In: Accounting
Waterways Continuing Problem 12
At the end of June the manager of the B.C. manufacturing plant was provided with the following variance analysis report:
Budget | Actual | Variance | Favourable (F)/ Unfavourable (U) |
|||||
Production in units | 334,000 | 349,000 | 15,000 | F | ||||
Production costs: | ||||||||
Direct material | $694,720 | $707,184 | $(12,464) | U | ||||
Direct labour | 1,586,500 | 1,623,380 | (36,880) | U | ||||
Variable overhead costs | 133,600 | 138,869 | (5,269) | U | ||||
Fixed overhead costs | 200,400 | 195,845 | 4,555 | F | ||||
Total production costs | $2,615,220 | $2,665,278 | $(50,058) | U |
The manager immediately called the production supervisor, demanding
an explanation for the large unfavourable variance for the quarter.
The production supervisor was puzzled. He thought the cost-cutting
measures they had incorporated were beginning to work. He certainly
wasn’t expecting such a large discrepancy.
The standard rates the plant was using with its normal costing
system are summarized below.
Volume | Cost | |||||
Direct material | 1.30 | kg per unit | $1.60 | per kg | ||
Direct labour | 0.25 | hour per unit | $19.00 | per hour | ||
Predetermined overhead rate: | ||||||
Variable | 0.25 | hour per unit | $1.60 | per hour | ||
Fixed | 0.25 | hour per unit | $2.40 | per hour |
Other relevant information:
1. | A total of 461,000 kg of direct materials were purchased during the quarter at a cost of $1.80 per kilogram. | |
2. | A total of 441,990 kg of direct materials were used in production to manufacture 349,000 units. | |
3. | Payroll recorded 86,350 direct labour hours at an average cost of $18.80 per hour. |
Calculate the following production variances.
Material price variance | $ |
Neither favourable nor unfavourable/ Unfavourable/ Favourable |
|
Material quantity variance | $ |
Unfavourable/ Neither favourable nor unfavourable/ Favourable |
|
Labour price variance | $ |
Favourable/ Unfavourable/ Neither favourable nor unfavourable |
|
Labour efficiency variance | $ |
Neither favourable nor unfavourable/ Favourable/ Unfavourable |
|
Variable overhead variance | $ |
Favourable/ Neither favourable nor unfavourable/ Unfavourable |
Actual DATA for |
349000 |
units |
|
Quantity (AQ) |
Rate (AR) |
Actual Cost |
|
Direct Material |
461000 |
$ 1.80 |
$ 829,800.00 |
Direct labor |
86350 |
$ 18.80 |
$ 1,623,380.00 |
Variable Overhead |
86350 |
$ 1.61 |
$ 138,869.00 |
Standard DATA for |
349000 |
units |
|
Quantity (SQ) |
Rate (SR) |
Standard Cost |
|
[A] |
[B] |
[A x B] |
|
Direct Material |
( 1.3 yards x 349000 units)=453700 yards |
$ 1.60 |
$ 725,920.00 |
Direct labor |
( 0.25 hours x 349000 units)=87250 hours |
$ 19.00 |
$ 1,657,750.00 |
Variable Overhead |
( 0.25 hours x 349000 units)=87250 hours |
$ 1.60 |
$ 139,600.00 |
[1]
Material Price Variance |
||||||
( |
Standard Rate |
- |
Actual Rate |
) |
x |
Actual Quantity |
( |
$ 1.60 |
- |
$ 1.80 |
) |
x |
461000 |
-92200 |
||||||
Variance |
$ 92,200.00 |
Unfavourable-U |
OR
Material Price Variance |
||||||
( |
Standard Rate |
- |
Actual Rate |
) |
x |
Actual Quantity |
( |
$ 1.60 |
- |
$ 1.80 |
) |
x |
441990 |
-88398 |
||||||
Variance |
$ 88,398.00 |
Unfavourable-U |
[2]
Material Quantity Variance |
||||||
( |
Standard Quantity |
- |
Actual Quantity |
) |
x |
Standard Rate |
( |
453700 |
- |
441990 |
) |
x |
$ 1.60 |
18736 |
||||||
Variance |
$ 18,736.00 |
Favourable-F |
[3]
Labor Rate Variance |
||||||
( |
Standard Rate |
- |
Actual Rate |
) |
x |
Actual Labor Hours |
( |
$ 19.00 |
- |
$ 18.80 |
) |
x |
86350 |
17270 |
||||||
Variance |
$ 17,270.00 |
Favourable-F |
[4]
Labour Efficiency Variance |
||||||
( |
Standard Hours |
- |
Actual Hours |
) |
x |
Standard Rate |
( |
87250 |
- |
86350 |
) |
x |
$ 19.00 |
17100 |
||||||
Variance |
$ 17,100.00 |
Favourable-F |
[5] All Variable variances
Variable Overhead Spending Variance |
||||||
( |
Standard Cost |
- |
Actual Cost |
) |
||
( |
$ 139,600.00 |
- |
$ 138,869.00 |
) |
||
731 |
||||||
Variance |
$ 731.00 |
Favourable-F |
Variable Overhead Rate Variance |
||||||
( |
Standard Rate |
- |
Actual Rate |
) |
x |
Actual Labor Hours |
( |
$ 1.60 |
- |
$ 1.61 |
) |
x |
86350 |
-709 |
||||||
Variance |
$ 709.00 |
Unfavourable-U |
||||
Variable Overhead Efficiency Variance |
||||||
( |
Standard Hours |
- |
Actual Hours |
) |
x |
Standard Rate |
( |
87250 |
- |
86350 |
) |
x |
$ 1.60 |
1440 |
||||||
Variance |
$ 1,440.00 |
Favourable-F |