In: Accounting
Solution
Pillar Pillar Manufacturing Inc
Q20.
Calculation of overhead cost that would be assigned for material handling to the job using the Activity Based Costing:
Material handling cost = $120,000
Material moves = 8,000
Material handling activity rate = 120,000/8,000 = $15 per move
Material moves for the job = 50
Material handling cost assigned to the job =$15 x 50 = $750
Q21. Calculation of overhead cost that would be assigned for maintenance to the job using the Activity Based Costing:
Maintenance cost = $360,000
Machine hours = 24,000
Maintenance activity rate = 360,000/24,000 = $15 per MH
Machine hours for the job = 1,200
Maintenance cost assigned to the job = $15 x 1,200 MH
= $18,000
Q22. Calculation of overhead cost that would be assigned for inspections to the job using the Activity Based Costing:
Inspection cost = $14,000
Inspections = 4,000
Inspection activity rate = 14,000/4,000 = $3.50 per inspection
Inspections for the job = 160
Inspection cost assigned to the job = $3.50 x 160 = $560
Q23. Total of material cost + direct labor cost that would assigned to the job:
Direct material = $42,000
Direct labor = $32,000
Total of material cost + direct labor cost = 42,000 + 32,000 = $74,000
Q24. If the company uses activity based costing, computation of the total cost assigned to the job:
Total cost assigned to the job:
Direct materials $42,000
Direct labor = $32,000
Overhead costs assigned:
Materials handling = $750
Maintenance = $18,000
Inspections = $560
Total cost assigned = $93,310
If the company uses activity based costing, the total cost assigned to the job would be = $93,310
Q25. If the company allocated overhead to the job using a plantwide overhead rate, calculate the total overhead cost assigned to the job:
Plantwide overhead rate = total overhead cost/budgeted direct labor hours
Total overhead cost –
Materials handlings = $120,000
Maintenance = $360,000
Inspections = $14,000
Total overhead cost = $494,000
Budgeted direct labor hours = 100,000
Plantwide overhead rate = $494,000/100,000 = $4.94 per direct labor hour
Direct labor hours needed for the job = 4,000
Overhead cost assigned to the job using plantwide overhead rate = $4.94 x 4,000 DLH
= $19,760
Q26. If the company allocated overhead to the job using a plantwide overhead rate, calculation of the total cost assigned to the job:
Total cost assigned to the job –
Direct materials = $42,000
Direct labor = $32,000
Overhead assigned = $19,760
Total cost assigned = $93,760
Total cost assigned to the job using a plantwide overhead rate = $93,760
Q27. It would not be appropriate to adopt an ABC policy if which of the following were true:
Answer - Option C. All of the other answers are correct.
a. All the products consume resources in a similar manner.
b. The cost of developing individual cost pools was too great.
D the products being produced were quite similar.