,000 = $15 per move

Material moves for the job = 50

Material handling cost assigned to the job =$15 x 50 = $750

Q21. Calculation of overhead cost that would be assigned for maintenance to the job using the Activity Based Costing:

Maintenance cost = $360,000

Machine hours = 24,000

Maintenance activity rate = 360,000/24,000 = $15 per MH

Machine hours for the job = 1,200

Maintenance cost assigned to the job = $15 x 1,200 MH

= $18,000

Q22. Calculation of overhead cost that would be assigned for inspections to the job using the Activity Based Costing:

Inspection cost = $14,000

Inspections = 4,000

Inspection activity rate = 14,000/4,000 = $3.50 per inspection

Inspections for the job = 160

Inspection cost assigned to the job = $3.50 x 160 = $560

Q23. Total of material cost + direct labor cost that would assigned to the job:

Direct material = $42,000

Direct labor = $32,000

Total of material cost + direct labor cost = 42,000 + 32,000 = $74,000

Q24. If the company uses activity based costing, computation of the total cost assigned to the job:

Total cost assigned to the job:

Direct materials $42,000

Direct labor = $32,000

Overhead costs assigned:

Materials handling = $750

Maintenance = $18,000

Inspections = $560

Total cost assigned = $93,310

If the company uses activity based costing, the total cost assigned to the job would be = $93,310

Q25. If the company allocated overhead to the job using a plantwide overhead rate, calculate the total overhead cost assigned to the job:

Plantwide overhead rate = total overhead cost/budgeted direct labor hours

Total overhead cost –

Materials handlings = $120,000

Maintenance = $360,000

Inspections = $14,000

Total overhead cost = $494,000

Budgeted direct labor hours = 100,000

Plantwide overhead rate = $494,000/100,000 = $4.94 per direct labor hour

Direct labor hours needed for the job = 4,000

Overhead cost assigned to the job using plantwide overhead rate = $4.94 x 4,000 DLH

= $19,760

Q26. If the company allocated overhead to the job using a plantwide overhead rate, calculation of the total cost assigned to the job:

Total cost assigned to the job –

Direct materials = $42,000

Direct labor = $32,000

Overhead assigned = $19,760

Total cost assigned = $93,760

Total cost assigned to the job using a plantwide overhead rate = $93,760

Q27. It would not be appropriate to adopt an ABC policy if which of the following were true:

Answer - Option C. All of the other answers are correct.

a. All the products consume resources in a similar manner.

b. The cost of developing individual cost pools was too great.

D the products being produced were quite similar.


Related Solutions

Monsoon Inc. is considering bidding on a government project. To do the project, the company must...
Monsoon Inc. is considering bidding on a government project. To do the project, the company must make an initial investment of $8 million to purchase the necessary equipment. The project will last for five years, at the end of which the equipment can be salvaged for $500,000. The equipment has a CCA rate of 30%. The bidding process for the project requires the firm to submit a bid for a constant amount of $X before-tax, to be remitted by the...
a. What is the three pillars policy? What tax incentives drive the third pillar? b. What...
a. What is the three pillars policy? What tax incentives drive the third pillar? b. What was the purpose of the introduction of compulsory superannuation contributions and the government’s superannuation guarantee scheme? c. Do you consider the superannuation guarantee scheme has significantly contributed to its objective?
Describe the three pillars of a good diversity and inclusion program. Give examples under each pillar.
Describe the three pillars of a good diversity and inclusion program. Give examples under each pillar.
5. The Basel II capital accord comprises a framework of three pillars. Pillar 1 established the...
5. The Basel II capital accord comprises a framework of three pillars. Pillar 1 established the minimum capital required by a commercial bank and incorporates three risk components: credit risk, operational risk and market risk. (a) Define credit risk. (b) Using the standardized approach to credit risk, explain how a commercial bank will use this method to calculate its minimum capital requirement.
Ross manufacturing produces machine parts on a job order basis. Ross gets orders after winning bidding....
Ross manufacturing produces machine parts on a job order basis. Ross gets orders after winning bidding. The bidding price is based on full cost with a 20% markup. This company has two service departments, A and B, and two production departments, C and D. The following table provides departmental information. Service Departments Production Departments A B C D Direct Costs $100,000 (total operating) $200,000 (total operating) $200,000 (overhead) $150,000 (overhead) Number of Employees 8 9 35 45 Maintenance Hours 2000...
1. Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead rate based on...
1. Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead rate based on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct labor hours are 85,000 and estimated factory overhead is $595,000. The following information is for September of the current year. Job A was completed during September, and Job B was started but not finished.      September 1, inventories   Materials inventory $ 7,600    Work-in-process inventory (All Job A) 31,400...
Polo Manufacturing Company has two jobs in the process – Job 10 and Job 11. Job...
Polo Manufacturing Company has two jobs in the process – Job 10 and Job 11. Job Cost Sheets are placed on the Answers Sheets. Company applies factory overhead using activity based costing. The predetermined overhead rates for activities are as follows:                                                                                           Machine Setup Activity                      Inspection Activity Overhead Rate                                                                 $120 per machine setup                    $75 per inspection    On the space provided on the answer sheet, provide journal entries for the following transactions. Complete Job Cost Sheets as needed. If you wish, you may...
Broucek Inc. makes baby furniture from fine hardwoods. The company uses a job-order costing system and...
Broucek Inc. makes baby furniture from fine hardwoods. The company uses a job-order costing system and predetermined overhead rates to apply manufacturing overhead cost to jobs. The predetermined overhead rate in the Preparation Department is based on machine hours, and the rate in the Fabrication Department is based on direct labor-hours. At the beginning of the year, the company’s management made the following estimates for the year:         Department    Preparation Fabrication   Machine-hours 99,000    30,000      Direct labor-hours 53,000...
A. The Green Company makes boats from wood. Job 489 is to build 40 rowboats. Job...
A. The Green Company makes boats from wood. Job 489 is to build 40 rowboats. Job 489 requires 1,000 pounds of wood costing $8 per pound. It requires 160 hours of direct labor costing $25 per hour. Also, use the following information about the company: Total manufacturing overhead cost expected for all jobs during the whole year $400,000 Estimated direct labor hours for all jobs during the whole year 40,000 Calculate the following if the Green Company uses the traditional...
Considering the following financial information for Atlas Awesome Manufacturing, Inc. and Delilah Superior Manufacturing Inc. Both...
Considering the following financial information for Atlas Awesome Manufacturing, Inc. and Delilah Superior Manufacturing Inc. Both companies are in the same industry and have identical operating income of $8.4 million. Atlas finances its $15 million in assets with $2 million debt ( on which it pays 9 percent interest) and 13 million in equity. Delilah finances its $15 million in assets with $12 million in debt ( on which it pays 8 percent interest). Both companies pay 32 percent tax...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT