Question

In: Operations Management

Universal Technologies, Inc. has identified two qualified vendors with the capability to supply some of its...

Universal Technologies, Inc. has identified two qualified vendors with the capability to supply some of its electronic components. For the coming year, Universal has estimated its volume requirements for these components and obtained price-break schedules from each vendor. (These are summarized as “all-units” discounts in the table below.) Universal’s engineers have also estimated each vendor’s maximum capacity for producing these components, based on available information about equipment in use and labor policies in effect. Finally, because of its limited history with Vendor A, Universal has adopted a policy that permits no more than 60% of its total unit purchases on these components to come from Vendor A.

Vendor A

Vendor B

Product

Requirement

Unit price

Volume required

Unit price

Volume required

1

500

$225

0–250

$224

0–300

$220

250–500

$214

300–500

2

1000

$124

0–600

$120

0–1000

$115

600–1000

(no discount)

3

2500

$60

0–1000

$54

0–1500

$56*

1000–2000

$52

1500–2500

$51

2000–2500

Total capacity (units)

2500

2000

*For example, if 1400 units are purchased from Vendor A, they cost $56 each, for a total of $78,400.

What is the minimum-cost purchase plan for Universal?

Solutions

Expert Solution

Let A1 & B1 be the number of Product 1 items purchased from Vendor 1 & Vendor 2 respectively.

Let A2 & B2 be the number of Product 2 items purchased from Vendor 1 & Vendor 2 respectively.

Let A3 & B3 be the number of Product 3 items purchased from Vendor 1 & Vendor 2 respectively.

Let X1 & Y1 be the Binary variable determining if the Product 1 purchased from Vendor 1 & Vendor 2 exceeds 250 & 300 respectively.

Let X2 be the Binary variable determining if the Product 2 purchased from Vendor 1 exceeds 600.

Let X3, X4 & Y3 be the Binary variable determining if the Product 1 purchased from Vendor 1 & Vendor 2 exceeds 1000, 2000 & 1500 respectively.

Our Objective is to minimize the cost in which the purchase requirements are met. Thus our objective function is-

Min(225*A1-5*X1*(A1-250) + 224*B1-10*Y1*(B1-300) + 124*A2-9*X2*(A2-600) + 120*B2 + 60*A3-4*X3*(A3-1000)-5*X4*(A3-2000) + 54*B3-2*Y3*(B3-1500)

Constraints-

From Demand Side-

A1+B1 = 500

A2+B2 = 1000

A3+B3 = 2500

From Supply Side-

A1+A2+A3 <= 2800

B1+B2+B3 <= 2400

The Solver Solution is as shown-

The Total Cost considering all discounts = 372450

Total Price without any discount = 500*225+1000*120+1100*60+1400*54 = 374100

Percentage of total cost this increase represents = (374100-372450)/372450 = 0.00443 = 0.443%


Related Solutions

What are some of the challenges identified by the World Health Organization (WHO) in bringing universal...
What are some of the challenges identified by the World Health Organization (WHO) in bringing universal health care to countries around the world?
Bumble’s Bees, Inc., has identified the following two mutually exclusive projects: Bumble’s Bees, Inc., has identified...
Bumble’s Bees, Inc., has identified the following two mutually exclusive projects: Bumble’s Bees, Inc., has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 -17,000 -17,000 1 8,000 2,000 2 7,000 5,000 3 5,000 9,000 4 3,000 9,500 Calculate the Internal Rate of Return (IRR) for each of the project using Trial and Error method. Apply the IRR decisionrule, which project should the company accept? If the required return is 11 percent, evaluate the...
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year:...
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year: Total overhead budgeted = $200,000 Total direct labor hours budgeted = 2,000 hours Actual direct labor hours worked on Job 21 = 100 Actual direct materials = $5,000 total Actual direct labor = $3,000 total Actual units completed = 100 The totoal cost of Job 21 is: a. $ 22,500 b. $ 16,000 c. $ 18,000 d. $ 19,900 The Total Cost of Job...
Dexcon Technologies, Inc., is evaluating two alternatives to produce its new plastic filament with tribological (i.e.,...
Dexcon Technologies, Inc., is evaluating two alternatives to produce its new plastic filament with tribological (i.e., low friction) properties for creating custom bearings for 3-D printers. The estimates associated with each alternative are shown below. Using a MARR of 11% per year, which alternative has the lower present worth? Method DDM LS First Cost $-240,000 $-420,000 M&O Cost, per Year $-50,000 $-40,000 Salvage Value $6,000 $17,000 Life 2 years 4 years The present worth for the DDM method is $_____....
The following information has been extracted from Universal Inc.’s financial records for its first year of...
The following information has been extracted from Universal Inc.’s financial records for its first year of operations: Units produced                         10,000             Beg. Finished Goods Inventory          0 Units sold                                     7,000             Sales Price per Unit                      $100 Variable costs per unit:                                   Fixed costs for year: Direct Materials          $8                    Overhead                    $70,000 Direct Labor                9                    Marketing & Admin   30,000 Overhead                    3 Selling                        4 per unit sold Required: 1. Compute the manufacturing cost of one unit using the Variable Costing method. 2. Compute the manufacturing cost of...
Garage, Inc., has identified the following two mutually exclusive projects. The required rate of return on...
Garage, Inc., has identified the following two mutually exclusive projects. The required rate of return on both projects is 12%. Which project should the company choose and why? Year Cash Flow (A) Cash Flow (B) 0 -$29,000 -$29,000 1 14,400 4,400 2 12,300 9,800 3 9,200 18,500 4 8,100 16,800 A: Choose A because project A has a higher IRR B: Choose B because project B has a higher NPV C: Choose B because project B has shorter payback period...
The director of capital budgeting for Giant Inc. has identified two mutually exclusive projects, L and...
The director of capital budgeting for Giant Inc. has identified two mutually exclusive projects, L and S, with the following expected net cash flows: Expected Net Cash Flows Year Project L Project S 0 ($100) ($100) 1 10 70 2 60 50 3 80 20 Both projects have a cost of capital of 12 percent. What is Project S's MIRR? What is Project L's MIRR?
Coleman Technologies Inc. Cost of Capital Coleman Technologies is considering a major expansion program that has...
Coleman Technologies Inc. Cost of Capital Coleman Technologies is considering a major expansion program that has been proposed by the company’s information technology group. Before proceeding with the expansion, the company must estimate its cost of capital. Assume that you are an assistant to Jerry Lehman, the financial vice president. Your first task is to estimate Coleman’s cost of capital. Lehman has provided you with the following data, which he believes may be relevant to your task: 1. The firm’s...
Garage, Inc., has identified the following two mutually exclusive projects:     Year Cash Flow (A) Cash...
Garage, Inc., has identified the following two mutually exclusive projects:     Year Cash Flow (A) Cash Flow (B) 0 –$ 29,500 –$ 29,500 1 14,900 4,550 2 12,800 10,050 3 9,450 15,700 4 5,350 17,300    a-1 What is the IRR for each of these projects? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)    IRR   Project A %   Project B %    a-2 Using the IRR decision rule, which...
Respond to the following: Parkallen Inc. has identified the following two mutually exclusive projects: Year Cash...
Respond to the following: Parkallen Inc. has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 -$29,000 -$29,000 1 14,400 4,300 2 12,300 9,800 3 9,200 15,200 4 5,100 16,800 What is the IRR for each of these projects? Using the IRR decision rule, which project should the company accept? Is this decision necessarily correct? If the required return is 11%, what is the NPV for each of these projects? Which project will the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT