A manager should always remember that he should undertake a
project only if the project has a positive NPV. Based on this fact
following points can be made -
- Even 1$ positive NPV indicates that a project must be
undertaken.
- For NPV to be positive Cost of Capital for the new project must
be less than the return generated by the project.
- Correctly estimating all the assumptions, like life of proect,
cost of equity, cost of debt etc is important to asses correct
value of NPV.
- However, one fact which is not considered by NPV is the
liquidity situation of the firm, if all the cashflow from the
project is coming a bit too late, it might cause liquidity risk for
the project in the initial years.
- Manager should also asses the Working Capital situation for the
project. If short term loans are utilized for long term project, it
might be a recipe for disaster.
- Manager should also consider the repair and maintenance as part
of evaluation of the CAPEX project.