Question

In: Statistics and Probability

Transrail is bidding on a project that it figures will cost $400,000 to perform. Using a...

Transrail is bidding on a project that it figures will cost $400,000 to perform. Using a 25% markup, it will charge $500,000, netting a profit of $100,000. However, it has been learned that another company, Rail Freight, is also considering bidding on the project. If Rail Freight does submit a bid, it figures to be a bid about $470,000. Transrail really wants this project and is considering a bid with only a 15% markup to $460,000 to ensure winning regardless of whether or not Rail Freight submits a bid.

a) Do a profit payoff table from Transrail's point of view

b) For this payoff table find Transrail's optimal decision using (1) the pessimistic approach, (2) the optimistic approach, and (3) minimax regret approach.

c) If Rail Freight is known to submit bids on only 25% of the projects it considers, what decision should Transrail make?

d)Given the information in (c), what is EVPI?

Solutions

Expert Solution

Answer:

Given that,

Transrail is bidding on a project that it figures will cost $400,000 to perform. Using a 25% markup, it will charge $500,000, netting a profit of $100,000.

However, it has been learned that another company, Rail Freight, is also considering bidding on the project. If Rail Freight does submit a bid, it figures to be a bid about $470,000.

Transrail really wants this project and is considering a bid with only a 15% markup to $460,000 to ensure winning regardless of whether or not Rail Freight submits a bid.

(a).

Do a profit payoff table from Transrail's point of view:

Profit payoff table from Transrail's point of view.

Decision Alternative Railfreight doesn't bid Railfreight bids
Bid $460000 60,000 60,000
Bid $500000 100000 0

(b).

For this payoff table find Transrail's optimal decision using (1) the pessimistic approach, (2) the optimistic approach, and (3) minimax regret approach:

(i).

Optimistic Approach -Maximax:

As per the optimistic approach, we determine the maximum payoff of each alternative and then select the alternative whose maximum payoff is the maximum of all of them.

Transrail should bid $5,00,000 to maximize its profit under optimistic approach.

Decision Alternative Railfreight doesn't bid Railfreight bids Max of row
Bid $460000 60,000 60,000 60,000
Bid $500000 100000 0 1,00,000 (Recommended decision)

(ii).

Conservative Approach - Maximin:

As per conservative approach, we find out the maxminimum apyoff of each alternative then select the alternative whose minimum payoff is the maximum of all of them.

Transrail should bid 4,60,000 to maximize its profit under conservative approach.

Decision Alternative Railfreight doesn't bid Railfreight bids Min of row
Bid $460000 60,000 60,000 60,000 (Recommended decision)
Bid $500000 100000 0 0

(iii).

Minimax regret approach:

Regret value of each decision alternative is computed by subtracting the value of particular decision from the maximum value of the corresponding state.

Decision corresponding to the minimum regret value is selected out of the averages or sum of values corresponding to each decision.

Transrail should bid $460000 to maximize its profit while minimizing regret.

Decision Alternative Railfreight doesn't bid Railfreight bids Min of row
Bid $460000 40,000 0 40,000 (Recommended decision)
Bid $500000 0 60,000 60,000

(c).

If Rail Freight is known to submit bids on only 25% of the projects it considers, what decision should Transrail make:

Payoff table under uncertainty:

In this case, it is given that there's a 25% probability of Railfreight bidding on the project. We calculate the EMV based on these probabilities And select the decision with the highest EMV. Decision B (bid 5,00,000) has the highest payoff.

Transrail should bid $4,60,000 to maximize its profit.

Decision Alternative Railfreight doesn't bid Railfreight bids Min of row
Bid $460000 60,000 60,000 60,000
Bid $500000 100000 0 75000 (Recommended decision)

(d).

Given the information in (c), what is EVPI:

EVP:

As expected value for a bid of 5,00,000 is greater than that for bidding 4,60,000, Transrail should bid 5,00,000.

A spy is worth up to15,000 the difference between expected values.


