Question

In: Statistics and Probability

A chemical plant is due for a major overhaul and the manager has to make an...

A chemical plant is due for a major overhaul and the manager has to make an assessment of a number of uncertainties associated with the project. These include the time the overhaul will take to complete (after 35 days the losses of production caused by the overhaul could have serious consequences for the company) and the risks that there will be leakage of dangerous chemicals into local watercourses during the cleaning process. The following extracts have been taken from the manager’s draft report which details plans for the overhaul.

(i)‘I assessed the most likely duration of the overhaul to be 30 days. I then tried to take an optimistic view and assumed that, if all goes well, we could finish the work 5 days earlier than this (i.e., in 25 days). I then took a pessimistic perspective and estimated that the longest the project will take is 34 days. I am therefore certain that we should complete the overhaul within 35 days.’

(ii)‘Essentially the overhaul will be split into eight independent phases. I think the chances of us completing each phase without a pollution problem are high, say 90%. Overall, I therefore estimate that we have almost a 90% chance of avoiding a pollution problem during the project.’

  • Please make an assessment of a number of uncertainties associated with the project.

Solutions

Expert Solution

SOLUTION:

i.Here we are given the following :

Most likely duration of over haul = m = 30 days

Optimistic View of duration of over haul = o = 25 days

Pessimistic View of duration of over haul = p = 34 days

Expected Time of completion = E = (o+4m+p)/6 = (25+4*30+34)/6=179/6=29.83 days

Variance here is given as V = square of ((p-o)/6) = square of (9/6) = 2.25

Standard deviation is given as = S = square root of V = square root of 2.25 = 1.5

Now number of standard deviations the due date or target date lies from expected time of completion = Z = (Due date - E)/S = (35-29.83)/1.5 = 3.446

For a Z score of 3.446 probability of over haul getting completed under 35 days is 99.98% so uncertainty is 100-99.97=0.02%.

ii Now considering 90% chances of avoiding a pollution problem let us calculate what should be the due date for completion .

Now Z value closest to 90% probability is 1.282 .

Now formula foe due date = Z*S+E = 1.282*1.5+29.83= 31.753 days

So line haul should be completed before 31.753 days to have 90% chance of avoiding a pollution problem.


Related Solutions

on 1 July 2004,Experimentor opened a chemical reprocessing plant. the plant was due to be active...
on 1 July 2004,Experimentor opened a chemical reprocessing plant. the plant was due to be active for five years until 30 June 2009, when it would be decommissioned. At 1 July, 2004, the costs of decommissioning the plant were estimated to be $4million in 5 years time. the company considers that a discount rate of 12% is approprite for the calculation of a present value, and the discount factor at 12% for year 5 is 0.567. what is the total...
Summary article "Swaps rules due for overhaul in bid to boost liquidity" and analysis it
Summary article "Swaps rules due for overhaul in bid to boost liquidity" and analysis it
The Government of Toan recently announced the approval of a major tax and spending overhaul that...
The Government of Toan recently announced the approval of a major tax and spending overhaul that aims to (1) reduce the burden on its government by requiring 85% of its population to live in one of three specially designated cities, (2) completely eliminate any and all taxes on corporations for five years, (3) offer a substantial reduction to 0.5% tax rate on capital gains by investors (prior rate was 35%), and (4) elimination of government spending programs such as social...
The Tax Cuts and Jobs Act of 2017 is a major overhaul of the tax codes...
The Tax Cuts and Jobs Act of 2017 is a major overhaul of the tax codes in nearly three decades: it has generated a lot of debates on its potential impacts on economic growth, budget and sustainability, and equality and fairness etc. For our purpose, focus your discussion on the corporate side: What would be possible impacts of some of the specific provisions on the corporate FCF, WACC, and Valuation? What would be the possible impacts of some of the...
A major overhaul of the Federal Tax structure was enacted at the end of 2017, effective...
A major overhaul of the Federal Tax structure was enacted at the end of 2017, effective beginning with the 2018 tax year. This assignment consists of calculations to gauge effects on situations as described. In all cases, for this assignment, assume that the tax being calculated is for a “Married couple filing jointly” who do not itemize deductions, and have no other additions, subtractions, or any tax situations not specifically stated. Complete the table below, finding the difference between the...
URGENTLY NEEDED A process plant is to be designed to make 65 kg/d of a chemical...
URGENTLY NEEDED A process plant is to be designed to make 65 kg/d of a chemical product selling at $200/kg. The operating time will be 300 day/year. Investments: Fixed capital investment is estimated to be $6×106 which is 75% of the total capital investment. Expenses: The annual production cost (not including depreciation) is estimated to be $1.2×106 /year. For depreciation charges, the straight line method can be used over ten years as expected life of the plant. Tax, MARR, and...
Major overhaul expenses of $3000 each are anticipated for a large piece of equipment. The expenses...
Major overhaul expenses of $3000 each are anticipated for a large piece of equipment. The expenses will occur at EOY four and will continue every three years thereafter up to and including year 13. If the interest rate is 6% per year, What is the present equivalent of the overhaul expenses at time 0? What is an annual equivalent expense during only years 5–13?
SW Company, a chemical firm, has developed an inexpensive chemical specialty item, and Iskandar, the manager...
SW Company, a chemical firm, has developed an inexpensive chemical specialty item, and Iskandar, the manager of the company, hopes it will find a huge market as a household product. Iskandar wants to package this product in one-gallon and two-gallon sizes. A number of container materials would appear to be practical – glass, aluminium, treated paper, steel, and various types of plastic. A young engineer who Iskandar hired recently and assigned to the packaging department has done a container-disposal study...
Major car manufacturers make use of computer simulations to experiment with possible plant layouts. The simulations...
Major car manufacturers make use of computer simulations to experiment with possible plant layouts. The simulations are designed to reflect stochastic effects such as different demand patterns, chance variations in processing times and breakdowns. Hence the results of running a simulation to calculate shifts’ production rates need to be analysed using appropriate statistical methods. Often these computer simulations are quite complex with quite long runtimes, and hence there is an interest in using as few runs of the simulation as...
The world has experienced a major crisis due to the rapid spread of the Coronavirus: •...
The world has experienced a major crisis due to the rapid spread of the Coronavirus: • What are the effects of this crisis on the image of China, The United States, and Europe? • What is the role of international public relations in changing of the image after the end of the virus? And how?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT