In: Accounting
Waterways Continuing Problem 12
At the end of June the manager of the B.C. manufacturing plant was provided with the following variance analysis report:
| Budget | Actual | Variance | Favourable (F)/ Unfavourable (U)  | 
|||||
| Production in units | 334,000 | 349,000 | 15,000 | F | ||||
| Production costs: | ||||||||
| Direct material | $694,720 | $707,184 | $(12,464) | U | ||||
| Direct labour | 1,586,500 | 1,623,380 | (36,880) | U | ||||
| Variable overhead costs | 133,600 | 138,869 | (5,269) | U | ||||
| Fixed overhead costs | 200,400 | 195,845 | 4,555 | F | ||||
| Total production costs | $2,615,220 | $2,665,278 | $(50,058) | U | 
The manager immediately called the production supervisor, demanding
an explanation for the large unfavourable variance for the quarter.
The production supervisor was puzzled. He thought the cost-cutting
measures they had incorporated were beginning to work. He certainly
wasn’t expecting such a large discrepancy.
The standard rates the plant was using with its normal costing
system are summarized below.
| Volume | Cost | |||||
| Direct material | 1.30 | kg per unit | $1.60 | per kg | ||
| Direct labour | 0.25 | hour per unit | $19.00 | per hour | ||
| Predetermined overhead rate: | ||||||
| Variable | 0.25 | hour per unit | $1.60 | per hour | ||
| Fixed | 0.25 | hour per unit | $2.40 | per hour | ||
Other relevant information:
| 1. | A total of 461,000 kg of direct materials were purchased during the quarter at a cost of $1.80 per kilogram. | |
| 2. | A total of 441,990 kg of direct materials were used in production to manufacture 349,000 units. | |
| 3. | Payroll recorded 86,350 direct labour hours at an average cost of $18.80 per hour. | 
Calculate the following production variances.
| Material price variance | $ | 
 Neither favourable nor unfavourable/ Unfavourable/ Favourable  | 
|
| Material quantity variance | $ | 
 Unfavourable/ Neither favourable nor unfavourable/ Favourable  | 
|
| Labour price variance | $ | 
 Favourable/ Unfavourable/ Neither favourable nor unfavourable  | 
|
| Labour efficiency variance | $ | 
 Neither favourable nor unfavourable/ Favourable/ Unfavourable  | 
|
| Variable overhead variance | $ | 
 Favourable/ Neither favourable nor unfavourable/ Unfavourable  | 
| 
 Actual DATA for  | 
 349000  | 
 units  | 
|
| 
 Quantity (AQ)  | 
 Rate (AR)  | 
 Actual Cost  | 
|
| 
 Direct Material  | 
 461000  | 
 $ 1.80  | 
 $ 829,800.00  | 
| 
 Direct labor  | 
 86350  | 
 $ 18.80  | 
 $ 1,623,380.00  | 
| 
 Variable Overhead  | 
 86350  | 
 $ 1.61  | 
 $ 138,869.00  | 
| 
 Standard DATA for  | 
 349000  | 
 units  | 
|
| 
 Quantity (SQ)  | 
 Rate (SR)  | 
 Standard Cost  | 
|
| 
 [A]  | 
 [B]  | 
 [A x B]  | 
|
| 
 Direct Material  | 
 ( 1.3 yards x 349000 units)=453700 yards  | 
 $ 1.60  | 
 $ 725,920.00  | 
| 
 Direct labor  | 
 ( 0.25 hours x 349000 units)=87250 hours  | 
 $ 19.00  | 
 $ 1,657,750.00  | 
| 
 Variable Overhead  | 
 ( 0.25 hours x 349000 units)=87250 hours  | 
 $ 1.60  | 
 $ 139,600.00  | 
[1]
| 
 Material Price Variance  | 
||||||
| 
 (  | 
 Standard Rate  | 
 -  | 
 Actual Rate  | 
 )  | 
 x  | 
 Actual Quantity  | 
| 
 (  | 
 $ 1.60  | 
 -  | 
 $ 1.80  | 
 )  | 
 x  | 
 461000  | 
| 
 -92200  | 
||||||
| 
 Variance  | 
 $ 92,200.00  | 
 Unfavourable-U  | 
||||
OR
| 
 Material Price Variance  | 
||||||
| 
 (  | 
 Standard Rate  | 
 -  | 
 Actual Rate  | 
 )  | 
 x  | 
 Actual Quantity  | 
| 
 (  | 
 $ 1.60  | 
 -  | 
 $ 1.80  | 
 )  | 
 x  | 
 441990  | 
| 
 -88398  | 
||||||
| 
 Variance  | 
 $ 88,398.00  | 
 Unfavourable-U  | 
||||
[2]
| 
 Material Quantity Variance  | 
||||||
| 
 (  | 
 Standard Quantity  | 
 -  | 
 Actual Quantity  | 
 )  | 
 x  | 
 Standard Rate  | 
| 
 (  | 
 453700  | 
 -  | 
 441990  | 
 )  | 
 x  | 
 $ 1.60  | 
| 
 18736  | 
||||||
| 
 Variance  | 
 $ 18,736.00  | 
 Favourable-F  | 
||||
[3]
| 
 Labor Rate Variance  | 
||||||
| 
 (  | 
 Standard Rate  | 
 -  | 
 Actual Rate  | 
 )  | 
 x  | 
 Actual Labor Hours  | 
| 
 (  | 
 $ 19.00  | 
 -  | 
 $ 18.80  | 
 )  | 
 x  | 
 86350  | 
| 
 17270  | 
||||||
| 
 Variance  | 
 $ 17,270.00  | 
 Favourable-F  | 
||||
[4]
| 
 Labour Efficiency Variance  | 
||||||
| 
 (  | 
 Standard Hours  | 
 -  | 
 Actual Hours  | 
 )  | 
 x  | 
 Standard Rate  | 
| 
 (  | 
 87250  | 
 -  | 
 86350  | 
 )  | 
 x  | 
 $ 19.00  | 
| 
 17100  | 
||||||
| 
 Variance  | 
 $ 17,100.00  | 
 Favourable-F  | 
||||
[5] All Variable variances
| 
 Variable Overhead Spending Variance  | 
||||||
| 
 (  | 
 Standard Cost  | 
 -  | 
 Actual Cost  | 
 )  | 
||
| 
 (  | 
 $ 139,600.00  | 
 -  | 
 $ 138,869.00  | 
 )  | 
||
| 
 731  | 
||||||
| 
 Variance  | 
 $ 731.00  | 
 Favourable-F  | 
||||
| 
 Variable Overhead Rate Variance  | 
||||||
| 
 (  | 
 Standard Rate  | 
 -  | 
 Actual Rate  | 
 )  | 
 x  | 
 Actual Labor Hours  | 
| 
 (  | 
 $ 1.60  | 
 -  | 
 $ 1.61  | 
 )  | 
 x  | 
 86350  | 
| 
 -709  | 
||||||
| 
 Variance  | 
 $ 709.00  | 
 Unfavourable-U  | 
||||
| 
 Variable Overhead Efficiency Variance  | 
||||||
| 
 (  | 
 Standard Hours  | 
 -  | 
 Actual Hours  | 
 )  | 
 x  | 
 Standard Rate  | 
| 
 (  | 
 87250  | 
 -  | 
 86350  | 
 )  | 
 x  | 
 $ 1.60  | 
| 
 1440  | 
||||||
| 
 Variance  | 
 $ 1,440.00  | 
 Favourable-F  | 
||||