In: Accounting
Waterways Continuing Problem 12
At the end of June the manager of the B.C. manufacturing plant was provided with the following variance analysis report:
Budget | Actual | Variance | Favourable (F)/ Unfavourable (U) |
|||||
Production in units | 302,000 | 319,000 | 17,000 | F | ||||
Production costs: | ||||||||
Direct material | $507,360 | $522,480 | $(15,120) | U | ||||
Direct labour | 1,283,500 | 1,323,000 | (39,500) | U | ||||
Variable overhead costs | 90,600 | 94,501 | (3,901) | U | ||||
Fixed overhead costs | 151,000 | 145,945 | 5,055 | F | ||||
Total production costs | $2,032,460 | $2,085,926 | $(53,466) | U |
The manager immediately called the production supervisor, demanding
an explanation for the large unfavourable variance for the quarter.
The production supervisor was puzzled. He thought the cost-cutting
measures they had incorporated were beginning to work. He certainly
wasn’t expecting such a large discrepancy.
The standard rates the plant was using with its normal costing
system are summarized below.
Volume | Cost | |||||
Direct material | 1.40 | kg per unit | $1.20 | per kg | ||
Direct labour | 0.25 | hour per unit | $17.00 | per hour | ||
Predetermined overhead rate: | ||||||
Variable | 0.25 | hour per unit | $1.20 | per hour | ||
Fixed | 0.25 | hour per unit | $2.00 | per hour |
Other relevant information:
1. | A total of 454,000 kg of direct materials were purchased during the quarter at a cost of $1.30 per kilogram. | |
2. | A total of 435,400 kg of direct materials were used in production to manufacture 319,000 units. | |
3. | Payroll recorded 78,750 direct labour hours at an average cost of $16.80 per hour. |
Calculate the following production variances.( Need the amount and
if its F, U or Neither Favourable/Unfavourable
Material price variance | $ |
FavourableNeither favourable nor unfavourableUnfavourable |
|
Material quantity variance | $ |
UnfavourableNeither favourable nor unfavourableFavourable |
|
Labour price variance | $ |
FavourableNeither favourable nor unfavourableUnfavourable |
|
Labour efficiency variance | $ |
FavourableUnfavourableNeither favourable nor unfavourable |
|
Variable overhead variance | $ |
UnfavourableFavourableNeither favourable nor unfavourable |