In: Finance
Apple's Project | |
NPV ($) | 10,258 |
IRR (%) | 13 |
MIRR (%) | 10 |
PI | 1.5 |
Payback (Years) | 3 |
Discounted Payback (years) | 3.5 |
Apple's cost of capital is 9%. Its critical payback and discounted payback periods are 2 and 2.5. Should the project be accepted or not.
NPV - (Accept or Do Not Accept)
IRR - (Accept or Do Not Accept)
MIRR - (Accept or Do Not Accept)
PI - (Accept or Do Not Accept)
Payback - (Accept or Do Not Accept)
Discounted Payback - (Accept or Do Not Accept)
NPV - (Accept or Do Not Accept)
If NPV>0 Accept the project
NPV = 10,258
NPV > 0
NPV - Accept
IRR - (Accept or Do Not Accept)
If IRR> Cost of Capital Accept the project
IRR Value = 13%
IRR (13%) > Cost of Capital(9%)
IRR - Accept
MIRR - (Accept or Do Not Accept)
If MIRR> Cost of Capital Accept theproject
MIRR = 10%
IRR (10%) > Cost of Capital(9%)
MIRR - Accept
PI - (Accept or Do Not Accept)
If Profitability Index PI > 01 Accept the Project
PI>01
PI - Accept
Payback - (Accept or Do Not Accept)
IF Payback Period < Required Payback Accept the Project
Payback Period = 3
Required Payback Accept the Project = 02
Payback Period 3 > Required Payback Accept the Project (02)
Payback Do Not Accept
Discounted Payback - (Accept or Do Not Accept)
IF Discounted Payback Period < Discounted Required Payback Accept the Project
Discounted Payback Period = 3.5
Discounted Required Payback Accept the Project = 2.5
Discounted Payback Period 3.5 > Discounted Required Payback Accept the Project 2.5
Discounted Payback Do Not Accept