In: Operations Management
Can i get an example of PERT schedule and Activity On Node (AON) with at least 6 activities for contract negotiation project.
let me consider contract negotiation project that includes various activities with duration
Project- Contract Negotiation Project | |
Activity | Activities description |
A | Identification of the issues |
B | search for various information related to various issues |
C | listing of various issues under category |
D | Review all the identied issues and their existance |
E | Review all the related information |
F | Build agenda for meeting |
G | be prepared to Negotiate |
PERT Diagram based on Activity on Node:
Activity | Days | Predecessor |
A | 15 | None |
B | 10 | None |
C | 15 | None |
D | 10 | A |
E | 12 | B |
F | 15 | C |
G | 12 | D,E |
Path | Duration | Duration formula |
Start - 1-4-5- End | 37 | =15+10+12 |
Start - 2-4-5- End | 34 | =10+12+12 |
Start -3-5- End | 30 | =15+15 |
Now I will prepare AON or activity on Node diagram for the above case of contract Negotiation project
here, AON or activity on Node diagram is prepared using forward and backward path method.
Conclusion:
Here, critical path is Start - A-D-G-End and project will take at least 37 days time to complete