Related Solutions

PowerPlug Corp. is evaluating a project that will cost $400,000 initially and will generate free cash...
PowerPlug Corp. is evaluating a project that will cost $400,000 initially and will generate free cash flows of either $440,000 (with a probability of 30%) or $600,000 (with a probability of 70%) in one year. The risk-free rate is 2% and the project's required return is 12%. Assume perfect capital markets. Part 1: If the project is the only project of the firm, what is the initial value of equity (in $)? Part 2: If the company finances 30% of...
A 10-yr project has an initial cost of $400,000 for fixed assets. The fixed assets will...
A 10-yr project has an initial cost of $400,000 for fixed assets. The fixed assets will be depreciated to a $0 book value using a 20-yr straight line depreciation method. Each year, annual revenue is $60,000 and cost is $10,000. After 10 years, you will terminate the project. You expect to sell the the fixed assets for $250,000. The project is financed by 40% equity and 60% debt. The required rate of return on equity is 7% and the borrowing...
A 10-yr project has an initial cost of $400,000 for fixed assets. The fixed assets will...
A 10-yr project has an initial cost of $400,000 for fixed assets. The fixed assets will be depreciated to a $0 book value using a 20-yr straight line depreciation method. Each year, annual revenue is $50,000 and cost is $15,000. After 10 years, you will terminate the project. You expect to sell the the fixed assets for $250,000. The project is financed by 40% equity and 60% debt. The required rate of return on equity is 12% and the borrowing...
A 10-yr project has an initial cost of $400,000 for fixed assets. The fixed assets will...
A 10-yr project has an initial cost of $400,000 for fixed assets. The fixed assets will be depreciated to a $0 book value using a 20-yr straight line depreciation method. Each year, annual revenue is $60,000 and cost is $10,000. After 10 years, you will terminate the project. You expect to sell the the fixed assets for $250,000. The project is financed by 40% equity and 60% debt. The required rate of return on equity is 12% and the borrowing...
A 25-year project has a cost of $1,500,000 and has annual cash flows of $400,000 in...
A 25-year project has a cost of $1,500,000 and has annual cash flows of $400,000 in years 1-15, and $200,000 in years 16-25. The company's required rate is 14%. Given this information, calculate the payback of the project. 2.25 years 4.25 years 2.75 years 3.75 years 3.25 years
Monsoon Inc. is considering bidding on a government project. To do the project, the company must...
Monsoon Inc. is considering bidding on a government project. To do the project, the company must make an initial investment of $8 million to purchase the necessary equipment. The project will last for five years, at the end of which the equipment can be salvaged for $500,000. The equipment has a CCA rate of 30%. The bidding process for the project requires the firm to submit a bid for a constant amount of $X before-tax, to be remitted by the...
You are considering bidding on a project to make new cases for mobile phones. The project...
You are considering bidding on a project to make new cases for mobile phones. The project details include: Upfront costs of $350,000 for a new injection-moulding machine. 4 year life $30,000 in yearly pre-tax operating costs Initial investment of $50,000 in working capital Your company has a tax rate of 30% Your company's required rate of return is 10% At the end of 4 years you can sell the equipment for $30,000 There is no depreciation consideration for this equipment...
1)A 25- year project has a cost of $1,500,000 and has annual cash flows of $400,000...
1)A 25- year project has a cost of $1,500,000 and has annual cash flows of $400,000 in years 1-15, and $200,000 in years 16-25. The company's required rate is 14%. Given this information, calculate the profitability index of the project. Answer is 1.74 Can someone explain this with the steps?
The new equipment will cost $400,000. It would be depreciated to zero using straight-line depreciation over...
The new equipment will cost $400,000. It would be depreciated to zero using straight-line depreciation over a 5-year period. The estimated salvage value is $100,000 at the end of the project. The initial requirement in net working capital is $55,000, all of which will be recouped at the end of the project. The projected operating cash flows are $155,500 per year. The tax rate is 30%. What is the internal rate of return on this 5-year project? Group of answer...
Using the data provided, perform the steps below to complete the final project. On December 1,...
Using the data provided, perform the steps below to complete the final project. On December 1, 2019, SoccerBox Inc. started operations. The following transactions occurred during December 2019. NOTE: There are no beginning balances-this is a new company. Dec 1 Randol Espy invested $80,000 cash in the company for common stock. 2 SoccerBox purchased soccer equipment for $20,000 cash. 2 SoccerBox rented an old warehouse for $30,000 cash for the first year's (December 2019-November 2020) rent. 3 SoccerBox purchased $500...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT