Question

In: Finance

An investment project requires a net investment of $200 million. The project is expected to generate...

An investment project requires a net investment of $200 million. The project is expected to generate annual net cash flows of $25 million for the next 15 years with a one-time end of project cash flow of $3 million. The firm's cost of capital is 14 percent and marginal tax rate is 40 percent.

a) Evaluate the project using the NPV method and state whether or not the project should be accepted.

b) Evaluate the project using the IRR method and state whether or not the project should be accepted.

c) Evaluate the project using the PI method and state whether or not the project should be accepted.

Answers: NPV = -$46 million < 0 so Reject; IRR = 9.20 < 14% so Reject; PI = 0.77 < 1 so Reject

Please show the step by step formula included process for each part of the question! Thank you.

Solutions

Expert Solution

Calculation of NPV
14.00%
Year Annual Cash flow PV factor Present values
0 $            (200.00)                 1.0000 $                 (200)
1 $               25.00                 0.8772 $                     22
2 $               25.00                 0.7695 $                     19
3 $               25.00                 0.6750 $                     17
4 $               25.00                 0.5921 $                     15
5 $               25.00                 0.5194 $                     13
6 $               25.00                 0.4556 $                     11
7 $               25.00                 0.3996 $                     10
8 $               25.00                 0.3506 $                       9
9 $               25.00                 0.3075 $                       8
10 $               25.00                 0.2697 $                       7
11 $               25.00                 0.2366 $                       6
12 $               25.00                 0.2076 $                       5
13 $               25.00                 0.1821 $                       5
14 $               25.00                 0.1597 $                       4
15 $               25.00                 0.1401 $                       4
15 $                  3.00                 0.1401 $                       0
Net Present Value $                   (46)
Since NPV is negative, hence reject
Calculation of IRR
9.00% 10.00%
Year Total cash flow PV factor @ 9% Present values PV factor @ 10% Present values
0 $            (200.00) 1.000 $            (200.00) 1.000 $           (200.00)
1 $               25.00 0.917 $               22.94 0.909 $               22.73
2 $               25.00 0.842 $               21.04 0.826 $               20.66
3 $               25.00 0.772 $               19.30 0.751 $               18.78
4 $               25.00 0.708 $               17.71 0.683 $               17.08
5 $               25.00 0.650 $               16.25 0.621 $               15.52
6 $               25.00 0.596 $               14.91 0.564 $               14.11
7 $               25.00 0.547 $               13.68 0.513 $               12.83
8 $               25.00 0.502 $               12.55 0.467 $               11.66
9 $               25.00 0.460 $               11.51 0.424 $               10.60
10 $               25.00 0.422 $               10.56 0.386 $                 9.64
11 $               25.00 0.388 $                  9.69 0.350 $                 8.76
12 $               25.00 0.356 $                  8.89 0.319 $                 7.97
13 $               25.00 0.326 $                  8.15 0.290 $                 7.24
14 $               25.00 0.299 $                  7.48 0.263 $                 6.58
15 $               25.00 0.275 $                  6.86 0.239 $                 5.98
15 $                  3.00 0.275 $                  0.82 0.239 $                 0.72
$                  2.34 $               (9.13)
IRR =Lower rate + Difference in rates*(NPV at lower rate)/(Lower rate NPV-Higher rate NPV)
IRR '=9%+ (10%-9%)*(2.34082/(2.34082-(-9.1298)
9.20%
Since IRR is 9.20% which is less than 14% so reject.
calculation of profitability index
PI= Sum of PV of cash inflows/outflow
PI= 153.97/200
PI=                  0.77
Since PI is less than 1 so reject

Related Solutions

An investment project requires an initial outlay of $100,000, and is expected to generate annual cash...
An investment project requires an initial outlay of $100,000, and is expected to generate annual cash inflows of $28,000 for the next 5 years. The cost of capital is 12 percent. Determine the internal rate of return for the project (to the nearest tenth of one percent). a. 12.0% b. 12.6% c. 3.6% d. 12.4%
A project requires an investment of 10500 today and it is expected to generate after-tax cash...
A project requires an investment of 10500 today and it is expected to generate after-tax cash flows of 2,500 per year for the next 6 years. The company’s weighted average cost of capital is 12.2% per year. What is the projects net present value?
A project requires an initial investment of $1.2 million. It expects to generate a perpetual cash...
A project requires an initial investment of $1.2 million. It expects to generate a perpetual cash flow. The first year cash flow is expected at $100,000. The cash flows are then expected to grow at 1.25% forever. If the cost of capital for this project is 11%, what is the project's NPV? Group of answer choices -$0.480 million $0.265 million $7,177 million -$0.174 million -$0.265 million $0.174 million
A project requires an initial investment of $1.2 million. It expects to generate a perpetual cash...
A project requires an initial investment of $1.2 million. It expects to generate a perpetual cash flow. The first year cash flow is expected at $100,000. The cash flows are then expected to grow at 1.25% forever. The appropriate cost of capital for this project is 11%. What is the project's IRR and should it be accepted based on the IRR rule? Group of answer choices IRR is 9.6%; project should not be accepted IRR is 9.6%; project should be...
2. An investment requires an initial capital outlay of $12,000. The investment is expected to generate...
2. An investment requires an initial capital outlay of $12,000. The investment is expected to generate future cash flows of $1,000 one year hence, $2000 two years hence, $3,000 three years hence, $4,000 four years hence, $5,000 five years hence. Assume a 10% cost of capital. This is the homework question but I think its asking for net present value?
A project requires an investment of $330 million and has expected annual cash flows of $27...
A project requires an investment of $330 million and has expected annual cash flows of $27 million in perpetuity, starting in one year. In fact, future cash flows will be either $78 million or $16 million, in perpetuity. The company can end the project in 1 year after collecting the first cash flow and thus finding out the amount of future cash flows, and then sell all project assets for $330 million (after taxes). The appropriate discount rate for the...
A project requires an investment of $110 million and has expected annual cash flows of $17...
A project requires an investment of $110 million and has expected annual cash flows of $17 million in perpetuity, starting in one year. The appropriate discount rate for the project is 14%. The company can delay the project by 1 year. After 1 year, the company can invest $110 million to start the project and will know whether demand will be high or low. With high demand, future cash flows will be $22 million in perpetuity, starting in year 2,...
Q1) A project requires an initial investment of $5,000. It is expected that the project will...
Q1) A project requires an initial investment of $5,000. It is expected that the project will last 3 years and generate net cash flows of $3,500 for each of these years. If the discount rate for the project is 10%, the discounted payback period for the project.is: Select one: a. 1.63 years b. 2.55 years c. 1 year d. More than 3 years Q2) Capital rationing refers to the limiting of capital resources to under-performing divisions. Select one: True False...
You're considering a project with initial investment of $120,000. The project is expected to generate $65,000...
You're considering a project with initial investment of $120,000. The project is expected to generate $65,000 in cash flow for 3 years and then the company has to pay $50,000 to shut down the operation in year 4. If your cost of capital is 12%, would you carry out the project?
An investment project requires an investment fund of Rp 200 billion with an economic life of...
An investment project requires an investment fund of Rp 200 billion with an economic life of 5 years with no residual value. The project's capital cost is 11%. Every year the project is predicted to provide net income of: Year Net Income 1 Rp 20 billions 2 Rp 22 billions 3 Rp 24 billions 4 Rp 26 billions 5 Rp 28 billions By using the Accounting Rate of Return, NPV and MIRR methods, does the investment need to be carried...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT