Question

In: Accounting

On July 1, 2014, Stuffing Inc. entered into a contract to build the longest ever Thanksgiving...

On July 1, 2014, Stuffing Inc. entered into a contract to build the longest ever Thanksgiving table. It is estimated that the table will cost $6,000,000 and will take 3 years to complete. The contract price was $7,800,000. The following information pertains to the construction period.

2014                            2015                           2016

Costs to date                                       $2,000,000                  $4,060,000                  $6,200,000

Estimated costs to complete               $4,000,000                 $1,740,000                  –0–        

Progress billings to date                     $1,200,000                 $4,800,000                  $7,800,000    

Cash collected to date                         $900,000                     $4,200,000                  $7,680,000

(a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of completion method is used.

(b) Prepare all necessary journal entries for 2016.

(c) Prepare a partial balance sheet for December 31, 2015, showing the balances in the receivables and inventory accounts.

Solutions

Expert Solution

1) calculation of gross profit
particulars 2014 2015 2016
cost incurred 2000000 2060000 2140000
cost incurred to date (1) 2000000 4060000 6200000
estimated cost (2) 4000000 1740000
total estimated cost (1)+(2) 6000000 5800000 6200000
percentage of completion 33% 70% 100%
cost to date/total estimated cost
income (1) 2574000 2886000 2340000
7800000*33% 7800000*70%-2574000 7800000*100%-2574000-2886000
cost incurred (2) 2000000 2060000 2140000
gross profit (1)-(2) 574000 826000 200000
2) Journal entries Debit credit
accounts receviable 3000000
bill on construction in progress 3000000
construction exp 2140000
construction in prosess 200000
long term contract revenue 2340000
cash 3480000
accounts receivable 3480000
partial balancehseet
accountd re rece 600000
construction in process 1400000

Related Solutions

Sonia Inc. entered into a contract with Lala Inc. on July 1, 2018 to construct an...
Sonia Inc. entered into a contract with Lala Inc. on July 1, 2018 to construct an office building. The total contract price for construction of the building is $400,000. The building was completed on December 31, 2020. Sonia’s fiscal year end is December 31. Below is related information of Sonia Inc. regarding this construction: 2018 2019 2020 Actual cost incurred during the year $35,000 $215,000 $175,000 Estimated costs to complete 315,000 170,000 0 Billings to Lala Inc. to date 72,000...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,020,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,020,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,660,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,080,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT