In: Accounting
Sun Systems Ltd. is considering installing a new heating system in its factory to provide heating and power.
Details are as follows:
The existing heating system will cost £8,000 to remove, and has no value. If retained, the existing heating system has an expected life of a further 5 years.
The new heating system will cost £57,000 including installation expenses of £2,800.
The current heating system costs £22,000 per year in energy, £8,000 per year in maintenance and £2,000 per year in depreciation.
The new heating system would cost £12,000 per year in energy, cost nothing to maintain in the first 2 years (as it would be under guarantee) and £3,000 per year for the remaining life.
The new heating would be depreciated in the accounts on a straight line basis over the life of 5 years. There is no expected residual value.
At the end of 5 year period, both old and new heating systems would have the same cost of removal.
The company’s cost of capital is 10%.
All annual costs can be assumed to occur in arrears.
Mikey Limited uses Target costing when developing new products. A new product is being considered which has the following costs and revenue information:
Sales: the demand is expected to average 5,000 units per month at a selling price of £7.00 per unit
Materials: the product requires 0.5 kg of material T for each unit
Labour: each unit requires 6 minutes of labour at £14 per hour
Overheads: the product would be manufactured in a separate factory, with total fixed production overheads of £10,000 per month
Profit :the gross margin required is at least 25%
a. Net Present Value for new healing system
0th year (out flow) | 1st year (out flow) | 2nd year (out flow) | 3rd year (out flow) | 4th year (out flow) | 5th year ( out flow) | |
removal cost for existing heating system | 8000 | |||||
cost for new heating system | 57000 | |||||
cost for energy | 12000 | 12000 | 12000 | 12000 | 12000 | |
cost for maintenence | 3000 | 3000 | 3000 | |||
cost for removal of new healing system | 8000 | |||||
total | 65000 | 12000 | 12000 | 15000 | 15000 | 23000 |
NPV = 65000 + 10909 + 9917 + 11270 + 10245 + 14281 = 135903
NPV for old heating system
1st year (out flow) | 2nd year(out flow) | 3rd year ( out flow) | 4th year (out flow) |
5th year (out flow) |
|
cost for energy | 22000 | 22000 | 22000 | 22000 | 22000 |
cost for maintenence | 8000 | 8000 | 8000 | 8000 | 8000 |
cost for removal | 8000 | ||||
total | 30000 | 30000 | 30000 | 30000 | 38000 |
NPV =27273 + 24793 + 22593 + 20490 + 23595 = 118744
Its better to use existing heating system instead of instaling new heating system. because npv of new heating system is greater than existing heating system.. so the total cost of new heating system is higher than existing.
b. Maximum cost per kilo for material T which company ready to pay is
Selling price = 5000 untis * 7 /unit = 35000
material = .05 * 5000 * cost/ kilo = 2500 * cost/kilo
Labour = 14 for 1 hour.. 6 minutes required. so for 6 minutes = 14/60 = .233.
.233*6 = 1.398
5000*.233*6 = 6990
Fixed overhead = 10000
gross profit margin = 25%
cost for material per kilo =
selling price - 35000
material -
Labour - 6990
Over head - 10000
gross profit - 8750 (35000*25/100)
so. 35000 - 6990- 10000 - 8750 = 9260
material cost = 9260, cost/kilo = 9260/2500 = 3.704
c. Standard costing is best suited activities within service organisation but it can be applied to activities within service organisation where output can be measured and there are clearly defined input / output relationships.