Question

In: Finance

Question 1 (a) Uzumba Maramba Pfungwa P/L has the following information about 3 projects A, B...

Question 1 (a) Uzumba Maramba Pfungwa P/L has the following information about 3 projects A, B and C that are being considered by Executive Committee Year Project A Project B Project C 0 ($15 000) ($15 000) (15 000) 1 11 000 3 500 42 000 2 7 000 8 000 (4 000) 3 4 800 13 000 -Yellowbone, the finance manager, believes all the 3 groups have risk characteristics similar to the average risk of the firm and hence the firm’s cost capital (12%) will apply. You have been asked to prepare a report covering the following: a) Calculate the payback period of Project A and B; b) Calculate the NPV of Projects A, B & C; c) Calculate the IRR for Projects A & B; d) Discuss the merits and demerits of accounting rate of return (ARR) as a project evaluation technique

Solutions

Expert Solution

a) Payback Period

Year Annual cash flows Cumulative Annual Cash flows Payback Period
Project A Project B Project A Project B Project A Project B
1 $                  11,000 $                    3,500 $                   11,000 $                  3,500
2 $                     7,000 $                    8,000 $                   18,000 $                11,500 1 Year and 6.8 Months 1 year + [(15000-11000)/7000]*12
3 $                     4,800 $                  13,000 $                   22,800 $                24,500 2 Year and 3.2 Months 2 year + [(15000-11500)/13000]*12
Total                       22,800 $                  24,500
Initial Investment                  15,000.0
Payback Period Time at which cumulative cash flow equals initial investment

--

b) Net Present Value (NPV)

Year Annual cash flows PV Factor @12% Present Value of cash flows
Project A Project B Project C Project A Project B Project C
0 $                 -15,000 $                -15,000 $                 -15,000 1 $                      -15,000 $                      -15,000 $                -15,000
1 $                  11,000 $                    3,500 $                   42,000 0.893 $                          9,823 $                          3,126 $                  37,506
2 $                     7,000 $                    8,000 $                   -4,000 0.797 $                          5,579 $                          6,376 $                   -3,188
3 $                     4,800 $                  13,000 $                            -   0.712 $                          3,418 $                          9,256 $                           -  
NPV-> $                          3,820 $                          3,758 $                  19,318

--

c) IRR

Year Annual cash flows PV Factor @12% PV of cash flows @12% PV Factor @18% PV of cash flows @18%
Project A Project B Project A Project B Project A Project B
0 $                 -15,000 $                -15,000 1 $              -15,000 $                      -15,000 1 $                -15,000 $                           -15,000
1 $                  11,000 $                    3,500 0.893 $                  9,823 $                          3,126 0.847 $                    9,317 $                               2,965
2 $                     7,000 $                    8,000 0.797 $                  5,579 $                          6,376 0.718 $                    5,026 $                               5,744
3 $                     4,800 $                  13,000 0.712 $                  3,418 $                          9,256 0.609 $                    2,923 $                               7,917
NPV-> $                  3,820 $                          3,758 NPV-> $                    2,266 $                               1,626

-

IRR =    R1 + [NPV1​ × (R2​−R1​) / (NPV1​−NPV2​)]
Project A Project B
12+(3820*(18-12))/(3820-2266) 12+(3758*(18-12))/(3758-1626)
IRR                         26.75                        22.58

where:

R1​,R2​=randomly selected discount rates

NPV1​=higher net present value

NPV2​=lower net present value​

--

d)

ARR is that it is easy to compute & understand. The main disadvantage of ARR is that it does not consider the time factor in terms of time value of money or risks for long term investments. The ARR is built on evaluation of profits and it can be easily manipulated with changes in depreciation methods. The ARR can give misleading information when evaluating investments of different size.

This technique is based on profits rather than annual cash flow. It ignores cash flow from investment. Therefore, it can be affected by non-cash items such as bad debts and depreciation when calculating profits. The change of methods for depreciation can be manipulated and lead to higher profits.

---

Hope you Understood.
If you have any doubt please leave a comment.

Thank you...


