Question

In: Operations Management

R. C. Coleman R. C. Coleman distributes a variety of food products that are sold through...

R. C. Coleman

R. C. Coleman distributes a variety of food products that are sold through grocery store and supermarket outlets. The company receives orders directly from the individual outlets, with a typical order requesting the delivery of several cases of anywhere from 20 to 50 different products. Under the company's current warehouse operation, warehouse clerks dispatch order-picking personnel to fill each order and have the goods moved to the warehouse shipping area. Because of the high labor costs and relatively low productivity of hand order picking, management has decided to automate the warehouse operation by installing a computer-controlled order picking system, along with a conveyor system for moving goods from storage to the warehouse shipping area.

R. C. Coleman's director of material management has been named the project manager in charge of the automated warehouse system. After consulting with members of the engineering staff and warehouse management personnel, the director compiled a list of activities associated with the project. The optimistic, most likely, and pessimistic times (in weeks) have also been provided for each activity.

Activity

Description

Predecessor

Time (weeks)

Optimistic

a

Most Likely

m

Pessimistic

b

a

b

c

d

e

f

g

h

i

j

k

Determine Equipment needs

Obtain vendor proposals

Select vendor

Order system

Design new warehouse layout

Design warehouse

Design computer interface

Interface computer

Install system

Train system operators

Test system

A, B

C

C

E

C

D, F, G

D, F

H

I, J

4

6

2

8

7

4

4

4

4

3

2

6

8

4

10

10

6

6

6

6

4

4

8

16

6

24

13

8

        20

8

14

5

6

Develop a report that presents the activity schedule and expected project completion time for the warehouse expansion project. Include a project network in the report. In addition, take into consideration the following issues:

  1. R. C. Coleman's top management established a required 40-week completion time for the project. Can this completion time be achieved? Include probability information in your discussion. What recommendations do you have if the 40-week completion time is required?

  1. Suppose that management requests that activity times be shortened to provide an 80% chance of meeting the 40-week completion time. If the variance in the project completion time is the same as you found in part (1), how much should the expected project completion time be shortened to achieve the goal of an 80% chance of completion within 40 weeks?

  1. Using the expected activity times as the normal times and the following crashing information, determine the activity crashing decisions and revised activity schedule for the warehouse expansion project:

Activity

Crashed Activity Time (weeks)

Normal Cost ($)

Crashed Cost ($)

b

c

d

e

f

g

h

i

j

k

4

7

2

8

7

4

5

4

4

3

3

1,000

1,000

1,500

2,000

5,000

3,000

8,000

5,000

10,000

4,000

5,000

1,900

1,800

2,700

3,200

8,000

4,100

10,250

6,400

12,400

4,400

5,500

                       

Solutions

Expert Solution

The network diagram:

Activity

Optimistic

most probable

pessimist

A

4

6

8

B

6

8

16

C

2

4

6

D

8

10

24

E

7

10

13

F

4

6

8

G

4

6

20

H

4

6

8

I

4

6

14

J

3

4

5

K

2

4

6

Expected time = (a+4m+b)/6

Variance = [(b-a)/6]2

Let's derive expected time and variance for each activity as follows:

Expected time of activity A = (4+4*6 + 8)/6 = 36/6 = 6

Variance of activity A = ](8-4)/6]2 = (4/6)2 = 0.44

Activity

expected time (weeks) = (a + 4m+ b)/6

variance = [(b-a)/6]2

A

6

0.44

B

9

2.78

C

4

0.44

D

12

7.11

E

10

1

F

6

0.44

G

8

7.11

H

6

0.44

I

7

2.78

J

4

0.11

K

4

0.44

ES,LS,EF,LF,Slack :

activity

ES

LS

EF

LF

Slack

A

0

3

6

9

3

B

0

0

9

9

0

C

9

9

13

13

0

D

13

17

25

29

4

E

13

13

23

23

0

F

23

23

29

29

0

G

13

21

21

29

8

H

29

29

35

35

0

I

29

32

36

39

3

J

35

35

39

39

0

K

39

39

43

43

0

Slack = difference between LS & ES or LF & EF

?Activities with zero slack are the activities on critical path

Critical path = B + C+ E+ F+ H+J+K = 43 WEEKS

Variance of above critical path = 5.65

z-score = 40 - 43 / (5.65)1/2 = -1.26

Z score of -1.26 = 0.1038

We can conclude that RC Coleman has 10.4% of chance of completion in 40 weeks

2.

When probability is 80%, Z= 0.84

0.84 = 40 - X / 5.651/2

X = 38 weeks

if we want 80% of the project completion by 40 weeks, then the expected project time should be reduced to 38 weeks

3.

Weeks

Cost $

Activity

Normal time

Crash time

Normal cost

Crash cost

Time to be
crashed

Cost of crash

Cost of
crash per period

A

6

4

1,000.00

1,900.00

2

900.00

450.00

B

9

7

1,000.00

1,800.00

2

930.00

400.00

C

4

2

1,500.00

2,700.00

2

1,200.00

600.00

D

12

8

2,000.00

3,200.00

4

1,200.00

300.00

E

10

7

5,000.00

8,000.00

3

3,000.00

1,000.00

F

6

4

3,000.00

4,100.00

2

1,100.00

550.00

G

8

5

8,000.00

10,250.00

3

2,250.00

750.00

H

6

4

5,000.00

6,400.00

2

1,400.00

700.00

I

7

4

10,000.00

12,400.00

3

2,400.00

800.00

1

4

3

4,000.00

4,400.00

1

400.00

400.00

k

4

3

5,000.00

5,500.00

1

500.00

500.00

45,500.00

60,650.00

The total expected time to complete the project is 43 week and the chance of 80% completion is 38 weeks. Thus, the difference is 5 weeks and the project cannot be crashed more than 5 weeks, if it is crashed more than 5 weeks then it cannot be achieved.

Potential Path

Length

Crash J - 1 week

Crash B-2 weeks

Crash K- 1 week

Crash F-1 week

A-C-D-I-K

33

33

33

32

32

A-C-D-H-J-K

36

35

35

34

34

A-C-E-F-I-K

37

37

37

36

35

A-C-E-F-H-J-K

40

39

39

38

37

A-C-G-H-J-K

32

31

31

30

30

B-C-D-I-K

36

36

34

33

33

B-C-D-H-J-K

39

38

36

35

35

B-C-E-F-I-K

40

40

38

37

36

B-C-E-F-H-J-K

43

42

40

39

38

B-C-G-H-J-K

35

34

32

31

31

Cost

400

800

500

550

Total crashing cost

2250

Total crashing week

5 week

Revised schedule:

