In: Finance
Year Project A Project B
1 $5,000,000 $20,000,000
2 10,000,000 10,000,000
3 20,000,000 6,000,000
Show your work.
Answer:-
Initial investment = $ 20 million
NPV when cost of capital = 5 %
NPV of A = - $ 20 m + $ 5 m / 1.05 + $ 10 m / 1.052 + $
20 m / 1.053
NPV of A = - $ 20 m + $ 4.76 m + $ 9.07 m + $ 17.27 m
NPV of A = - $ 20 m + $ 31.1 m
NPV of A = $ 11.1 million
NPV of B = - $ 20 m + $ 20 m / 1.05 + $ 10 m /
1.052 + $ 6 m / 1.053
NPV of B = - $ 20 m + $ 19.05 + $ 9.07 m + $ 5.18 m
NPV of B = - $ 20 m + $ 33.3
NPV of B = $ 13.3 million
NPV when cost of capital = 10 %
NPV of A = - $ 20 m + $ 5 m / 1.1 + $ 10 m / 1.12 + $ 20
m / 1.13
NPV of A = - $ 20 m + $ 4.54 m + $ 8.26 m + $ 15.02 m
NPV of A = - $ 20 m + $ 27.82 m
NPV of A = $ 7.82 million
NPV of B = - $ 20 m + $ 20 m / 1.1 + $ 10 m /
1.12 + $ 6 m / 1.13
NPV of B = - $ 20 m + $ 18.18 + $ 8.26 m + $ 4.51 m
NPV of B = - $ 20 m + $ 30.95 m
NPV of B = $ 10.95 million
NPV when cost of capital = 15 %
NPV of A = - $ 20 m + $ 5 m / 1.15 + $ 10 m / 1.152 + $
20 m / 1.153
NPV of A = - $ 20 m + $ 4.35 m + $ 7.56 m + $ 13.15 m
NPV of A = - $ 20 m + $ 25.06 m
NPV of A = $ 5.06 million
NPV of B = - $ 20 m + $ 20 m / 1.15 + $ 10 m /
1.152 + $ 6 m / 1.153
NPV of B = - $ 20 m + $ 17.39 m + $ 7.56 m + $ 3.94 m
NPV of B = - $ 20 m + $ 28.89
NPV of B = $ 8.89 million
IRRs
IRR of A , NPV is set at zero
0 = - $ 20 m + $ 5 m / (1+ IRR) + $ 10 m / ( 1 + IRR )2
+ $ 20 m / (1+ IRR)3
IRR of A = 26.72 %
IRR of B , NPV is set at zero
0 = - $ 20 m + $ 20 m / (1+ IRR) + $ 10 m / ( 1 + IRR )2
+ $ 6 m / (1+ IRR)3
IRR of B = 47.63 %