Related Solutions

Could you answer Question 3, and the information about question 1 has been given. Question 1...
Could you answer Question 3, and the information about question 1 has been given. Question 1 Bill has bought a new home in Canberra. He borrowed $600000 at a rate of 3.5% p.a., which is to be repaid in annual instalments over a thirty year period. The first instalment is due on 19 March 2020. What are Bill’s annual repayments? the annual repayment is  $32622.8 Question 3 The recently released recommendations of the Banking Royal Commission (the Royal Commission into Misconduct...
Real Analysis Conception Question 1. Lemma: if P is a subset of Q, then L(f,p)<=L(f,Q) and...
Real Analysis Conception Question 1. Lemma: if P is a subset of Q, then L(f,p)<=L(f,Q) and U(f,P)>=U(f,Q) why??? for P is a subset of Q, however, why the upper sum of U(f,P) is even bigger than or equal to U(f,Q) it doesn't make any sense. Please draw the geometric description to help with clear hand written 2. Let's assume the partition={x0,x1...xn} of the interval [a,b] what is the diference between m=inf{f(x):x is a element of [a,b]} and mk=inf{f(x):x is a...
1. You are given the following information about the dumpling market: P = -6Qd + 80...
1. You are given the following information about the dumpling market: P = -6Qd + 80 P = 14Qs + 10 a. Calculate the equilibrium quantity b. calculate the equilibrium price c. suppose that the government taxes dumplings by $10/dumpling. Calculate the new taxed equilibrium quantity, Qt. d. suppose that the government taxes dumplings by $10/dumpling. Calculate the new taxed equilibrium price, Pt. e. what is the price that producers receive after this tax is implemented? f. calculate consumer surplus...
INFORMATION Hattingh Limited has the option to invest in machinery in Projects A and B but...
INFORMATION Hattingh Limited has the option to invest in machinery in Projects A and B but finance is only available to invest in one of them. You are provided with the following projected data: Project A Project B Initial cost 500 000 500 000 Year 1 120 000 150 000 Year 2 160 000 150 000 Year 3 170 000 150 000 Year 4 180 000 150 000 Year 5 150 000 150 000 Depreciation per year 90 0000 100...
A process using a p-chart with L=3 has an in-control fraction defective of p=0.01. Sample size...
A process using a p-chart with L=3 has an in-control fraction defective of p=0.01. Sample size is 300. What is the probability of detecting a shift to an out-of-control value of p=0.05 for the first time on the second sample following the shift?
On the overlap of two events, suppose two events A and B , P(A)=1/2, P(B)=2/3, but...
On the overlap of two events, suppose two events A and B , P(A)=1/2, P(B)=2/3, but we have no more information about the event, what are the maximum and minimum possible values of P(A/B)
Q. Let A, B independent events, with P(A) = 1/2 and P(B) = 2/3. Now C...
Q. Let A, B independent events, with P(A) = 1/2 and P(B) = 2/3. Now C be an event with P(C) = 1/4, and suppose that P(A|C) = 1/3, P(B|?̅) =7/9, P(A∩B|?̅) = 7/18. (a) Calculate the P(A∩B) (b) Calculate the P(A|?̅) and P(B|C) (c) Calculate the P(A∩B|C) (d) Show if P(A∩B|C) equals P(A|C)P(B|C) or not.
Question 1 Consider the production function:F(L,K) = L^1/3 K^1/3 . Suppose the wage rate (price per...
Question 1 Consider the production function:F(L,K) = L^1/3 K^1/3 . Suppose the wage rate (price per unit of labour), w, is 2 and the capital rental rate (price per unit of capital), r, is 1. (a) Does this production function exhibit increasing, decreasing or constant returns to scale? Explain. (b) (If you would like to, you can do part (c) first and use your answer to (c) to answer this question.) Find the total cost of producing 32 units of...
q= K^1/3 L^1/3 w=$2, V=$16, k=27, p=$32 a)what's the firm level of labor and profit? b)what'd...
q= K^1/3 L^1/3 w=$2, V=$16, k=27, p=$32 a)what's the firm level of labor and profit? b)what'd you suggest for adjustment of short-run and future amount of K and L?
Question 1: Use the following information about the economy of Guyana in 2018 to answer the...
Question 1: Use the following information about the economy of Guyana in 2018 to answer the below question (NOTE - values are in Guyanese dollars): 2018 GDP - $689 billion 2018 Taxes - $117 billion 2018 Investment - $345 billion 2018 Government Spending - $144 billion 2018 Consumption - $454 billion What was the value of net capital inflow in 2018? (You can assume no transfer payments.) (Answers should be in the form "Z billion." Just enter "Z.") Question 2:...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT