In: Finance
A firm has the following project (assume that the expenditures
are at the end of the year in question):
1) The land will be acquired for $ 500,000 in year zero
2) The first year, $ 1 million will be spent on the construction of
the plant.
3) The equipment will be purchased on year 2 at a cost of $1.5
million.
4) The third year, $ 500,000 will be disbursed to start operating
the plant.
5) The plant and equipment will depreciate in a straight line for
the next 10 years, beginning year 4 (project ends in year 13). The
equipment and the physical construction will be worthless after
these 10 years, but the land can be sold at its original cost, when
the plant is closed.
6) The annual income (during the 10 years, that is, from the 4th to
the 13th year) is 2 million.
7) The annual fixed cost (excluding depreciation) will be $
200,000
8) The variable costs are annually of $ 300,000, assuming that the
plant operates at its maximum capacity during the 10 years
9) The tax rate will be 50 percent as it will be treated as if it
were a private business of the state itself (i.e. treat the state
as a company, that is, pure neoliberalism)
Calculate the Net Present Value of the Project, if the discount rate is 14%.
Year | Revenue (1) | Fixed Cost (Exl Depn) (2) | Variable Cost (3) | Deprecation (4) | Net Income Before Tax (5) = (1-2-3-4) | Net Income after Tax (6) =(5*50%) | Investment (7) | Working of Cashflow | Cash Flows (8) | DF @ 14% (9) | Present Value (10) = (8*9) |
0 | - | - | - | - | - | - | (500,000) | 7 - (500000) | (500,000) | 1 | (500,000) |
1 | - | - | - | - | - | - | (1,000,000) | 7 - (1000000) | (1,000,000) | 0.877192982 | (877,193) |
2 | - | - | - | - | - | - | (1,500,000) | 7 - (1500000) | (1,500,000) | 0.769467528 | (1,154,201) |
3 | - | - | - | - | - | - | (500,000) | 7 - (500000) | (500,000) | 0.674971516 | (337,486) |
4 | 2,000,000 | 200,000 | 300,000 | 200,000 | 1,300,000 | 650,000 | (6+4) --(650000+200000) | 850,000 | 0.592080277 | 503,268 | |
5 | 2,000,000 | 200,000 | 300,000 | 200,000 | 1,300,000 | 650,000 | (6+4) --(650000+200000) | 850,000 | 0.519368664 | 441,463 | |
6 | 2,000,000 | 200,000 | 300,000 | 200,000 | 1,300,000 | 650,000 | (6+4) --(650000+200000) | 850,000 | 0.455586548 | 387,249 | |
7 | 2,000,000 | 200,000 | 300,000 | 200,000 | 1,300,000 | 650,000 | (6+4) --(650000+200000) | 850,000 | 0.399637323 | 339,692 | |
8 | 2,000,000 | 200,000 | 300,000 | 200,000 | 1,300,000 | 650,000 | (6+4) --(650000+200000) | 850,000 | 0.350559055 | 297,975 | |
9 | 2,000,000 | 200,000 | 300,000 | 200,000 | 1,300,000 | 650,000 | (6+4) --(650000+200000) | 850,000 | 0.307507943 | 261,382 | |
10 | 2,000,000 | 200,000 | 300,000 | 200,000 | 1,300,000 | 650,000 | (6+4) --(650000+200000) | 850,000 | 0.26974381 | 229,282 | |
11 | 2,000,000 | 200,000 | 300,000 | 200,000 | 1,300,000 | 650,000 | (6+4) --(650000+200000) | 850,000 | 0.236617377 | 201,125 | |
12 | 2,000,000 | 200,000 | 300,000 | 200,000 | 1,300,000 | 650,000 | (6+4) --(650000+200000) | 850,000 | 0.207559102 | 176,425 | |
13 | 2,000,000 | 200,000 | 300,000 | 200,000 | 1,300,000 | 650,000 | 500,000 | (6+4+7)--(650000+200000+500000) | 1,350,000 | 0.182069388 | 245,794 |
NPV | 214,775 |
Calculation of Depreciation on Plant & Equipment |
(15,00,000+5,00,000)/10 |
200,000 |
Tax shield on depn every year from 4 th year = 200,000*50% |
NPV of the project is $214,775.