Potential Path

Length

A-C-D-I-K

32

A-C-D-H-J-K

34

A-C-E-F-I-K

35

A-C-E-F-H-J-K

37

A-C-G-H-J-K

30

B-C-D-I-K

33

B-C-D-H-J-K

35

B-C-E-F-I-K

36

B-C-E-F-H-J-K

38

B-C-G-H-J-K

31


Related Solutions

The R. R. Bean Company produces, packages, and distributes freeze-dried food for the camping and outdoor...
The R. R. Bean Company produces, packages, and distributes freeze-dried food for the camping and outdoor sportsman market. R. R. Bean is ready to introduce a new line of products based on a new drying technology that produces a higher quality, tastier food, so they want to discontinue their current line. The basic ingredients of the current line are dried fruit, dried meat and dried vegetables. There are two products in the current line: the "Weekender" and the "Expedition." In...
2. Airbiz Food Products produces a wide variety of food and related products. The? company's tomato-canning...
2. Airbiz Food Products produces a wide variety of food and related products. The? company's tomato-canning operation relies partly on tomatoes grown on Airbiz?'s own farms and partly on tomatoes bought from other growers. Airbiz?'s tomato farm is on the edge of? Sharpestown, a? fast-growing, medium-sized city. It produces 14 million pounds of tomatoes a year and employs 58 persons. The annual costs of tomatoes grown on this farm are as? follows: Variable production costs $605,000 Fixed production costs 1,250,000...
The Alpha Dog Company manufactures and distributes a variety of pet-related products. In response to customer...
The Alpha Dog Company manufactures and distributes a variety of pet-related products. In response to customer feedback relating to the fragile nature of many commercially available dog leashes, the company’s product development team has recently introduced a prototype of a new, virtually indestructible dog leash. The development of the prototype cost $250,000 in research and development costs. The product development team has presented their proposal to Adam Smith, the company’s president and CEO. Adam has asked you, as the chief...
ABSTRACT: The objective of this study was to test a variety of bush meat products sold...
ABSTRACT: The objective of this study was to test a variety of bush meat products sold by meat retailer. Police investigate the incident and seized the knife. There was a small piece of tissue adhering to the knife for further investigation. DNA was extracted from the meat sample and PCR done using Forward: L14841 (5'-AAAAAGCTTCCATCCAACATCTCAGCATGATGAAA-3') and Reverse: H15149 (5'-AAACTGCAGCCCCTCAGAATGATATTTGTCCTCA-3') primer. after that dna sequencing performed for identification of species. The resulted sequence aligned against Nucleotide blast and create phylogenetic tree...
Saputo Inc. produces, markets, and distributes a wide variety of products, including cheese, fluid milk, yogurt,...
Saputo Inc. produces, markets, and distributes a wide variety of products, including cheese, fluid milk, yogurt, dairy ingredients, and snack cakes. It is the largest dairy processor in Canada and serves customers in over 50 countries.    The following transactions occurred during a recent year. Amounts are in millions of dollars. a. Issued $30 in shares to investors (example). b. Purchased $149 of additional property, plant, and equipment for cash. c. Incurred $309 in selling expenses with two-thirds paid in...
WSR Inc. sells a variety of drink and food products including potato chips and sodas. The...
WSR Inc. sells a variety of drink and food products including potato chips and sodas. The segmented income statements for these two products are as follows: Sodas Chips Sales $800,000 $900,000 Variable expenses   200,000   315,000 Contribution margin 600,000 585,000 Traceable fixed expense   120,000   160,000 Segment margin $480,000 $425,000 WSR's management is considering a special advertising campaign that will run during a major sporting event. The advertising campaign is expected to cost $30,000 and only one product can be featured. In-house...
You are on a factory visit to a plant for food products. Rushing through the factory,...
You are on a factory visit to a plant for food products. Rushing through the factory, you hear that a vapor compression cycle with refrigerant HFC-134a as the working fluid is being used. You see that they use a throttle valve as part of the system and that one part of the cycle is running at 0.32 MPa and another part of the cycle is running at 1.6 MPa. If the compressor is 80% efficient and throttle, condenser, and evaporator...
Butter Quart Industries produces a variety of bottled food products at its various plants. At its...
Butter Quart Industries produces a variety of bottled food products at its various plants. At its Americus plant, it produces two products, peanut butter and apple butter. There are two scarce resources at this plant: packaging capacity and sterilization capacity. Both have a capacity of 40 hours per week. Production of 1000 jars of peanut butter requires 4 hours of sterilizer time and 5 hours of packaging time, whereas it takes 6 hours of sterilizer time and 4 hours of...
The experiment is: analyzing food products for vitamin C. "Determine the amount of vitamin C (ascorbic...
The experiment is: analyzing food products for vitamin C. "Determine the amount of vitamin C (ascorbic acid) in different food products by oxidation- reduction titrimetry." A student performed the experiment described in this module. She first standardized her DCP solution by preparing an ascorbic acid solution containing 46mg of reagent-grade ascorbic acid. Three 10.00mL samples of the ascorbic acid solution required an average of 25.7mL of titrant for the complete reaction. 1)calculate the mean molartity of the DCP solution. The...
Work out the products of the matrices E, R, R^2,R^3, A, B, C, D, and verify...
Work out the products of the matrices E, R, R^2,R^3, A, B, C, D, and verify that these products reproduce the multiplication table for the symmetries of the square, as expected. (Instead of computing all 64 products, compute “sufficiently many” products, and show that your computations suffice to determine all other products.)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT