Question

In: Finance

Your company is evaluating the following 9 independent indivisible projects. The company’s capital budgeting for the...

Your company is evaluating the following 9 independent indivisible projects. The company’s capital budgeting for the year is limited to a maximum of $20,000.

Use solver with simplex linear programing method to find the set of projects that should be included in the capital budget. (Mark all that applies)

Project NPV cost
A 500.00 2,000.00
B 2,000.00 7,000.00
C 1,800.00 3,000.00
D 3,000.00 5,000.00
E 800.00 2,200.00
F 1,700.00 5,000.00
G 1,800.00 4,000.00
H 3,500.00 5,800.00
I 2,200.00 4,800.00

Solutions

Expert Solution

Whenever there is capital rationing i.e., limited availability of funds and independent projects, we choose PI to evaluate which projects should be chosen. Using PI, projects C, D, H & I should be chosen which totals the cost to $18600 and the NPV from these projects would total to $10500

Projects NPV Cost PI= (NPV / Cost)+1
A 500 2000                         1.25
B 2000 7000                         1.29
C 1800 3000                         1.60
D 3000 5000                         1.60
E 800 2200                         1.36
F 1700 5000                         1.34
G 1800 4000                         1.45
H 3500 5800                         1.60
I 2200 4800                         1.46

Related Solutions

AS A CAPITAL BUDGETING DIRECTOR OF DAYTON CORPORATION, YOU ARE EVALUATING TWO PROJECTS WITH THE FOLLOWING...
AS A CAPITAL BUDGETING DIRECTOR OF DAYTON CORPORATION, YOU ARE EVALUATING TWO PROJECTS WITH THE FOLLOWING NET CASH FLOWS: COST OF CAPITAL IS 12% YEAR 0 1 2 3 4 X $-2,000 $250 $380 $480 $2,000 Y $-1,800 $1,600 $600 $200 $420 Calculate Project X's DISCOUNT PAYBACK PERIOD (DPB) A. 1.57 B. 1.78 C. 3.47 D. 3.89 E. 5.22
A company is evaluating two independent projects for capital investment purposes. If the company has only...
A company is evaluating two independent projects for capital investment purposes. If the company has only $85 million to invest, and its required return is 10 percent by how much the company’s value will increase? All values are in millions. Project 1 Project 2 0 -50 -50 1 30 0 2 25 0 3 20 0 4 20 150 A) 52.45 million B) 26.62 million C) 79.07 million D) 60.77 million E) 45.33 million
You are evaluating a capital budgeting project for your company that is expected to last for...
You are evaluating a capital budgeting project for your company that is expected to last for six years. The project begins with the purchase of a $1,200,000 investment in equipment. You are unsure what method of depreciation to use in your analysis, straight-line depreciation or the 5-year MACRS accelerated method. Straight-line depreciation results in the cost of the equipment depreciated evenly over its life. The 5-year MACRS depreciation rates are 20%, 32%, 19%, 12%, 11%, and 6%. Your company's WACC...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$6,000 $2,000 $2,000 $2,000 $2,000 $2,000 Project N -$18,000 $5,600 $5,600 $5,600 $5,600 $5,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$12,000 $4,000 $4,000 $4,000 $4,000 $4,000 Project N -$36,000 $11,200 $11,200 $11,200 $11,200 $11,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$3,000 $1,000 $1,000 $1,000 $1,000 $1,000 Project N -$9,000 $2,800 $2,800 $2,800 $2,800 $2,800 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
7- CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this...
7- CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$15,000 $5,000 $5,000 $5,000 $5,000 $5,000 Project N -$45,000 $14,000 $14,000 $14,000 $14,000 $14,000 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$12,000 $4,000 $4,000 $4,000 $4,000 $4,000 Project N -$36,000 $11,200 $11,200 $11,200 $11,200 $11,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
12- CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this...
12- CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$15,000 $5,000 $5,000 $5,000 $5,000 $5,000 Project N -$45,000 $14,000 $14,000 $14,000 $14,000 $14,000 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to...
Capital budgeting criteria A firm with a 13% WACC is evaluating two projects for this year's...
Capital budgeting criteria A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$15,000 $5,000 $5,000 $5,000 $5,000 $5,000 Project N -$45,000 $14,000 $14,000 $14,000 $14,000 $14,000 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT